In the Matter of Permit

New Jersey Superior Court Appellate Division·Decided November 21, 2023·No. A-1897-21/A-2270-21·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-1897-21

A-2270-21

IN THE MATTER OF PERMIT NUMBER 0807-21-0002.1 LUP210001 ISSUED BY THE NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION TO DELAWARE RIVER PARTNERS, LLC.

IN THE MATTER OF PERMIT NUMBER 0807-21-0002.1 LUP210002 ISSUED BY THE NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION TO DELAWARE RIVER PARTNERS, LLC.

Submitted October 24, 2023 – Decided November 21, 2023 Before Judges Gooden Brown and Natali.

On appeal from the New Jersey Department of Environmental Protection.

Kacy C. Manahan, attorney for appellants Delaware Riverkeeper Network and Maya van Rossum, the

Delaware Riverkeeper (Kacy C. Manahan, of counsel and on the briefs).

Matthew J. Platkin, Attorney General, attorney for respondent New Jersey Department of Environmental Protection (Melissa H. Raksa, Assistant Attorney General, of counsel; Kathrine M. Hunt and Kristina Miles, Deputy Attorneys General, on the briefs).

Manko, Gold, Katcher & Fox, LLP, attorneys for respondent Delaware River Partners LLC (Kathleen B.

Campbell and Michael Dillon, on the briefs).

PER CURIAM In these consolidated appeals, the Delaware Riverkeeper Network and Maya van Rossum challenge the Department of Environmental Protection's (DEP) issuance of a Flood Hazard Area Permit, a Waterfront Development Permit, a Coastal Wetlands Permit, a Freshwater Wetlands Permit, and a Water Quality Certificate (the Permits) to Delaware River Partners, LLC (DRP). Those Permits, issued on December 30, 2021 and February 25, 2022, authorize DRP to construct a new railway loop (the Loop) to aid in the delivery of liquid energy products, primarily liquefied natural gas (LNG), to the Gibbstown Logistics Center (GLC), a facility it built on the Delaware River.

Appellants contend DEP acted arbitrarily, capriciously, and unreasonably in issuing the Permits for the Loop. For the reasons that follow, we disagree with all these arguments and affirm.

A-1897-21

I.

In light of the numerous issues raised by these appeals, and the necessary consideration of the complex state and federal environmental statutes and regulations at issue, we detail the facts with a greater degree of granularity than ordinary.

In 2016, DRP purchased a portion of property situated on the Delaware River which had previously been used by E.I. du Pont de Nemours and Company (DuPont) as an industrial site known as the DuPont Repauno Works. The site is located near residential areas in Gibbstown, and during its ownership by DuPont, hosted such operations as explosives manufacturing, industrial diamond manufacturing, and storage and shipment of ammonia.

From 1951 to 1986, Atlantic City Electric also operated a power plant on the property and used a pier for the transfer of coal. Railway lines to support operations on the site were constructed in the late 1800s and extended around 1940; they were abandoned "sometime after 1971," and part of the former railway was repurposed as an unpaved roadway. Chemours Co., LLC, a successor to DuPont, is currently engaged in remediation of the historic contamination of the upland areas of the site, under DEP's supervision.

A-1897-21

After purchasing approximately 371 acres of the 1600-acre area, DRP proposed building the GLC, a "multi-use deep-water port and logistics center" intended to replace structures constructed by DuPont in the early 1900s. DRP intended for the GLC to receive and load cargo from and to ships, such as automobiles, other "roll-on/roll-off" cargo, and bulk liquid products including "liquid gases and energy liquid products." On April 10, 2017, DEP issued individual Waterfront Development, Flood Hazard, Coastal Wetland, and Freshwater Wetlands permits to DRP for the GLC's construction. DEP determined that the construction of the GLC satisfied all applicable siting conditions and environmental standards under the Energy Facility Use rule, N.J.A.C. 7:7-15.4, and the Stormwater Management rules, N.J.A.C. 7:8-1.1 to - 6.3.

The 2017 permits authorized DRP to dredge 460,000 cubic yards of sediment within a 29-acre area of the Delaware River in order to accommodate a 750-foot-long berth for large vessels and provide access to the structure from the river's navigational channel. The permits also allowed the permanent disturbance of 4.603 acres of freshwater wetlands; DEP included conditions in the permits intended to protect animal habitats and endangered species in the area including sturgeon, bald eagles, and ospreys, and to mitigate wetlands

A-1897-21

losses. DRP was also required to comply with a stormwater maintenance plan it had developed for the site. The construction authorized by the 2017 permits is known as the "Dock 1 and Marine Terminal" project (Dock 1/GLC). Neither appellants nor any other party challenged the issuance of these permits.

In 2018, DRP applied for a modification to the Dock 1/GLC permits to allow for changes to the proposed footprint and location of the marine terminal, which would now include "a bulk liquid storage and handling facility for the transfer of [LNG] and other materials." In November of that year, DEP authorized the modification, conditioned upon DRP's compliance with all Toxic Catastrophe Prevention Act Program rules under N.J.A.C. 7:31-1.1 to -11.5. The modified permits were also unchallenged. DRP completed construction of Dock 1 in December 2018, and of a rail transloading rack for liquified petroleum gas in October 2020.

On March 14, 2019, DRP applied to DEP for a new individual Waterfront Development permit, to construct a second dock that would accommodate vessels to export liquid energy products including LNG (Dock 2). Following a public comment period during which appellants sent opposing comments, DEP issued the permit on September 5, 2019. The Dock 2 permit authorized the dredging of 665,000 cubic yards of sediment to provide access by vessels to the

A-1897-21

new dock. It contained conditions intended to protect water quality, endangered fish and birds, fisheries, and aquatic vegetation during construction of the dock.

Appellants appealed the issuance of the Dock 2 permit, and we affirmed DEP's actions, finding that the agency did not act arbitrarily, capriciously, or unreasonably. In re Challenge of Del. Riverkeeper Network, No. A-709-19 (June 23, 2021) (slip op. at 3). In doing so, we specifically rejected appellants' argument that Dock 2 should have been reviewed by DEP as a separate "energy facility" under N.J.A.C. 7:7-15.4, finding that the new dock was "merely an additional set of two berths" and would not "store," "vaporize," or "receive" LNG "for transmission by pipeline" as that regulation defines such a facility. Id. at 8, 21-22.

We also found that DEP had fully considered the potential impacts to endangered species when issuing both the Dock 2 and original GLC permits. Id. at 25-26. The court further rejected appellants' argument that DEP should have required DRP to obtain a new Industrial Stormwater permit for Dock 2. Id. at 34-37. We found that DRP had shown compliance with the Stormwater Management rules as part of the GLC permitting process by designing a stormwater management system for the facility, and that Dock 2 was not in itself a "major development" requiring any further consideration of those rules under

A-1897-21

Free access — add to your briefcase to read the full text and ask questions with AI

In the Matter of Permit, (N.J. Ct. App. 2023).

In the Matter of Permit (In the Matter of Permit) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Boardwalk Regency Casino License Appl.
434 A.2d 1111 (New Jersey Superior Court App Division, 1981)
In Re Freshwater Wetlands General Permit
878 A.2d 22 (New Jersey Superior Court App Division, 2005)
In Re Adopted Amendments To
839 A.2d 60 (New Jersey Superior Court App Division, 2003)
Barone v. D. of Human Serv., Div. of Med. Asst.
509 A.2d 786 (New Jersey Superior Court App Division, 1986)
American Cyanamid v. D. of Envir. Prot.
555 A.2d 684 (New Jersey Superior Court App Division, 1989)
In Re Herrmann
926 A.2d 350 (Supreme Court of New Jersey, 2007)
In Re Carter
924 A.2d 525 (Supreme Court of New Jersey, 2007)
Zrb, LLC v. Nj Dept. of Environmental Protection
959 A.2d 866 (New Jersey Superior Court App Division, 2008)
Matter of Egg Harbor Associates (Bayshore Centre)
464 A.2d 1115 (Supreme Court of New Jersey, 1983)
In Re Election Law Enforcement Commission Advisory Opinion No. 01-2008
989 A.2d 1254 (Supreme Court of New Jersey, 2010)
Circus Liquors, Inc. v. Governing Body of Middletown Township
970 A.2d 347 (Supreme Court of New Jersey, 2009)
In Re Freshwater Wetlands Protection Act Rules
852 A.2d 167 (Supreme Court of New Jersey, 2004)
Nj Chapter of Naiop v. Dept. of Environmental Protection
574 A.2d 514 (New Jersey Superior Court App Division, 1990)
US Bank, N.A. v. Hough
42 A.3d 870 (Supreme Court of New Jersey, 2012)
In Re Protest of Coastal Permit
807 A.2d 198 (New Jersey Superior Court App Division, 2002)
In Re Freshwater Wetlands
860 A.2d 450 (New Jersey Superior Court App Division, 2004)
Messick v. Board of Review
21 A.3d 631 (New Jersey Superior Court App Division, 2011)
State in the Interest of K.O., a Minor (070406)
85 A.3d 938 (Supreme Court of New Jersey, 2014)