I-291 Why? Association v. Joseph B. Burns, as Connecticut Commissioner of Transportation

517 F.2d 1077, 5 Envtl. L. Rep. (Envtl. Law Inst.) 20430, 7 ERC (BNA) 2147, 1975 U.S. App. LEXIS 14436
CourtCourt of Appeals for the Second Circuit
DecidedMay 30, 1975
Docket478, Docket 74-1545
StatusPublished
Cited by39 cases

This text of 517 F.2d 1077 (I-291 Why? Association v. Joseph B. Burns, as Connecticut Commissioner of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
I-291 Why? Association v. Joseph B. Burns, as Connecticut Commissioner of Transportation, 517 F.2d 1077, 5 Envtl. L. Rep. (Envtl. Law Inst.) 20430, 7 ERC (BNA) 2147, 1975 U.S. App. LEXIS 14436 (2d Cir. 1975).

Opinion

PER CURIAM:

This is an appeal by state highway officials 1 from a grant of plaintiff’s motion for a preliminary injunction halting construction of about eight miles of highway 1 — 291 southwest of Hartford. 2 *1079 Plaintiff is an unincorporated association of residents of the proposed highway’s corridor.

Plaintiff has filed a complaint seeking injunctive and declaratory relief based on alleged breaches of four federal statutes by defendants. The motion for the preliminary injunction was premised on defendants’ alleged breach of duties imposed by the National Environmental Policy Act of 1969, NEPA, 42 U.S.C. § 4331-32 (1970). 3 Plaintiff claims 1) *1080 that construction of the highway will violate the substantive mandate of § 101(b)(3), 42 U.S.C. § 4331(b)(3) of NEPA to “attain the widest range of beneficial uses of the environment without degradation, risk to health or safety, or other undesirable and unintended consequences,” by creating a high level of air pollution and noise; 2) that defendants failed to act in accordance with the “continuing responsibility” placed on federal agencies by NEPA insofar as air and noise pollution data obtained by defendants after approval of the original Environmental Impact Statement (EIS) were not incorporated into a supplemental EIS which would have been circulated for comment and approval in appropriate federal channels; 3) that the original EIS was not prepared in accordance with applicable Federal Highway Administration (FHWA) guidelines; 4) that the EIS lacked the adequacy and good faith preparation required by NEPA and was not prepared “by the responsible official” as directed by NEPA since the EIS was prepared by the state officials and not by officials in the Federal Highway Administration; and 5) that a breach of “continuing responsibility” is demonstrated by the failure to file a supplemental EIS once it was learned that the southwest quadrant of the circumferential beltway was the only portion to be constructed in the foreseeable future.

We affirm the grant of the preliminary injunction substantially on the bases set out in the District Court opinion 4 and summarized below.

The beltway in question has been in a variety of state planning stages for several years. In order to have the construction of 1 — 291 occur as part of the federal interstate highway system with 90% of the cost to be borne by the federal government, Connecticut officials submitted design study reports on the beltway along with a request for design approval to the FHWA in August 1970 and in December 1970. In early February 1971, the FHWA Division Engineer notified the Commissioner of the Connecticut Department of Transportation (CONNDOT) that an EIS would be required for 1 — 291. A CONNDOT official prepared a rough draft of an EIS “off the top of his head.” This draft was reviewed by an FHWA employee at the division level 5 in February 1971 and CONNDOT personnel who had frequent contact with FHWA personnel then prepared a preliminary draft EIS which was filed in June 1971 and circulated to various federal agencies, not including the Environmental Protection Agency. When comments had been received and after a multidisciplinary review of the preliminary draft, the final EIS was written by CONNDOT personnel who maintained contact with the FHWA division office. The final EIS was submitted to the FHWA division office in printed form in February 1972. Four days later the division office forwarded the EIS to the regional office recommending acceptance which was granted without alteration or comment.

The EIS was filed with the Council on Environmental Quality on September 18, 1972, and on October 4, 1972 public notice by newspaper was given that the EIS was available for inspection for the next thirty days. When thirty days had expired the FHWA Division Engineer for Connecticut granted formal design approval for 1 — 291 on November 6, 1972. The Division Engineer also requested CONNDOT to give further consideration to the noise and air quality impacts of 1 — 291 to reflect advances in evaluation techniques. The 28-page EIS dealt with *1081 noise pollution in a 2-page treatment devoid of any data or other objective support for conclusory statements. Air pollution was treated in one short paragraph again with mere conclusory statements that the impact of the highway was insignificant.

Pursuant to the Division Engineer’s request, CONNDOT submitted a noise impact evaluation report in March 1973 noting one area of open space as “noise sensitive” and recommending a noise .barrier mound to be constructed at that location. An air quality study performed by consultants was sent by CONNDOT to the FHWA Division Engineer on June 8, 1973 indicating that projected 1990 traffic on 1 — 291 would under “worst case” meteorological and traffic conditions cause the hydrocarbon levels to exceed EPA standards at three points. These two studies were not made “supplemental EIS’s” and were not circulated or made public. A week later the Division Engineer granted “plans, specification and estimates” approval for the first two miles of 1 — 291. Pursuant to this approval, carrying a federal commitment to fund 90% of the construction costs, bids were solicited and a contract was awarded in September. The contractor began clearing the site in late September. On October 12, the FHWA Division Engineer notified CONNDOT that the air quality study with its conclusions that 1 — 291 would not cause significant air quality problems was accepted without reservation. Plaintiff retained counsel in late October 1973. Within a few days counsel reviewed the CONNDOT and- FHWA files and when the air and noise quality studies and other documentary material as to the decision-making in this case became known to plaintiff, plaintiff filed suit on November 12, 1973.

Defendants below asserted laches as an affirmative defense. The District Court analyzed fully the factual setting in making its equitable determination that laches did not bar plaintiff’s action. We agree with that analysis and balancing of considerations and with the conclusion that absent a showing of great progress during the alleged delay and in view of the non-public nature of the noise and air quality studies which squarely indicated the inadequacy of the EIS in respect to these elements, laches is not a bar to this suit. See also Steubing v. Brinegar, 511 F.2d 489 (2d Cir. 1975).

We also agree with the court below that the amount of federal contact in the preparation of the 1 — 291 EIS does not comport with the standard of primary and non-delegable responsibility placed on the federal agency, the FHWA, by NEPA as- that standard has been articulated in Greene County Planning Board v. FPC, 455 F.2d 412 (2d Cir.), cert. denied, 409 U.S. 849, 93 S.Ct. 56, 34 L.Ed.2d 90 (1972); Conservation Society of Southern Vermont v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of South Pasadena v. Slater
56 F. Supp. 2d 1106 (C.D. California, 1999)
County of Westchester v. Town of Greenwich, Conn.
793 F. Supp. 1195 (S.D. New York, 1992)
Stow v. US ON BEHALF OF SOIL CONSERVATION SERV.
696 F. Supp. 857 (W.D. New York, 1988)
Milwaukee Brewers v. DH&SS
387 N.W.2d 245 (Wisconsin Supreme Court, 1986)
Club v. Wisconsin Department of Health & Social Services
387 N.W.2d 245 (Wisconsin Supreme Court, 1986)
Association Concerned About Tomorrow, Inc. v. Dole
610 F. Supp. 1101 (N.D. Texas, 1985)
Adler v. Education Department of New York
760 F.2d 454 (Second Circuit, 1985)
Adler v. Education Department of State of New York
760 F.2d 454 (Second Circuit, 1985)
Walt Disney Productions v. Basmajian
600 F. Supp. 439 (S.D. New York, 1984)
National Wildlife Federation v. Marsh
568 F. Supp. 985 (District of Columbia, 1983)
Sierra Club v. United States Army Corps of Engineers
701 F.2d 1011 (Second Circuit, 1983)
Action for Rational Transit v. West Side Highway Project
536 F. Supp. 1225 (S.D. New York, 1982)
Sutter Sensible Planning, Inc. v. Board of Supervisors
122 Cal. App. 3d 813 (California Court of Appeal, 1981)
National Wildlife Federation v. Lewis
519 F. Supp. 523 (D. Connecticut, 1981)
Manchester Environmental Coalition v. Stockton
441 A.2d 68 (Supreme Court of Connecticut, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
517 F.2d 1077, 5 Envtl. L. Rep. (Envtl. Law Inst.) 20430, 7 ERC (BNA) 2147, 1975 U.S. App. LEXIS 14436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/i-291-why-association-v-joseph-b-burns-as-connecticut-commissioner-of-ca2-1975.