Hussein v. City of Perrysburg

617 F.3d 828, 2010 U.S. App. LEXIS 17364, 2010 WL 3271727
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 20, 2010
Docket09-4054
StatusPublished
Cited by13 cases

This text of 617 F.3d 828 (Hussein v. City of Perrysburg) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hussein v. City of Perrysburg, 617 F.3d 828, 2010 U.S. App. LEXIS 17364, 2010 WL 3271727 (6th Cir. 2010).

Opinion

OPINION

ROGERS, Circuit Judge.

Dr. Fadhil Hussein and his wife, Raya Ahmed, endured a lengthy dispute with local zoning authorities after their builder failed to adhere to a number of zoning ordinances in the course of constructing the Husseins’ home. In June 2006, the zoning authorities issued a “stop work” order, but as winter approached, Hussein sought to have a temporary layer of asphalt installed on top of his otherwise-gravel driveway. He alleges that the zoning authorities gave oral permission for this installation. Nevertheless, while the subcontractor was installing the asphalt layer, the city inspector arrived with two policemen and threatened to take the subcontractor to court unless the subcontractor ceased the asphalt installation and removed what asphalt had already been laid down. The Husseins allege that this action violated their substantive and procedural due process rights. Because the city inspector only threatened litigation rather than removing the asphalt, the Husseins’ rights were not violated and the defendants—the city inspector and his direct superior—are entitled to qualified immunity.

Dr. Fadhil Hussein and his wife, Raya Ahmed, had the misfortune of hiring a builder who proved not capable of either competently constructing their home or of complying with local zoning ordinances in the process. Hussein and Ahmed (the Husseins) purchased an eight-acre property from Hafner & Shugarman Enterprises (Hafner) in October 2002. The Husseins retained Hafner to construct the home beginning in July 2004. The home construction was apparently flawed in nearly every respect. After a subsequent arbitration between the Husseins and Hafner, the arbitrator determined: (1) “[Hafner] performed few if any aspects of the work on the home in a craftsman like manner;” (2) “[Hafner] failed to pay all subcontractors ... even though [Hafner] had been paid by [the Husseins];” (3) Hafner falsely signed affidavits claiming to have paid the subcontractors; and (4) “[Hafner] did not comply with the zoning and building codes of the city of Perrysburg until June 2007, a year after the home was substantially complete.” The arbitrator awarded the Husseins approximately $330,000 in damages and approximately $190,000 in attorneys’ fees.

What remains of this case concerns the interactions between the Husseins and the zoning personnel of the city of Perrysburg during the approximately one-year period between the summer of 2006 and the summer of 2007, during which time the city was attempting to enforce its zoning regulations. There were three areas of contention: (1) the construction of the driveway entrance, (2) the filling of a flood plain while leveling ground for the Husseins’ tennis court and pool, and (3) the installation of public sidewalks. On June 28, 2006, City Inspector—and here defendant—Roud Klag issued a stop work order to Hafner, citing zoning deficiencies in these three areas. In July, the city initially refused to issue a certificate of occupan *831 cy to the Husseins, but eventually allowed the family to move into their home in return for Hussein’s promise to cooperate in addressing the three zoning deficiencies.

In the fall of 2006, the Husseins’ home had only a gravel driveway. Hussein sought a way to make his driveway safer in preparation for winter, and his (new) contractor, Rick Maeek, suggested putting a temporary thin layer of asphalt over the gravel. The Husseins’ lawyers sought approval for this plan, and one of the attorneys, Anastasia Hanson, testified that in early October 2006, she spoke with Klag about this plan. Hanson testified that, subject to the Husseins’ promise to install a code-compliant final driveway later, Klag authorized the installation of the temporary asphalt layer. Klag denies that this conversation took place, but as the defendants concede, the panel should view the facts in the light most favorable to the party asserting constitutional injury. Scott v. Harris, 550 U.S. 372, 377, 127 S.Ct. 1769, 167 L.Ed.2d 686 (2007). We therefore assume that Klag granted verbal authorization to install the asphalt layer.

Macek hired Gene Baird to install the asphalt, and the work took place on Friday, November 3, 2006. In the afternoon of that day, Baird arrived and began laying asphalt on the driveway, partly on the Husseins’ property and partly on the city’s right of way. A neighbor of the Husseins called Rick Thielen. Thielen is the city’s administrator for planning, zoning, and economic development, is Klag’s direct superior, and is Klag’s co-defendant in this case. The neighbor left a voice mail message reporting the paving work and inquiring about the situation. Thielen asked Klag if any driveway work had been authorized, and when Klag responded in the negative, Thielen asked Klag to investigate the situation.

Klag went out to the Husseins’ home, and he asked two police officers to accompany him. There are only two direct accounts—Klag’s and Baird’s—of the ensuing interaction between Klag and Baird, and they agree on the essence of the story. Baird recounted the interaction as follows:

[Klag] told me that there was a stop work order on the job and that I had to stop work and remove the asphalt. He said if I did not remove the asphalt that I had put down that they would require me to go to court and get fined. He said that I would be under litigation. I called [Hussein] and told him that the inspector said there was no permit. And [Hussein] told me that I should do what they instructed me to do rather than become involved in litigation.

The police officers meanwhile looked at the identification documents of the contractors. After the conversation, Baird removed the asphalt he had installed.

On June 11, 2007, the Husseins filed suit against the City of Perrysburg and against Klag, Thielen, and the city administrator in their official and personal capacities. In an amended complaint, the Husseins alleged that the defendants violated the Husseins’ procedural and substantive due process rights by ordering Baird to remove the temporary asphalt layer. In the first of two published opinions, the district court dismissed all of the claims against the city and the city administrator and the claims against Klag and Thielen in their official capacities. Hussein v. City of Perrysburg, 535 F.Supp.2d 862, 870, 873, 875 (N.D.Ohio 2008). In the second published opinion, the district court denied the defendants’ motion for summary judgment on the due process claims. Hussein v. City of Perrysburg, 647 F.Supp.2d 838 (N.D.Ohio 2009).

The district court concluded that the Husseins had produced sufficient evidence to show that the Husseins had a protected property interest in the asphalt that was *832 laid down on their driveway, that the defendants had deprived them of that interest by ordering the asphalt removed, and that this deprivation was arbitrary and capricious and was conducted without granting the Husseins any notice or opportunity to be heard. Id. at 852-56. After concluding that the rights at issue were clearly established, the court denied Klag and Thielen’s contention that they were entitled to qualified immunity. Id. at 856-57.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bailey v. Houk
S.D. Ohio, 2022
Shreeve v. Nahra
E.D. Michigan, 2021
Black Earth Meat Market, LLC v. Village of Black Earth
834 F.3d 841 (Seventh Circuit, 2016)
William Viehweg v. City of Mount Olive
559 F. App'x 550 (Seventh Circuit, 2014)
Rafael Marderosian v. City of Beavercreek
423 F. App'x 524 (Sixth Circuit, 2011)
Huckaby v. Priest
636 F.3d 211 (Sixth Circuit, 2011)
Dennis Dubuc v. Township of Green Oak
406 F. App'x 983 (Sixth Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
617 F.3d 828, 2010 U.S. App. LEXIS 17364, 2010 WL 3271727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hussein-v-city-of-perrysburg-ca6-2010.