Hunnicutt & Bellingrath Co. v. Van Hoose

36 S.E. 669, 111 Ga. 518, 1900 Ga. LEXIS 674
CourtSupreme Court of Georgia
DecidedJuly 13, 1900
StatusPublished
Cited by17 cases

This text of 36 S.E. 669 (Hunnicutt & Bellingrath Co. v. Van Hoose) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hunnicutt & Bellingrath Co. v. Van Hoose, 36 S.E. 669, 111 Ga. 518, 1900 Ga. LEXIS 674 (Ga. 1900).

Opinions

Little, J.

The Hunnicutt & Bellingrath Company instituted an action against Van Hoose and Pearce, in which they alleged that the defendants owned certain land in the city of Gainesville, and that in the spring of 1896 such owners entered into a contract with G. W. Foote, who was a contractor, to erect on said land a large building to be known as an auditorium, and agreed with Foote to pay him the sum of $14,200 for said building complete. It is further alleged that such - contract was in two parts; that is, that when certain portions of the work were done the owners were to pay Foote ten thousand dollars, and if the remainder was completed, the remaining sum of $4,200 was to be paid. The petitioner further alleged that it did certain work on and furnished certain material for the building, under a contract with Foote, to wit, that it furnished all the galvanized iron, tin, slate work, and sky-light for the building; for which Foote agreed to pay it $1,148, -which was a fair market price for the sanie; that $400 of said sum has been paid, leaving an indebtedness of $748 to the petitioner for said work and material. It is further alleged, that [520]*520after the contract had been entered into between the owners and Foote, the latter commenced the work, and did finish the building substantially so far as to have the brick walls put up and all stone, terra cotta, galvanized iron, etc., pertaining to the exterior work, so as to be entitled to the payment of the first-named amount of ten thousand dollars; and that thereupon the owners did pay to Foote the full amount of ten thousand dollars, without reserving twenty-five per cent, of said contract price, and without requiring any affidavit from the contractor, and without obtaining the consent of the petitioner; that at this point Foote abandoned his contract without completing the building according to the stipulations; and that the owners thereupon undertook to complete the building themselves, and did expend thereon the full sum of $14,200, including the sum paid to Foote, and did therefore use on said building and the completion thereof the full amount of the contract price without reserving any sum whateverand in this manner they obtained from the petitioner said material and labor, and have now no sum of money held back and reserved to pay for the same.’ The plaintiff prays a judgment against the owners of the property for the amount due it for labor performed and material furnished in the construction of the building as set out. Attached to the petition is a copy of the contract entered into between Van Hoose and Pearce, signing as the Georgia Female Seminary, and Foote, for the construction of the building. It is dated April 1, 1896; and, by its terms, Foote undertook, in consideration of the sum of $14,200, to build, finish, and deliver on or before September 1, 1896, a building for a conservatory of music, according to specifications made a part of the contract; and to provide all labor and materials of every kind for the completion and finishing of said work. Van Ploose and Pearce undertook on their part, for the faithful performance of the terms of the contract, to pay Foote the sum of $14,200 in the following manner: to pay on Saturday of each week during construction a sufficient amount to meet the pay-roll of the laborers for the week; and, on the first day of each month, a sufficient amount to cover seventy-five per cent, of the labor and material actually in the building. The last instalment was to be paid in thirty days after [521]*521-the work was fully completed and accepted by the owner, free from all claim by lien or other attachments. It was further provided, if the contractor should, at'any time during the progress of the work, refuse or neglect to supply and furnish a sufficiency of material or workmen, or cause any unreasonable neglect or suspense of the work, or fail or refuse to comply, with any of the articles of this agreement, that the owners should have the right and power to enter and take possession of the premises and provide material and workmen sufficient to finish the work, and the expense of so doing should be deducted from the amount of the contract. There was a stipulation in the following language: “It is mutually agreed between the parties of the first and second parts, that, in consideration of ten thousand dollars, the party of the first part is to complete all brick walls, put in all stone, terra cotta, galvanized iron, all O. S. doors, all windows, sash,floor linings, iron columns, and all necessary partitions, to lay all floor linings and everything pertaining to exterior work except stone steps; and that when this much of the building is completed the work may be suspended until such time as the party of the second part may decide to finish the building. If work is suspended for more than thirty days, the twenty-five per cent held back by the, party of the second part shall become payable by the party of the first part turning over' above-described work free from lien •or other attachment.”

To this petition the defendants filed a general demurrer, which on the hearing was sustained, and the petition dismissed; To this ruling the plaintiff excepted.

1. This action was based on the provisions of the Civil Code, §§2802; 2803, which, in effect, provide that every person who' shall give out a contract for the construction of any house shall retain twenty-five per cent, of the contract price Until the contractor shall submit to such person an affidavit that all debts' incurred for material and labor in constructing the house have been paid, or that the persons to whom such debts are due have consented to the payment of said twenty-five per cent and that, if any person shall pay said twenty-five per cent, of the contract price of the house without requiring the affidavit, he shall be liable to the extent of twenty-five per cent, of said [522]*522contract price to any materialman or laborer for material furnished or work done for said contractor in constructing said house. These sections were repealed by the act approved Dec. 18, 1897, and are not now in force. The plaintiff claims that its rights accrued under their provisions before such repeal; hence it becomes necessary to pass on the questions made. It was contended for the plaintiff that, under the provisions of the code which we have recited, it was the legal duty of the defendants to retain twenty-five per cent, of ten. thousand dollars; because, under a proper construction of the contract, this sum was to be paid to the contractor, separate and apart, for the completion of certain particular parts of the building. It is also contended that inasmuch as the defendants in error paid to the contractor ten thousand dollars of the contract price, at a certain stage of the work, and, after the abandonment of his contract by Foote, used the remaining part of the full contract price in completing the building, they thereby became liable for labor and material on the building, to the extent of twenty-five per cent, of $14,200, because that sum was the entire contract price. Two questions, therefore, are material to be considered. First, is the contract -which was entered into by the parties an entire or divisible one? Second, what legal obligations, as to the retention of a part of the contract price, were imposed upon the owner, who gave out a contract for the construction of a building on his land while these provisions of the code were in force? We shall address ourselves to these questions, in their order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowers v. Howell
417 S.E.2d 392 (Court of Appeals of Georgia, 1992)
Bishop v. Forsyth Paving Contractors, Inc.
352 S.E.2d 198 (Court of Appeals of Georgia, 1986)
Marathon Oil Co. v. Hollis
305 S.E.2d 864 (Court of Appeals of Georgia, 1983)
Thompson v. BRANNEN BUILDING SUPPLY
264 S.E.2d 498 (Court of Appeals of Georgia, 1980)
E. Smith Heating & Air Conditioning, Inc. v. Biggers
228 S.E.2d 203 (Court of Appeals of Georgia, 1976)
Haynie v. First Nat. Bank of Atlanta
162 S.E.2d 27 (Court of Appeals of Georgia, 1968)
Barnes v. Goodner
49 S.E.2d 128 (Court of Appeals of Georgia, 1948)
Burns v. Mitchell
191 S.E. 870 (Court of Appeals of Georgia, 1937)
Hillhouse v. Adams
161 S.E. 274 (Court of Appeals of Georgia, 1931)
Young v. Harley-Mitchell Hardware Co.
159 S.E. 567 (Supreme Court of Georgia, 1931)
Christman v. Salway
205 P. 541 (Oregon Supreme Court, 1922)
Timmons v. Citizens Bank
74 S.E. 798 (Court of Appeals of Georgia, 1912)
Heim v. Elliott
119 P. 826 (Washington Supreme Court, 1911)
Chamberlin v. Booth & McLeroy
70 S.E. 569 (Supreme Court of Georgia, 1911)
Prince v. Neal-Millard Co.
53 S.E. 761 (Supreme Court of Georgia, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
36 S.E. 669, 111 Ga. 518, 1900 Ga. LEXIS 674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hunnicutt-bellingrath-co-v-van-hoose-ga-1900.