Hull v. Baran Telecom, Inc.

242 F. App'x 504
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 12, 2007
Docket06-5136
StatusUnpublished

This text of 242 F. App'x 504 (Hull v. Baran Telecom, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hull v. Baran Telecom, Inc., 242 F. App'x 504 (10th Cir. 2007).

Opinion

ORDER AND JUDGMENT *

MONROE G. McKAY, Circuit Judge.

This negligence action was filed against Baran Telecom, Inc., the general contractor on a cellular telephone tower construction project, after Plaintiff, the foreman for the subcontractor tower erection crew, fell 240 feet when a cable used to hoist tower sections snapped. The district court awarded summary judgment in favor of Baran Telecom, and this appeal followed.

Background 1

Plaintiff Ray Hull, an experienced tower construction specialist, accepted a position with Innovative Wireless Construction (“IWC”) in an effort to resurrect its failing cellular telephone tower construction business. Mr. Hull’s first job with IWC was the time-sensitive construction of a three-leg, 350-foot, self-supporting cellular telephone tower in Fremont, Nebraska for Baran Telecom after Baran’s original subcontractor defaulted.

According to the undisputed material facts, IWC accepted the job on the express condition that Baran Telecom would provide a hydraulic crane and crane operators to assist IWC with the hoisting of preassembled tower sections into position. Mr. Hull and his crew immediately began assembly of the tower sections and, using the crane supplied by Baran Telecom, erected the tower to a height of 240 feet before the crane operator refused to continue working due to windy conditions. The next morning the crane operator disassembled his crane and left the work site over Baran Telecom’s on-site representative’s objections because the crane was scheduled for another job.

IWC and Baran agree that, because Baran Telecom could not secure another crane, the job could only be completed on time with the use of a gin pole and hoist. 2 Although IWC offered the use of its gin pole and hoist at additional cost, Mr. Hull was unable to retrieve it from its off-site location. Baran Telecom, concerned over meeting the project deadline, secured the use of one of its gin poles and hoists, which Mr. Hull retrieved and brought to the construction site.

Mr. Hull and his crew inspected the gin pole and hoist system, erected it, and tested its operation. Mr. Hull then ascended the tower and secured his safety rigging to the gin pole in preparation for the first hoist. Shortly after they began the first *506 hoist, however, the cable snapped under only seventeen percent of its maximum load-bearing capability. This failure caused the gin pole, and Mr. Hull along with it, to fall some 240 feet to the ground. Mr. Hull’s safety cable attempted to arrest his fall after 200 feet, but snapped under the pressure, causing him to free fall the last 40 feet.

Mr. Hull and his wife sued Baran Telecom for negligence under Nebraska law 3 , alleging Baran Telecom owed him a duty of care as the general contractor and site supervisor as well as the supplier of chattel. Baran Telecom moved for summary judgment, which the district court granted in part and denied in part. The district court granted Baran Telecom summary judgment with respect to the supplier of chattel claim after concluding that Baran Telecom offered its gin pole and hoist only as a favor. But genuine issues of material fact concerning the precise nature of Bar-an Telecom’s supervision prevented the district court from awarding Baran Telecom summary judgment on the supervisor claim.

Baran Telecom moved for summary judgment a second time on the supervisor claim after submitting newly obtained testimony. That testimony came from Baran Telecom’s on-site representative, an employee of a company to which Baran Telecom frequently subcontracted non-tower-related construction such as fencing and ground work. The representative testified that as Baran Telecom’s liaison he merely observed and reported on IWC’s progress. The district court found this evidence persuasive enough to award Baran Telecom summary judgment on that remaining issue. Plaintiffs’ appeal challenges both awards of summary judgment.

Analysis

A. Standard of Review

We review summary judgment decisions de novo, taking the evidence in the light most favorable to the non-moving party, in this case, Mr. Hull’s favor. See Zamora v. Elite Logistics, Inc., 478 F.3d 1160, 1164 (10th Cir.2007) (en banc). Summary judgment is appropriate only “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed. R. Civ. P. 56(c).

B. Duty Owed by a General Contractor

A general contractor’s duty of care under Nebraska law is set forth in Parrish v. Omaha Public Power District, 242 Neb. 783, 496 N.W.2d 902 (1993). That case, which distinguished between the duties of care owed by premise owners versus general contractors in control of the premises, stated that general contractors owe a duty of care to those lawfully on the premises “to keep the premises in a reasonably safe condition while the contract is in the course of performance.” Id. at 911 (quotation omitted). Under Parrish,

to impose liability on a general contractor for injury to a subcontractor’s employee, the general contractor must have (1) supervised the work that caused the injury to the employee; (2) had actual or constructive knowledge of the danger which ultimately caused the injury; and (3) had the opportunity to prevent the injury, but negligently failed to prevent the injury.

Id. at 912. “ ‘Normally when a general contractor has a supervisor on the site, it will be able to exercise control over the *507 premises.’ ” Id. at 911 (quoting Farris v. Gen. Growth Dev. Corp., 354 N.W.2d 251, 254 (Iowa Ct.App.1984)). However, “[i]t is not enough that [the general contractor] has merely a general right to order the work stopped or resumed, to inspect its progress or to receive reports, to make suggestions or recommendations which need not necessarily be followed, or to prescribe alterations and deviations.” Restatement (Second) of Torts § 414, cmt. c.

The district court analyzed Plaintiffs’ factual assertions that Baran Telecom’s on-site liaison supervised IWC’s work, but rejected those assertions as insufficient proof that Baran Telecom “controlled the manner and details of Hull’s work.” (Aplts.’ App., v. 2, at 604 (Order at 8 [hereinafter Order II]).)

Plaintiff argues that the district court applied the wrong law when it cited Didier v. Ash Grove Cement Co., No. A-03-924, 2005 WL 2276848, *6-7, 2005 Neb.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zamora v. Elite Logistics, Inc.
478 F.3d 1160 (Tenth Circuit, 2007)
Didier v. Ash Grove Cement Co.
718 N.W.2d 484 (Nebraska Supreme Court, 2006)
Parrish v. Omaha Public Power District
496 N.W.2d 902 (Nebraska Supreme Court, 1993)
Madler v. McKenzie County
467 N.W.2d 709 (North Dakota Supreme Court, 1991)
Farris v. General Growth Development Corp.
354 N.W.2d 251 (Court of Appeals of Iowa, 1984)
Semler v. Sears, Roebuck and Co.
689 N.W.2d 327 (Nebraska Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
242 F. App'x 504, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hull-v-baran-telecom-inc-ca10-2007.