Huffines v. Swor Sand & Gravel Co., Inc.

750 S.W.2d 38, 103 Oil & Gas Rep. 626, 1988 Tex. App. LEXIS 1204, 1988 WL 51913
CourtCourt of Appeals of Texas
DecidedMay 5, 1988
Docket2-87-155-CV
StatusPublished
Cited by24 cases

This text of 750 S.W.2d 38 (Huffines v. Swor Sand & Gravel Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huffines v. Swor Sand & Gravel Co., Inc., 750 S.W.2d 38, 103 Oil & Gas Rep. 626, 1988 Tex. App. LEXIS 1204, 1988 WL 51913 (Tex. Ct. App. 1988).

Opinion

OPINION

FENDER, Chief Justice.

Appellants J.L. Huffines, Jr., James Huf-fines, Ray Huffines, Phillip Huffines, and Donald Huffines, plaintiffs in the court below, sued appellee, Swor Sand & Gravel Co., Inc., for breach of a sand, gravel, rock, and clay mining lease. After a jury trial, the trial court entered judgment for appel-lee. Appellants appeal the take-nothing judgment.

We reverse and render in part, and we reverse and remand in part.

In June, 1982, appellants and appellee executed a sand, gravel, rock, and clay lease for the mining of minerals on appellants’ ranch. By its own terms, the lease was effective from June 1, 1982, until midnight May 31, 1983. In order to assure appellants a certain amount of income from the mining operations, the lease contained the following clause:

Lessee [Swor] guarantees that royalties payable to lessors for each year that this lease is in effect shall be not less than Five hundred thousand, ($500,-000), and lessee agrees to pay at the end of each lease period (May 31st) the difference between $500,000 and the royalty actually paid for removal of gravel, sand, rock and clay from the property to the lessor. In the event the royalty payable under this lease does not reach the amount guaranteed and the difference in the amount guaranteed and the royalty actually paid under the terms of this lease is not paid in cash to the lessor prior to the end of the lease, the lease shall terminate and the lessor shall have a claim for debt against the lessee in the amount of such deficiency. [Emphasis added.]

In addition, the lease contained a provision that required appellee to restore the property to a certain specified condition.

In order to remove the minerals from the premises, appellee had large trucks exit appellants’ ranch to Holferd’s Prairie Road. The homeowners along the road complained of the disturbance created by the trucks. As a result, on May 16, 1983, the Denton County Commissioners Court set a weight limit of fifteen tons on Holferd’s Prairie Road.

Appellee voluntarily vacated the premises and ceased all mining operations in May, 1983. At that time, appellee had paid only $319,000.00 of the $500,000.00 promised to appellants under the minimum guaranteed royalty clause. Nor did appellee restore the premises to the condition specified by the lease.

Appellants brought this lawsuit to enforce appellee’s obligations under the lease. Appellee defended by claiming that it was “economically impracticable” to continue performance under the lease because of the weight limit change on the road. The jury answered the special issue as to the impracticability of performing the contract in favor of appellee.

Appellants’ first point of error asserts that the trial court erred in submitting special issue no. 5 to the jury. We agree.

Special issue no. 5 reads as follows:

Do you find from a preponderance of the evidence that Swor Sand and Gravel Co. was unable to perform under the contract because performance of the contract became unexpectedly impracticable as a result of the load limit placed on Holferd’s Road?
Answer “Yes” or “No”.
ANSWER: Yes
You are instructed that “impracticability” means more than “impraeticality”. *40 A change in the degree of difficulty or expense unless well beyond the normal range does not amount to impracticality. A party is expected to use reasonable efforts to surmount obstacles to performance. A performance is impracticable only if it is so in spite of such efforts.
“Unexpectedly” means that the event or events might not reasonably have been anticipated and guarded against in a contract.

Where the obligation to perform is absolute, impossibility of performance occurring after the contract is made is not an excuse for nonperformance if the impossibility might have reasonably been anticipated and guarded against in the contract. Metrocon Const. Co. v. Gregory Const. Co., 663 S.W.2d 460, 462 (Tex.App.—Dallas 1983, writ ref’d n.r.e.); Calvin v. Koltermann v. Underream Piling Co., 563 S.W.2d 950, 957 (Tex.Civ.App.—San Antonio 1977, writ ref’d n.r.e.); T.G. Shaw Oil Corp. v. Parker, 61 S.W.2d 587, 589 (Tex.Civ.App.—Fort Worth 1933, no writ).

Here, Clarence Swor, the president of Swor Sand & Gravel Co., Inc., admitted load limits on roads were a big problem in the sand and gravel business. Clarence Swor also testified that the weight limit set in May, 1983, on the Holferd’s Prairie Road was not surprising. Moreover, the weight limit was not imposed until May 16, 1983, just fifteen days before the $500,000.00 guaranteed minimum royalty was due. Appellee’s obligations in the lease, as evidenced by the minimum guaranteed royalty clause and the restoration clause, were absolute. The weight limit change was admittedly foreseeable. Nevertheless, appel-lee did not take adequate measures to protect itself in the written lease against a weight limit change. As a result, appellee had no defense of impossibility of performance available to it.

As for the alleged “impracticability” defense, which is the actual term used in special issue no. 5, we find no support for such a defense in Texas law. On the contrary, Texas courts have held contractual obligations cannot be avoided simply because the obligor’s performance has become more economically burdensome than anticipated. Alamo Clay Products, Inc. v. Gunn Tile Co., 597 S.W.2d 388, 392 (Tex.Civ.App.—San Antonio 1980, writ ref’d n.r.e.); Mahrer v. Mahrer, 510 S.W.2d 402, 405 (Tex.Civ.App.—Dallas 1974, no writ). Although the trial court and appellee may have relied on the RESTATEMENT (SECOND) OF CONTRACTS secs. 261, 264 (1981), for the wording of special issue no. 5, a close reading of the American Law Institute’s illustrations 2, 3, 4, 5, and 11 following section 261 of the Restatement leads us to the conclusion that “impracticability” is not a proper justification for nonperformance under the facts of the instant case. We conclude the submission of a jury issue on “impracticability” was improper. Nor, as we previously indicated, could special issue no. 5 be interpreted as an impossibility defense because appellee had no such defense available to it. Accordingly, appellants’ point of error one is sustained.

We must next address the issue of no evidence to support the submission of an issue on impossibility or impracticability urged in appellants’ second point of error. In determining a “no evidence” point, we are to consider only the evidence and inferences which tend to support the finding of the jury and disregard all evidence and inferences to the contrary. See Larson v. Cook Consultants, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Triyar Companies v. Fireman's Fund Insurance Co.
515 S.W.3d 517 (Court of Appeals of Texas, 2017)
John Stephen Philips v. Gail McNease
467 S.W.3d 688 (Court of Appeals of Texas, 2015)
Steven Jeffrey Johnson v. Michele Jean Johnson
Court of Appeals of Texas, 2011
Reeder v. Wood County Energy L.L.C.
320 S.W.3d 433 (Court of Appeals of Texas, 2010)
Solar Soccer Club v. Prince of Peace Lutheran Church of Carrollton
234 S.W.3d 814 (Court of Appeals of Texas, 2007)
Railroad Commission of Texas v. Coppock
215 S.W.3d 559 (Court of Appeals of Texas, 2007)
Jason Vidal v. State
Court of Appeals of Texas, 2007
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 2004
Opinion No.
Texas Attorney General Reports, 2004
Kirby Forest Industries, Inc. v. Kirkland
772 S.W.2d 226 (Court of Appeals of Texas, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
750 S.W.2d 38, 103 Oil & Gas Rep. 626, 1988 Tex. App. LEXIS 1204, 1988 WL 51913, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huffines-v-swor-sand-gravel-co-inc-texapp-1988.