Alamo Clay Products, Inc. v. Gunn Tile Co. of San Antonio, Inc.

597 S.W.2d 388, 29 U.C.C. Rep. Serv. (West) 31
CourtCourt of Appeals of Texas
DecidedJanuary 23, 1980
Docket16184
StatusPublished
Cited by13 cases

This text of 597 S.W.2d 388 (Alamo Clay Products, Inc. v. Gunn Tile Co. of San Antonio, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alamo Clay Products, Inc. v. Gunn Tile Co. of San Antonio, Inc., 597 S.W.2d 388, 29 U.C.C. Rep. Serv. (West) 31 (Tex. Ct. App. 1980).

Opinion

CADENA, Chief Justice.

Defendant, Alamo Clay Products, Inc., appeals from a judgment based on jury findings awarding plaintiff, Gunn Tile Company of San Antonio, Inc., $11,000.00 as damages for defendant’s breach of its contractual obligation to deliver to plaintiff 61,000 square feet of 8" X 12" X 1 ⅜" paving bricks or tiles. These items will be referred to in this opinion as 8 X 12 pavers.

In May, 1972, the general contract in connection with some construction work on the campus of the University of Texas at San Antonio (UTSA) had been awarded to T. C. Bateson Co. Defendant was aware of the proposed construction and had distributed information containing quotations of prices on the tile to be used to various tile contractors, including plaintiff. The prices reflected in such documents included quotations on the cost of the 8 X 12 pavers. Plaintiff, after having received the quotations from defendant, submitted a bid to the general contractor concerning the tile work required for the UTSA project. The instrument distributed by defendant stated that the prices quoted were binding for 15 days unless specifically stated otherwise, and that in no event would the prices quoted be binding on defendant for more than 30 days after the signing of the general contract.

Plaintiff was the successful bidder for the tile work. Its contract with the general contractor specified the use of pavers of a color and texture approved by the architect, and recited that pavers which complied with the requirements of the specifications included, without being limited to, San Juan tile pavers manufactured by defendant.

There were delays in connection with the UTSA project, and it was not until August 31, 1973, that Compton, plaintiff’s supervisor and estimator, telephoned Rogers, defendant’s general manager, concerning the acquisition of the required tile, including the 8 X 12 pavers. During this conversation no mention was made of price or of time, place or method of delivery. On that same date, following the telephone conversation, Compton mailed to Rogers a document referred to by Compton as “a telephone confirmation purchase order,” which referred to 4 X 8 pavers and 8 X 12 pavers, both of which sizes were required by plaintiff to fulfill its obligations under its contract with the general contractor. This instrument made no mention of price, or of the time, place or method of delivery.

There was no further communication between plaintiff and defendant until December 27, 1973, when defendant, by means of a letter signed by Rogers, informed plaintiff that production difficulties beyond defendant’s control were making it extremely *390 difficult, if not impossible, to manufacture the 8 X 12 “San Juan pavers scheduled for [plaintiff’s] P.O. 1471.” In this letter Rogers stated that defendant was trying “alternate methods of procedure” which, if successful, would enable defendant to furnish the 8 X 12 pavers “within approximately 60 to 90 days.” However, Rogers referred to the possibility of failure of the alternate methods.

Rogers assured plaintiff that defendant would be able to satisfy “the entire order” of the 4X8 pavers, and he recommended that plaintiff use additional 4X8 pavers in lieu of the 8 X 12 pavers. Although the letter ended with a request that plaintiff “please advise” defendant, plaintiff did not reply.

On February 25, 1974, defendant, again by means of a letter signed by Rogers, informed plaintiff that all efforts to produce the 8 X 12 pavers had been unsuccessful; but that defendant could produce 6 X 9 pavers which could be delivered within three weeks or less, if the architect approved the substitution of such smaller pav-ers for the 8 X 12 pavers.

Plaintiff submitted the samples of the 6 X 9 pavers to the architect because “there wasn’t much choice,” and arranged a meeting on April 17, 1974, at which plaintiff, defendant, the architect, the general contractor and a representative of UTSA were present. After some discussion, the architect approved the use of the smaller (6 X 9) pavers. Plaintiff pointed out that the use of the smaller pavers would increase the cost of the job, but the architect insisted that his use of the smaller pavers was approved only if there was no increase in the cost of the project. The architect reminded plaintiff that plaintiff’s subcontract provided for liquidated damages for delay in the amount of $420.00 per day.

Plaintiff then purchased the smaller tile from defendant “under protest.” The 6 X 9 pavers were sold and delivered by defendant to plaintiff in lieu of the larger pavers at prices prevailing on August 31, 1973, the date on which plaintiff had first contacted defendant by telephone. The August 31, 1973, price of the 6X9 pavers was $175.00 per thousand pieces. The 4X8 pavers required by plaintiff were also furnished by defendant on the basis of the August 31, 1973, price.

Because more of the 6X9 pieces were needed than would have been required if defendant had furnished the 8 X 12 pavers, based on August, 1973, prices, the total cost of the 6X9 pavers delivered by defendant exceeded by $2,699.12 the total cost of the larger pavers originally specified. The testimony reflects that, because the smaller pavers were used, additional labor expenses were incurred by plaintiff. The use of the smaller pavers resulted in a necessary increase in the number of “grout joints,” requiring the use of almost 24,000 additional pounds of grout. The change to the smaller size resulted in more delays in the work. The testimony shows that such additional expenses are to be expected when there is a change to a tile of a smaller size; and there is testimony that the substitution resulted in additional expense to plaintiff, including the additional cost of the tile itself, totaling $12,362.78.

There is testimony that defendant had previously furnished 12 X 8 pavers, although in smaller quantities, in connection with some construction work at Trinity University, also located in San Antonio.

In answer to special issue no. 1, the jury found that on August 31,1973, plaintiff and defendant had entered into an “agreement” that defendant would sell and deliver to plaintiff, and plaintiff would purchase from defendant, 61,000 square feet of 8 X 12 pavers. In answer to the second special issue the jury found that $11,000.00 would fairly compensate plaintiff for his damages resulting from the fact that defendant delivered 6X9 pavers rather than 8 X 12 pavers.

We will not consider those portions of defendant’s brief which seek reversal because of defects in the court’s charge to the jury. The complaints which defendant now presents to this Court were not called to the attention of the trial court by means of objection to the issues and instructions, nor *391 by requests for the submission of issues or instructions. The defects, if any, were waived by defendant. Tex.R.Civ.P. 274; Texas Employers’ Ins. Ass’n v. Neuman, 379 S.W.2d 295, 296 (Tex.1964).

Defendant claims that the trial court should have granted its motion for instructed verdict and for judgment n. o. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Mark at Weatherford Owner v. German
Texas Business Court, 2026
1464-Eight, Ltd. v. Joppich
154 S.W.3d 101 (Texas Supreme Court, 2004)
Huffines v. Swor Sand & Gravel Co., Inc.
750 S.W.2d 38 (Court of Appeals of Texas, 1988)
Heritage Life Insurance Co. v. Heritage Group Holding Corp.
751 S.W.2d 229 (Court of Appeals of Texas, 1988)
Valero Transmission Co. v. Mitchell Energy Corp.
743 S.W.2d 658 (Court of Appeals of Texas, 1987)
Smith v. State
676 S.W.2d 379 (Court of Criminal Appeals of Texas, 1984)
Metrocon Construction Co. v. Gregory Construction Co.
663 S.W.2d 460 (Court of Appeals of Texas, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
597 S.W.2d 388, 29 U.C.C. Rep. Serv. (West) 31, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alamo-clay-products-inc-v-gunn-tile-co-of-san-antonio-inc-texapp-1980.