Brath, Inc. and the Glens Falls Insurance Company v. GFCS, Inc.

CourtCourt of Appeals of Texas
DecidedJanuary 29, 1998
Docket03-97-00149-CV
StatusPublished

This text of Brath, Inc. and the Glens Falls Insurance Company v. GFCS, Inc. (Brath, Inc. and the Glens Falls Insurance Company v. GFCS, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brath, Inc. and the Glens Falls Insurance Company v. GFCS, Inc., (Tex. Ct. App. 1998).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN




NO. 03-97-00149-CV

Brath, Inc. and The Glens Falls Insurance Company, Appellants


v.



GFCS, Inc., Appellee



FROM THE DISTRICT COURT OF TRAVIS COUNTY, 201ST JUDICIAL DISTRICT

NO. 96-04737, HONORABLE JERRY DELLANA, JUDGE PRESIDING

PER CURIAM

This cause concerns the impossibility of performance of a contract. GFCS, Inc. was a subcontractor on a public works construction project on which Brath, Inc. (1) was the general contractor. Brath withheld money from the contract amount due to GFCS, based on GFCS's alleged failure to complete its subcontract on schedule. GFCS sued Brath under breach of contract and quantum meruit theories seeking recovery of the withheld money, attorney's fees and costs. After a bench trial, the court rendered judgment in favor of GFCS. On appeal, Brath brings six points of error attacking the legal and factual sufficiency of the evidence to support various trial-court findings. We will affirm the trial-court judgment.



Background


The Pflugerville Independent School District (PISD) contracted with Brath to construct improvements to a school. Brath subcontracted with GFCS for labor and material to install flooring, which consisted of carpet, ceramic tile, vinyl composition tile (VCT) and base. The contract required GFCS to complete the work by December 12, 1995. The contract also required GFCS to use a particular Mohawk-brand carpet, which would take four to six weeks to deliver. On October 11, 1995, GFCS placed its order for the carpet and was informed that the delivery would be made November 11, 1995; however, Mohawk missed that delivery date and the next delivery date of December 2, 1995. Mohawk informed GFCS that it missed the delivery dates because of defective material. GFCS attempted to substitute carpet other than Mohawk but PISD's architect refused to accept any substitutes. Mohawk finally delivered the carpet on December 22, 1995; GFS finished installing the carpet December 27, 1995.

The contract also required GFCS to install VCT and base, with the same December 12 completion date. Brath rejected a bid for the floor leveling that had to be done before GFCS could install the base and VCT. Brath attempted to do the leveling itself but failed to have the work completed by December 12, 1995, GFCS's scheduled completion date. On December 19, 1995, Brath executed a field change order requiring GFCS to perform the additional leveling and agreed to pay additional money to GFCS for this work.

GFCS completed all work by January 4, 1996. Brath withheld $7,452.00 from its scheduled payment to GFCS. Brath did not contend that any work was defective. The amount withheld was a per diem amount based on the delay from December 12, 1995 to January 4, 1996, calculated to include "general condition costs" and a fifteen percent markup. The contract contained no liquidated damages clause. The contract contained a clause providing for an extension of time if changes were ordered. PISD withheld no money from Brath based on any contract delay.



Sufficiency of the Evidence


In deciding a no-evidence point, we must consider only the evidence and inferences tending to support the finding of the trier of fact and disregard all evidence and inferences to the contrary. Burroughs Wellcome Co. v. Crye, 907 S.W.2d 497, 499 (Tex. 1995); Garza v. Alviar, 395 S.W.2d 821, 823 (Tex. 1965). We will uphold the finding if more than a scintilla of evidence supports it. Crye, 907 S.W.2d at 499; In re King's Estate, 244 S.W.2d 660, 661 (Tex. 1951). The evidence supporting a finding amounts to more than a scintilla if reasonable minds could differ in their conclusions. Transportation Ins. Co. v. Moriel, 879 S.W.2d 10, 25 (Tex. 1994); Crye, 907 S.W.2d at 499.

When deciding an insufficient evidence point, we must consider and weigh all of the evidence and should set aside the judgment only if it is so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986); In re King's Estate, 244 S.W.2d 660, 661 (Tex. 1951); see also Pool v. Ford Motor Co., 715 S.W.2d 629 (Tex. 1986).

Impossibility of Performance


In its first point of error, Brath asserts that there was no evidence to support the trial-court finding that performance was impossible. It is undisputed that the contract required Brath to use only this particular Mohawk-brand carpet and that Mohawk failed to meet two scheduled delivery dates because of defectively milling the carpet. GFCS's president, with seventeen years' experience in the flooring business, testified that he decided when to place the order based on the anticipated amount of time to deliver added to the amount of time he knew it would take to install the carpet. He testified that due to storage and payment considerations, it would not have been customary to have ordered earlier and stored the material. Pat Potts, a flooring material supplier with over twenty years' experience, testified that the order was placed at a reasonable time and would have allowed timely completion if timely delivered. He also said that he had never heard of anyone having two defective mill runs.

Centex Corp. v. Dalton, 840 S.W.2d 952 (Tex. 1992), discussed the application of the doctrine of impossibility of performance. In Centex, a savings and loan holding company entered a contract with a consultant for the payment of finder's fees for the acquisition of four thrift institutions. However, the Federal Home Loan Bank Board prohibited payment of that fee as a condition of the acquisition of the thrifts. Id. at 953. The court held that the holding company's obligation to the consultant for the payment of finder's fees was discharged by impossibility because of the bank board's prohibition. Id. at 954. Although the consultant argued that the holding company should have foreseen and guarded against the possibility of regulatory changes, the court de-emphasized the aspect of foreseeability in determining whether performance was impossible. Id. at 954-55.

Brath relies on several distinguishable cases. In Huffines v. Swor Sand & Gravel Co., Inc., 750 S.W.2d 38 (Tex. App.--Fort Worth 1988, no writ), performance was possible, although less profitable. Id. at 40. Huffines

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pool v. Ford Motor Co.
715 S.W.2d 629 (Texas Supreme Court, 1986)
Centex Corp. v. Dalton
840 S.W.2d 952 (Texas Supreme Court, 1992)
In Re King's Estate
244 S.W.2d 660 (Texas Supreme Court, 1951)
Burroughs Wellcome Co. v. Crye
907 S.W.2d 497 (Texas Supreme Court, 1995)
Transportation Insurance Co. v. Moriel
879 S.W.2d 10 (Texas Supreme Court, 1994)
Metrocon Construction Co. v. Gregory Construction Co.
663 S.W.2d 460 (Court of Appeals of Texas, 1983)
Garza v. Alviar
395 S.W.2d 821 (Texas Supreme Court, 1965)
Huffines v. Swor Sand & Gravel Co., Inc.
750 S.W.2d 38 (Court of Appeals of Texas, 1988)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Brath, Inc. and the Glens Falls Insurance Company v. GFCS, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/brath-inc-and-the-glens-falls-insurance-company-v--texapp-1998.