OPINION

O’HORA, Judge.

On June 5, 1967, plaintiffs entered into a contract with defendant-contractor which called for construction of a house at a price of $17,400.00. Settlement was tentatively set for sometime in October, 1968. The contract was drawn on a standard, printed form.

*168 In May, 1968, plaintiffs were informed that completion of the house would be delayed until mid-1969. In August, 1968, plaintiffs were informed that the house could not and would not be completed at the contract price, but could be completed at a price of $1,500.00 in excess thereof. Plaintiffs refused to pay the additional $1,500.00. Offers of similar style houses on different lots for $500.00 above the contract price were also rejected and plaintiffs instituted an action for breach of contract.

The matter now before the_Court_Js defendant’s motion to dismiss based upon iirfpossibility of performance under the terms ~of the contract.. As grounds for excusing performance under the terms of the contract, defendant cites the following factors:

1. Interest on construction financing has increased from 6% as of June 1, 1967, the contract date, to 7% as of October, 1968, the date on which the motion to dismiss was filed.
2. “Points” required to be paid by the builder-seller in connection with an F.H.A. mortgage increased from 4 points (i. e. 4% of the mortgage) on the contract date to as high as 11 points and in October, 1968 the figure stood at 5 points.
3. Construction costs increased 10-15% during the period from June, 1967 to October, 1968.
4. Help was generally available within the building industry in June, 1967, and is “almost unavailable” now, particularly in the fields of masonry, painting and carpentry.

The contract terms under which defendant argues his performance is excused are paragraphs 13 and 23. Paragraph 13 provides :

“If for any reason Sel’er’s title is not good and marketable and Seller shall be unable to perfect such title, or if for any other reason Seller is unable to construct or complete said premises or make title as herein provided, Seller shall return to the Purchaser the sum or sums paid on account of the purchase price, without interest, and this agreement shall thereupon become cancelled, null and void, and the Seller shall have no further liability whatsoever to Purchaser.” (Emphasis added).
Paragraph 23 provides:
“This agreement is conditioned upon the ability of Seller to complete the above described property under conditions similar to those presently existing in the home building industry. If Seller is unable to procure promptly, as and when needed, labor and material required for construction as aforesaid, or if Seller for any reason cannot complete these premises due to any present or future rules, regulations or restrictions (particularly those involving priorities or material allocation) by the federal, state or municipal governments, or their agencies, then, and in any such event, Seller is hereby given the option to cancel this contract upon written notice to Purchaser, in which event the full deposit money shall be returned to Purchaser without interest, and this agreement shall thereupon become cancelled, null and void, and Seller shall have no further liability whatsoever to Purchaser.” (Emphasis added).

Defendant argues that the quoted paragraphs of the contract permit the Seller to cancel further performance for any reason which he deems to be sufficient. Even if these provisions may be viewed as ambiguous and theoretically capable of the broad interpretation defendant suggests, the contract must nonetheless be construed against him. It is a fundamental rule of construction that ambiguities must be resolved against the one who chose the language used and, further, that an interpretation should be adopted if possible, so that the contract will not be found illusory. 17 *169 Am.Jtir.2d, Contracts, § 276; 3 Corbin on Contracts, § 546 (1960).

In this instance, however, no rules of interpretation need be employed since the language of the contract appears to have clear meaning. Futhermore, the factors cited by defendant do not appear to constitute an excuse of performance within the meaning of paragraph 13 and 26.

Paragraph 13 refers to inability to construct or complete the premises “as herein provided”. Use of the phrase “as herein provided” calls special attention to the cardinal rule that one paragraph in a contract, cannot be read in isolation, but must be read within the context of the entire instrument. 3 Corbin on Contracts, § 549 (1960). The inability to perform referred to in paragraph 13 must, therefore, be consistent with the inability to perform set forth in more detail in paragraph 26.

Paragraph 26 states that the agreement is conditioned upon Seller’s ability to complete the premises under conditions similar to those then existing in the home building industry. Defendant reads the paragraph as if it stops at that point and concludes that cost considerations are necessarily part of the “similar conditions” that must exist before he will be bound to complete his job. Defendant ignores the fact that immediately following the first sentence of paragraph 26 there is an enumeration of the specific conditions previously referred to, followed by the statement that “in any such event” the Seller has the option to cancel. “Such events” enumerated do not include the kind of cost considerations cited by defendant as grounds to excuse performance. Unavailability of labor and materials and existence of rules and regulations making completion impossible are the only factors which will excuse performance under paragraphs 13 and 26 of the contract. Nowhere does the contract say that increased cost to the Seller will excuse performance.

It is well established that:
‘(Mere inconvenience or substantial increase in the cost of compliance with a contract, though they mightjnake compliance^ hardship,_cannot excuse a party from the performance of jm absolute and unqualified undertaking to do a thing that is possible and lawful. Courts cannot alter contracts merely because they work a hardship. A contract is not invalid, nor is the obligor therein in any manner discharged from its binding effect, because it turns out to be difficult or burdensome to perform.” Safe Harbor Fishing Club v. Safe Harbor Realty Co., 34 Del.Ch. 28, 107 A.2d 635 (1953).

Contractual provisions attempting to qualify an undertaking in the face of increased cost considerations should be more specific in reference to such factors than was the case here before parties can be held to have contractually modified or altered existing law.

The first three “cost” factors cited by defendant are, therefore, quite clearly not grounds to excuse performance within the meaning of the. contract. The fourth factor presents a somewhat different problem.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: Zohar III, Corp.
D. Delaware, 2020
Buller v. Montague
Superior Court of Delaware, 2020
Duncan v. STTCPL, LLC
Superior Court of Delaware, 2020
Physiotherapy Corp. v. Samuel Moncure, III
Court of Chancery of Delaware, 2018
Deanna Gilbert v. Nationwide Mutual Insurance Company
Delaware Court of Common Pleas, 2016
KWSO Television Co., Inc. v. KFDA Operating Company, LLC
442 S.W.3d 695 (Court of Appeals of Texas, 2014)
Stonewall Insurance Co. v. E.I. Du Pont De Nemours & Co.
996 A.2d 1254 (Supreme Court of Delaware, 2010)
In Re NVF Co.
309 B.R. 698 (D. Delaware, 2004)
In Re Teligent, Inc.
268 B.R. 723 (S.D. New York, 2001)
USH Ventures v. Global Telesystems Group, Inc.
796 A.2d 7 (Superior Court of Delaware, 2000)
Chamison v. HealthTrust, Inc.-Hosp. Co.
735 A.2d 912 (Court of Chancery of Delaware, 1999)
Cities Service Co. v. Gulf Oil Corp.
1999 OK 14 (Supreme Court of Oklahoma, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
252 A.2d 166, 1969 Del. Super. LEXIS 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hudson-v-d-v-mason-contractors-inc-delsuperct-1969.