Current Solutions, Inc. v. Appoquinimik School District

CourtSuperior Court of Delaware
DecidedDecember 13, 2024
DocketN23C-11-042 PAW
StatusPublished

This text of Current Solutions, Inc. v. Appoquinimik School District (Current Solutions, Inc. v. Appoquinimik School District) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Current Solutions, Inc. v. Appoquinimik School District, (Del. Ct. App. 2024).

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

CURRENT SOLUTIONS, INC., ) ) Plaintiff, ) ) v. ) C.A. No. N23C-11-042 PAW ) APPOQUINIMINK SCHOOL ) DISTRICT, ) ) Defendant. )

Submitted: September 30, 2024 Decided: December 13, 2024

MEMORANDUM OPINION

Upon consideration of Defendant’s Motion to Dismiss;

DENIED, in part and GRANTED, in part.

Scott Earle, Esq., of Goldberg Segalla LLP and Judith Jones, Esq., of Zarwin Baum DeVito Kaplan Schaer Toddy PC, Attorneys for Plaintiff.

William Gamgort, Esq. and Carmella Cinaglia, Esq., of Young Conaway Stargatt & Taylor LLP, Attorneys for Defendant.

WINSTON, J. I. INTRODUCTION

Current Solutions, Inc., (“CSI”) sues Appoquinimink School District, (“the

District”) for breaches of contract and the implied covenant of good faith and fair

dealing. In response, the District moves to dismiss. CSI pleads facts supporting an

inference of breach of contract, and it is reasonably conceivable that CSI is entitled

to recover. The implied covenant claims, however, conflict with the express terms

of the agreement. Accordingly, the District’s Motion to Dismiss is DENIED, in

part and GRANTED, in part.

II. FACTUAL AND PROCEDURAL BACKGROUND1

CSI is an electrical subcontractor that was the successful bidder for the

electrical work to construct a new elementary school, Crystal Run Elementary

School (“the Project”), for the District.2 The Electrical Contract (“the Contract”)

was prepared using AIA Document A132-2019.3 The Contract sum was

$2,086,400.00.4 The Contract provides that the Project’s Construction Manager

(“CM”) will create, publish, and update or revise the formal Project Construction

1 The following facts are drawn from the Complaint and documents incorporated by reference. Windsor I, LLC v. CW Capital Asset Mgmt. LLC, 238 A.3d 863, 873 (Del. 2020). Citations in the form of “Ex. __” refer to documents attached to the Complaint. 2 Compl. ¶ 1. 3 Compl. ¶ 13. 4 Compl. ¶ 13.

2 Schedule throughout the Project’s construction.5 The Contract also provides for an

initial review and decision process overseen by the Project’s architect for certain

claims or disputes.6

By no fault of CSI, the Project was delayed from the beginning.7 To remedy

these delays, the District compressed CSI’s work schedule and engaged other

electrical subcontractors to complete CSI’s scope of work.8 This engagement led to

CSI’s constructive discharge.9 Additionally, throughout the Project, the District

failed to issue contractually required schedules and instead, issued informal

schedules on an ad hoc basis.10 Lastly, CSI contends that the District failed to pay

CSI for work performed, wrongfully projected its failures onto CSI, and wrongfully

back-charged CSI for costs attributable to the District.11 Despite the District’s

conduct, CSI performed its obligations under the Contract.12

On November 7, 2023, CSI filed its Complaint seeking damages for breach of

contract (“Count I”) and breach of covenant of good faith and fair dealing (“Count

5 Compl. ¶ 15. 6 Ex. B at Article 15 (“Claims and Disputes”). 7 Compl. ¶ 6. 8 Compl. ¶ 8. 9 Compl. ¶ 8. 10 Compl. ¶ 9. 11 Compl. ¶ 10. 12 Compl. ¶ 10.

3 II”), relating to the District’s alleged failure to pay CSI for completed electrical

work, allow CSI additional time to complete its work, and increase CSI’s fixed price

contract for the hiring of additional workers.13 In response, the District moves under

Superior Court Civil Rule 12(b)(6) for failing to state a claim upon which relief can

be granted.14

III. ANALYSIS

Upon a Rule 12(b)(6) motion, the Court accepts all well-pleaded factual

allegations as true; (2) credits vague allegations if they give the opposing party notice

of the claim; (3) draws all reasonable inferences in favor of the non-moving party;

and (4) denies dismissal if recovery on the claim is reasonably conceivable.15

When both parties present their positions and reference materials neither

incorporated into nor integral to the complaint, the Court can convert the motion to

one for summary judgment.16 However, this will not occur if “the additional

documents are incorporated by reference into the complaint and are integral to the

claims of the complaint” or “the documents are not being relied upon to prove the

13 See Compl. 14 Def. Mot. to Dismiss at Introduction. 15 Cent. Mortg. Co. v. Morgan Stanley Mortg. Cap. Holding, LLC, 27 A.3d 531, 535 (Del. 2011). 16 Driggus v. State Farm Mut. Auto. Ins. Co., 2023 WL 7599490 at *1 (Del. Super. Nov. 15, 2023).

4 truth of its contents.”17 If either of these situations exists, a conversion will not

occur.

At present, both parties submitted additional documents not incorporated by

reference. Although the documents are “being relied upon to prove the truth of its

contents” and were submitted by the parties to demonstrate the veracity of the

allegations in the Complaint, at oral arguments, both parties acknowledged the Court

should not consider the additional documents.18 Accordingly, the Court will address

the Motion by considering only the Complaint and documents incorporated by

reference.

A. COUNT I – BREACH OF CONTRACT

The allegations set forth in the Complaint are sufficient to state a breach of

contract claim, and it is reasonably conceivable that CSI is entitled to recover. For

a breach of contract claim to survive a motion to dismiss, it is sufficient to “simply

allege first, the existence of the contract; second, the breach of an obligation imposed

by that contract; and third, the resultant damage to the plaintiff.” 19

17 Cambridge Strategic Mgmt. Grg. v. IDT Domestic Telecom, Inc., 2013 WL 2480887 at *3 (Del. Super. Apr. 8, 2013). 18 The District clarified it would be comfortable with the Court not considering its submitted affidavit. CSI agreed that it believed converting the Motion to one for summary judgment would be premature without time for additional discovery. 19 Nucor Coatings Corp. v. Precoat Metals Corp., 2023 WL 6368316 at *13 (Del. Super. Aug. 31, 2023) (quoting Garfield v. Allen, 277 A.3d 296, 328 (Del. Ch.

5 CSI first alleges that the District breached the Contract by terminating CSI

without the requisite justification provided for under Section 14.2.1 of the Contract

Documents.20 CSI also alleges that the Construction Manager breached his duties

under the Contract when the CM “failed to issue or otherwise revise the Project

Construction Schedule per the requirements set forth” in Section 013216(2)(A)&(B)

or the Contract.21 The Complaint further alleges that the District breached the

Contract by failing to adjust the Contract time and sum to accommodate for the

truncated work schedule issued by the CM on an arbitrary and ad hoc-rolling basis,

a failure which breached, among other provisions, Article 7 regarding Changes in

the Work and Article 8.3 regarding Delays and Extensions of Time of the General

Conditions.22 Finally, CSI claims that the District breached Article 5 of the Contract

by failing to pay CSI for the work performed in accordance with payment

applications 7 and 8, and by routinely failing to pay CSI for its work by the 15th of

the following month.23

2022)); see also Humanigen, Inc. v. Savant Neglected Diseases, Inc., 238 A.3d 194, 202 (Del. Super. Aug.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hudson v. D & v. Mason Contractors, Inc.
252 A.2d 166 (Superior Court of Delaware, 1969)
Kuroda v. SPJS Holdings, L.L.C.
971 A.2d 872 (Court of Chancery of Delaware, 2009)
Merrill v. Crothall-American, Inc.
606 A.2d 96 (Supreme Court of Delaware, 1992)
Emmett S. Hickman Co. v. Emilio Capaldi Developer, Inc.
251 A.2d 571 (Superior Court of Delaware, 1969)
Nationwide Emerging Managers, LLC v. Northpointe Holdings, LLC
112 A.3d 878 (Supreme Court of Delaware, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Current Solutions, Inc. v. Appoquinimik School District, Counsel Stack Legal Research, https://law.counselstack.com/opinion/current-solutions-inc-v-appoquinimik-school-district-delsuperct-2024.