IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
CURRENT SOLUTIONS, INC., ) ) Plaintiff, ) ) v. ) C.A. No. N23C-11-042 PAW ) APPOQUINIMINK SCHOOL ) DISTRICT, ) ) Defendant. )
Submitted: September 30, 2024 Decided: December 13, 2024
MEMORANDUM OPINION
Upon consideration of Defendant’s Motion to Dismiss;
DENIED, in part and GRANTED, in part.
Scott Earle, Esq., of Goldberg Segalla LLP and Judith Jones, Esq., of Zarwin Baum DeVito Kaplan Schaer Toddy PC, Attorneys for Plaintiff.
William Gamgort, Esq. and Carmella Cinaglia, Esq., of Young Conaway Stargatt & Taylor LLP, Attorneys for Defendant.
WINSTON, J. I. INTRODUCTION
Current Solutions, Inc., (“CSI”) sues Appoquinimink School District, (“the
District”) for breaches of contract and the implied covenant of good faith and fair
dealing. In response, the District moves to dismiss. CSI pleads facts supporting an
inference of breach of contract, and it is reasonably conceivable that CSI is entitled
to recover. The implied covenant claims, however, conflict with the express terms
of the agreement. Accordingly, the District’s Motion to Dismiss is DENIED, in
part and GRANTED, in part.
II. FACTUAL AND PROCEDURAL BACKGROUND1
CSI is an electrical subcontractor that was the successful bidder for the
electrical work to construct a new elementary school, Crystal Run Elementary
School (“the Project”), for the District.2 The Electrical Contract (“the Contract”)
was prepared using AIA Document A132-2019.3 The Contract sum was
$2,086,400.00.4 The Contract provides that the Project’s Construction Manager
(“CM”) will create, publish, and update or revise the formal Project Construction
1 The following facts are drawn from the Complaint and documents incorporated by reference. Windsor I, LLC v. CW Capital Asset Mgmt. LLC, 238 A.3d 863, 873 (Del. 2020). Citations in the form of “Ex. __” refer to documents attached to the Complaint. 2 Compl. ¶ 1. 3 Compl. ¶ 13. 4 Compl. ¶ 13.
2 Schedule throughout the Project’s construction.5 The Contract also provides for an
initial review and decision process overseen by the Project’s architect for certain
claims or disputes.6
By no fault of CSI, the Project was delayed from the beginning.7 To remedy
these delays, the District compressed CSI’s work schedule and engaged other
electrical subcontractors to complete CSI’s scope of work.8 This engagement led to
CSI’s constructive discharge.9 Additionally, throughout the Project, the District
failed to issue contractually required schedules and instead, issued informal
schedules on an ad hoc basis.10 Lastly, CSI contends that the District failed to pay
CSI for work performed, wrongfully projected its failures onto CSI, and wrongfully
back-charged CSI for costs attributable to the District.11 Despite the District’s
conduct, CSI performed its obligations under the Contract.12
On November 7, 2023, CSI filed its Complaint seeking damages for breach of
contract (“Count I”) and breach of covenant of good faith and fair dealing (“Count
5 Compl. ¶ 15. 6 Ex. B at Article 15 (“Claims and Disputes”). 7 Compl. ¶ 6. 8 Compl. ¶ 8. 9 Compl. ¶ 8. 10 Compl. ¶ 9. 11 Compl. ¶ 10. 12 Compl. ¶ 10.
3 II”), relating to the District’s alleged failure to pay CSI for completed electrical
work, allow CSI additional time to complete its work, and increase CSI’s fixed price
contract for the hiring of additional workers.13 In response, the District moves under
Superior Court Civil Rule 12(b)(6) for failing to state a claim upon which relief can
be granted.14
III. ANALYSIS
Upon a Rule 12(b)(6) motion, the Court accepts all well-pleaded factual
allegations as true; (2) credits vague allegations if they give the opposing party notice
of the claim; (3) draws all reasonable inferences in favor of the non-moving party;
and (4) denies dismissal if recovery on the claim is reasonably conceivable.15
When both parties present their positions and reference materials neither
incorporated into nor integral to the complaint, the Court can convert the motion to
one for summary judgment.16 However, this will not occur if “the additional
documents are incorporated by reference into the complaint and are integral to the
claims of the complaint” or “the documents are not being relied upon to prove the
13 See Compl. 14 Def. Mot. to Dismiss at Introduction. 15 Cent. Mortg. Co. v. Morgan Stanley Mortg. Cap. Holding, LLC, 27 A.3d 531, 535 (Del. 2011). 16 Driggus v. State Farm Mut. Auto. Ins. Co., 2023 WL 7599490 at *1 (Del. Super. Nov. 15, 2023).
4 truth of its contents.”17 If either of these situations exists, a conversion will not
occur.
At present, both parties submitted additional documents not incorporated by
reference. Although the documents are “being relied upon to prove the truth of its
contents” and were submitted by the parties to demonstrate the veracity of the
allegations in the Complaint, at oral arguments, both parties acknowledged the Court
should not consider the additional documents.18 Accordingly, the Court will address
the Motion by considering only the Complaint and documents incorporated by
reference.
A. COUNT I – BREACH OF CONTRACT
The allegations set forth in the Complaint are sufficient to state a breach of
contract claim, and it is reasonably conceivable that CSI is entitled to recover. For
a breach of contract claim to survive a motion to dismiss, it is sufficient to “simply
allege first, the existence of the contract; second, the breach of an obligation imposed
by that contract; and third, the resultant damage to the plaintiff.” 19
17 Cambridge Strategic Mgmt. Grg. v. IDT Domestic Telecom, Inc., 2013 WL 2480887 at *3 (Del. Super. Apr. 8, 2013). 18 The District clarified it would be comfortable with the Court not considering its submitted affidavit. CSI agreed that it believed converting the Motion to one for summary judgment would be premature without time for additional discovery. 19 Nucor Coatings Corp. v. Precoat Metals Corp., 2023 WL 6368316 at *13 (Del. Super. Aug. 31, 2023) (quoting Garfield v. Allen, 277 A.3d 296, 328 (Del. Ch.
5 CSI first alleges that the District breached the Contract by terminating CSI
without the requisite justification provided for under Section 14.2.1 of the Contract
Documents.20 CSI also alleges that the Construction Manager breached his duties
under the Contract when the CM “failed to issue or otherwise revise the Project
Construction Schedule per the requirements set forth” in Section 013216(2)(A)&(B)
or the Contract.21 The Complaint further alleges that the District breached the
Contract by failing to adjust the Contract time and sum to accommodate for the
truncated work schedule issued by the CM on an arbitrary and ad hoc-rolling basis,
a failure which breached, among other provisions, Article 7 regarding Changes in
the Work and Article 8.3 regarding Delays and Extensions of Time of the General
Conditions.22 Finally, CSI claims that the District breached Article 5 of the Contract
by failing to pay CSI for the work performed in accordance with payment
applications 7 and 8, and by routinely failing to pay CSI for its work by the 15th of
the following month.23
2022)); see also Humanigen, Inc. v. Savant Neglected Diseases, Inc., 238 A.3d 194, 202 (Del. Super. Aug.
Free access — add to your briefcase to read the full text and ask questions with AI
IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
CURRENT SOLUTIONS, INC., ) ) Plaintiff, ) ) v. ) C.A. No. N23C-11-042 PAW ) APPOQUINIMINK SCHOOL ) DISTRICT, ) ) Defendant. )
Submitted: September 30, 2024 Decided: December 13, 2024
MEMORANDUM OPINION
Upon consideration of Defendant’s Motion to Dismiss;
DENIED, in part and GRANTED, in part.
Scott Earle, Esq., of Goldberg Segalla LLP and Judith Jones, Esq., of Zarwin Baum DeVito Kaplan Schaer Toddy PC, Attorneys for Plaintiff.
William Gamgort, Esq. and Carmella Cinaglia, Esq., of Young Conaway Stargatt & Taylor LLP, Attorneys for Defendant.
WINSTON, J. I. INTRODUCTION
Current Solutions, Inc., (“CSI”) sues Appoquinimink School District, (“the
District”) for breaches of contract and the implied covenant of good faith and fair
dealing. In response, the District moves to dismiss. CSI pleads facts supporting an
inference of breach of contract, and it is reasonably conceivable that CSI is entitled
to recover. The implied covenant claims, however, conflict with the express terms
of the agreement. Accordingly, the District’s Motion to Dismiss is DENIED, in
part and GRANTED, in part.
II. FACTUAL AND PROCEDURAL BACKGROUND1
CSI is an electrical subcontractor that was the successful bidder for the
electrical work to construct a new elementary school, Crystal Run Elementary
School (“the Project”), for the District.2 The Electrical Contract (“the Contract”)
was prepared using AIA Document A132-2019.3 The Contract sum was
$2,086,400.00.4 The Contract provides that the Project’s Construction Manager
(“CM”) will create, publish, and update or revise the formal Project Construction
1 The following facts are drawn from the Complaint and documents incorporated by reference. Windsor I, LLC v. CW Capital Asset Mgmt. LLC, 238 A.3d 863, 873 (Del. 2020). Citations in the form of “Ex. __” refer to documents attached to the Complaint. 2 Compl. ¶ 1. 3 Compl. ¶ 13. 4 Compl. ¶ 13.
2 Schedule throughout the Project’s construction.5 The Contract also provides for an
initial review and decision process overseen by the Project’s architect for certain
claims or disputes.6
By no fault of CSI, the Project was delayed from the beginning.7 To remedy
these delays, the District compressed CSI’s work schedule and engaged other
electrical subcontractors to complete CSI’s scope of work.8 This engagement led to
CSI’s constructive discharge.9 Additionally, throughout the Project, the District
failed to issue contractually required schedules and instead, issued informal
schedules on an ad hoc basis.10 Lastly, CSI contends that the District failed to pay
CSI for work performed, wrongfully projected its failures onto CSI, and wrongfully
back-charged CSI for costs attributable to the District.11 Despite the District’s
conduct, CSI performed its obligations under the Contract.12
On November 7, 2023, CSI filed its Complaint seeking damages for breach of
contract (“Count I”) and breach of covenant of good faith and fair dealing (“Count
5 Compl. ¶ 15. 6 Ex. B at Article 15 (“Claims and Disputes”). 7 Compl. ¶ 6. 8 Compl. ¶ 8. 9 Compl. ¶ 8. 10 Compl. ¶ 9. 11 Compl. ¶ 10. 12 Compl. ¶ 10.
3 II”), relating to the District’s alleged failure to pay CSI for completed electrical
work, allow CSI additional time to complete its work, and increase CSI’s fixed price
contract for the hiring of additional workers.13 In response, the District moves under
Superior Court Civil Rule 12(b)(6) for failing to state a claim upon which relief can
be granted.14
III. ANALYSIS
Upon a Rule 12(b)(6) motion, the Court accepts all well-pleaded factual
allegations as true; (2) credits vague allegations if they give the opposing party notice
of the claim; (3) draws all reasonable inferences in favor of the non-moving party;
and (4) denies dismissal if recovery on the claim is reasonably conceivable.15
When both parties present their positions and reference materials neither
incorporated into nor integral to the complaint, the Court can convert the motion to
one for summary judgment.16 However, this will not occur if “the additional
documents are incorporated by reference into the complaint and are integral to the
claims of the complaint” or “the documents are not being relied upon to prove the
13 See Compl. 14 Def. Mot. to Dismiss at Introduction. 15 Cent. Mortg. Co. v. Morgan Stanley Mortg. Cap. Holding, LLC, 27 A.3d 531, 535 (Del. 2011). 16 Driggus v. State Farm Mut. Auto. Ins. Co., 2023 WL 7599490 at *1 (Del. Super. Nov. 15, 2023).
4 truth of its contents.”17 If either of these situations exists, a conversion will not
occur.
At present, both parties submitted additional documents not incorporated by
reference. Although the documents are “being relied upon to prove the truth of its
contents” and were submitted by the parties to demonstrate the veracity of the
allegations in the Complaint, at oral arguments, both parties acknowledged the Court
should not consider the additional documents.18 Accordingly, the Court will address
the Motion by considering only the Complaint and documents incorporated by
reference.
A. COUNT I – BREACH OF CONTRACT
The allegations set forth in the Complaint are sufficient to state a breach of
contract claim, and it is reasonably conceivable that CSI is entitled to recover. For
a breach of contract claim to survive a motion to dismiss, it is sufficient to “simply
allege first, the existence of the contract; second, the breach of an obligation imposed
by that contract; and third, the resultant damage to the plaintiff.” 19
17 Cambridge Strategic Mgmt. Grg. v. IDT Domestic Telecom, Inc., 2013 WL 2480887 at *3 (Del. Super. Apr. 8, 2013). 18 The District clarified it would be comfortable with the Court not considering its submitted affidavit. CSI agreed that it believed converting the Motion to one for summary judgment would be premature without time for additional discovery. 19 Nucor Coatings Corp. v. Precoat Metals Corp., 2023 WL 6368316 at *13 (Del. Super. Aug. 31, 2023) (quoting Garfield v. Allen, 277 A.3d 296, 328 (Del. Ch.
5 CSI first alleges that the District breached the Contract by terminating CSI
without the requisite justification provided for under Section 14.2.1 of the Contract
Documents.20 CSI also alleges that the Construction Manager breached his duties
under the Contract when the CM “failed to issue or otherwise revise the Project
Construction Schedule per the requirements set forth” in Section 013216(2)(A)&(B)
or the Contract.21 The Complaint further alleges that the District breached the
Contract by failing to adjust the Contract time and sum to accommodate for the
truncated work schedule issued by the CM on an arbitrary and ad hoc-rolling basis,
a failure which breached, among other provisions, Article 7 regarding Changes in
the Work and Article 8.3 regarding Delays and Extensions of Time of the General
Conditions.22 Finally, CSI claims that the District breached Article 5 of the Contract
by failing to pay CSI for the work performed in accordance with payment
applications 7 and 8, and by routinely failing to pay CSI for its work by the 15th of
the following month.23
2022)); see also Humanigen, Inc. v. Savant Neglected Diseases, Inc., 238 A.3d 194, 202 (Del. Super. Aug. 17, 2020) (quoting Garfield, 277 A.3d at 328). 20 Compl. ¶ 42. 21 Compl. ¶ 43. 22 Compl. ¶ 44. 23 Compl. ¶ 45.
6 The District contends that CSI’s breach of contract claim must be dismissed
due to failure to satisfy preconditions to litigation required under the Contract. In
its Motion, the District states that “where a contract is clear and unambiguous in
requiring that a condition precedent to litigation be satisfied before a lawsuit is
initiated, failure to meet such condition constitutes a material breach of the contract
and a forfeiture of rights.”24 Under the Contract, an initial decision from the architect
“shall be required as a condition precedent to mediation” of a claim, and a mediation
is a condition precedent to filing suit regarding such a claim.25 Thus, the District
argues that CSI’s failure to demonstrate that specific conditions precedent were
satisfied forfeited its rights to bring a claim for breach of contract.
Under Delaware law, to recover damages for a breach of contract, the plaintiff
must demonstrate substantial compliance with all of the provisions of the contract.26
“[A] party may only be excused from performance of a contract when the other party
24 Def.’s Mot. to Dismiss at 4 (citing Millsboro Fire Co. v. Constr. Mgmt. Serv., Inc., 2009 WL 846614 at *4 (Del. Super. Mar. 31, 2009)). 25 Ex. B at Article 15.2.1 (“General Conditions”). 26 Commonwealth Const. Co. v. Cornerstone Fellowship Baptist Church, Inc., 2006 WL 2567916 at *19 (Del. Super. Aug. 31, 2006) (citing Eastern Elec. & Heating Inc. v. Pike Creek Prof'l Ctr., 1987 WL 9610 at *4 (Del. Super. April 7, 1987)) (citing Emmett Hickman Co. v. Emilio Capano Developer, Inc., 251 A.2d 571 (Del. Super. 1969)).
7 has materially breached the contract.”27 Likewise, a party in material breach of the
contract cannot then complain if the other party fails to perform. 28 Performance
under a contract is justifiably excused when the other party to the contract commits
a material breach.29 Whether a breach is material is a fact-sensitive analysis.30
CSI alleges it met all its performance obligations under the Contract and was
constructively discharged. At oral argument, CSI argued that its discharge was a
material breach of the Contract which excused its performance of the condition
precedent. CSI’s allegations, coupled with the District’s alleged breaches of
contract, create a reasonable inference that CSI is excused from the preconditions of
mediation and additional claim submission under the Contract. Accordingly, any
factual disputes, including the applicability of the preconditions to litigation within
the Contract, will not be resolved in the current procedural posture.31
27 Daystar Const. Mgmt., Inc. v. Mitchell, 2006 WL 2053649 at *7 (Del. Super. July 12, 2006). 28 Commonwealth Const. Co. v. Cornerstone Fellowship Baptist Church, Inc., 2006 WL 2567916 at *19 (Del. Super. Aug. 31, 2006) (citing Hudson v. D & v. Mason Contractors, Inc., 252 A.2d 166 (Del.Super. 1969)). 29 Id. (citing Eastern Elec. & Heating Co. v. Pike Creek Prof’l Ctr., 1987 WL 9610 at *4 (Del. Super. April 7, 1987)). 30 Id. (citing SLMSoft.com, Inc. v. Cross Country Bank, 2003 WL 1769770 at *13 (Del. Super. April 2, 2003)). 31 See Bryant v. Way, 2011 WL 2163606 at *3 (Del. Super. May 25, 2011) (“Factual issues cannot be resolved at the motion to dismiss stage…”).
8 Next, the District contends that there was no breach of the Contract because
it had “the right to assign work to other contractors where Plaintiff failed to carry
out the work in accordance with the terms of the Contract,”32 and it exercised this
right following CSI’s failure to complete its obligations.33 The Court cannot
determine on the pleadings whether the District materially breached the Contract
terms.34 For now, the claims cannot be dismissed on the pleadings because, until the
material breach issue is decided, the allegations that the reassignment of all Contract
duties acted as a termination must be accepted as true.
The Complaint alleges that the District had no cause under Section 14.2.1 to
terminate CSI.35 And, even if cause existed, the District failed to abide by the notice
provision in Section 14.2.2.36 Drawing all reasonable inferences in favor of the non-
moving party, the Court finds that it is reasonably conceivable that CSI is entitled to
recover on its breach of contract claim.
The Court finds that CSI has sufficiently pled the basic elements of a breach
of contract claim. CSI has alleged the existence of a contract, an alleged breach of
32 See Ex. B, General Conditions §§ 2.5 (Owner’s Right to Carry Out Work); 12.2 (Correction of Work). 33 Def. Mot. to Dismiss ¶ 15. 34 See SphereCommerce, LLC v. Caulfield, 2022 WL 325952 at *9 (Del. Ch. Feb. 2, 2022). 35 Compl. ¶ 42. 36 Compl. ¶24.
9 the terms of the Contract, and resulting damage. Further, CSI generally pled it had
met all its performance obligations under the Contract.37 Thus, the facts and
allegations set forth in the Complaint are sufficient to state a breach of contract
claim, and it is reasonably conceivable that CSI is entitled to recover.
B. COUNT II – BREACH OF THE IMPLIED COVENANT OF GOOD FAITH AND FAIR DEALING
The allegations set forth in the Complaint do not sufficiently state a claim for
breach of the implied covenant of good faith and fair dealing. In Merill v. Crothall-
American, Inc.,38 the Delaware Supreme Court held that every employment contract
includes an implied covenant of good faith and fair dealing. Under the implied
covenant, an employer may be liable on a contract claim if they act in bad faith in
the hiring or firing of an employee.39 To properly plead a claim for breach of the
implied covenant, Plaintiff must allege some injury to its contractual interest because
of the breach of the implied obligation.40 In summary, Plaintiff must allege: (1) a
37 Plaintiff generally averred that it complied with all obligations under the Contract when stating that the District had no basis under Section 14.2.1 to terminate CSI from the Project. Compl. ¶ 27. See Eisenmann Corp. v. General Motors Corp., 2000 WL 140781, at *18 (Del. Super. Jan. 28, 2000), cert. denied (denying defendant’s motion to dismiss based on plaintiff's failure to plead specific conditions precedent were satisfied when plaintiff “certainly alleges complete performance generally.”). 38 606 A.2d 96, 101 (Del.1992). 39 Id. 40 Kuroda v. SPJS Holdings, LLC, 971 A.2d 872, 888-89 (Del. Ch. 2009).
10 specific implied contractual obligation; (2) a breach of that obligation; and (3)
resulting damage.41
The implied covenant of good faith and fair dealing, however, infers
contractual terms to handle developments or contractual gaps that neither party
anticipated.42 Thus, the implied covenant does not apply when the express terms of
the contract govern the subject of the conduct at issue.43
Here, CSI alleges that the District breached the implied covenant through (1)
systematically assigning work covered by the Contract to other electrical trade
contractors; (2) establishing commercially unreasonable and arbitrary deadlines for
the completion of Plaintiff’s work; and (3) excessively back charging Plaintiff for
supplemental work performed by other contractors to offset the amount owed under
the Contract.44
CSI’s claims for breach of the implied covenant address the same allegations
raised in its claim for breach of contract.45 Accordingly, each of these alleged
breaches are covered by express contractual provisions. The Contract addressed the
41 Id. 42 Nationwide Emerging Managers, LLC v. Northpointe Holdings, LLC, 112 A.3d 878, 896 (Del. Mar. 28, 2015) (emphasis added). 43 Id. 44 Compl. ¶¶ 48-51. 45 See Compl. ¶¶ 42-45; see also Compl. ¶¶ 48-51. CSI also seeks damages in the same amount (“in excess of $470,705.00”) for both claims. See Compl. ¶¶ 46, 51.
11 Project schedule and the rights of the parties to modify that schedule in Article 3.46
The Contract authorized the District to engage other labor where CSI failed to meet
its contractual obligations under Sections 2.5 (Owner’s Right to Carry Out Work)
and 12.2 (Correction of Work), and, in the event that the District intended to reassign
the remainder of the Contract, the Contract provided a process for termination with
cause under Section 14.2 (Termination by the Owner for Cause). Finally, the
Contract granted the District the right to perform uncompleted work called for by
the agreement and back charge CSI for said work if CSI failed to perform as
required.47
Any factual disputes regarding whether CSI failed to perform under the
Contract cannot be determined at this juncture.48 At this early stage, the Court must
accept both sides’ well-pled allegations as true.49 Accordingly, the Court finds that
the conduct at issue is covered under express contractual provisions; however, the
46 Ex. B § 3.10.1 (“The schedule shall be revised at appropriate intervals as required by the conditions of the Work and Project.”); Ex. B § 3.10.3 (“The Contractor shall make revisions to the construction schedule and submittal schedule as deemed necessary by the Construction Manager to conform to the Project schedule.”). 47 Ex. B, General Conditions § 2.5 (“If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents… the Owner may, without prejudice to other remedies the Owner may have, correct such a default or neglect. […] If current and future payments are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner.”). 48 Bryant, 2011 WL 2163606 at *3. 49 Cent. Mortg. Co., 27 A.3d at 535.
12 Court will not determine at this time whether the conduct at issue was a material
breach under the Contract.
Thus, the facts here do not implicate the implied covenant of good faith and
fair dealing. Simply mirroring the factual allegations that support a breach of
contract claim is insufficient to state a claim for breach of the implied covenant of
good faith and fair dealing.50
More, the Court finds that the implied covenant of good faith and fair dealing
cannot be pled in the alternative if the Plaintiff’s breach of contract claim does not
survive under these circumstances.51 Here, CSI does not plead an unanticipated
development or contractual gap; it simply realleges its breach of contract claim as
an implied covenant claim.52 Accordingly, the Court finds that CSI’s claim for
breach of the implied covenant of good faith and fair dealing cannot be pled in the
alternative to breach of contract and must be dismissed.
50 See 3M Company v. Neology, Inc., 2019 WL 2714832 at *10 (Del. Super. June 28, 2019). 51 3M Company, 2019 WL 2714832 at *11 (holding that the implied covenant of good faith and fair dealing cannot be plead in the alternative where the alleged breach of the implied covenant mirrors the factual allegations used to support a breach of contract claim). 52 Id.
13 IV. CONCLUSION
For the reasons stated herein, the District’s Motion to Dismiss DENIED, in
IT IS SO ORDERED.
/s/ Patricia A. Winston Patricia A. Winston, Judge