H.R. Miller Co. v. Board of Supervisors

605 A.2d 321, 529 Pa. 478, 1992 Pa. LEXIS 252
CourtSupreme Court of Pennsylvania
DecidedMarch 27, 1992
Docket31 E.D. Appeal Docket 1990
StatusPublished
Cited by24 cases

This text of 605 A.2d 321 (H.R. Miller Co. v. Board of Supervisors) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H.R. Miller Co. v. Board of Supervisors, 605 A.2d 321, 529 Pa. 478, 1992 Pa. LEXIS 252 (Pa. 1992).

Opinions

OPINION OF THE COURT

ZAPPALA, Justice.

H.R. Miller Company, Inc., challenged the Lancaster Township zoning ordinance, claiming that it excluded a legitimate commercial use, i.e., quarrying. In conjunction [480]*480with its challenge, the Company submitted a proposed curative amendment, suggesting that the deficiency be corrected by amending the zoning map to include a Mineral Recovery District encompassing land owned by the Company. The township board of supervisors dismissed the Company’s challenge and denied its request for curative amendment, but on appeal, the court of common pleas accepted the Company’s argument that the ordinance operated as a de facto exclusion of quarries. Notwithstanding this finding, the court did not grant the Company “site-specific relief” as to any aspect of its proposed use. The court limited its remedy to a declaration that certain setback requirements contained in the ordinance, which had the effect of limiting the area where quarrying was a permitted use, be stricken. Commonwealth Court affirmed. We granted allowance of appeal to review the Company’s claim that the court, having found the ordinance to be exclusionary, was required to grant site-specific relief or, at the least, to order the plan approved in some part and refer other elements of the Company’s plan to the governing body for further proceedings.

H.R. Miller Company, Inc., operates a limestone quarry on twenty-nine acres of land in the southwest portion of Lancaster Township. The quarry has existed since approximately 1890. When the township enacted its first zoning ordinance in 1940, the area where the quarry is located was zoned as “agricultural”. The following year, the Company’s predecessor in title was successful in petitioning the Township to rezone the land “industrial”. The Company acquired the quarry sometime before 1960. In that year, the Township revised its zoning ordinance and the area was rezoned “residential”. It remained so classified when the ordinance was again revised in 1972. The Company’s operation thus continues as a pre-existing non-conforming use. The Company has also purchased several tracts of adjacent property in the residential district, currently owning a total of one hundred seventeen acres.

[481]*481When the Company filed its challenge to the zoning ordinance in 1986, the ordinance permitted quarry operations as a special exception in the Township’s “industrial” districts. The challenge, therefore, was not a claim of de jure exclusion of a legitimate use. Rather, the Company argued that quarrying had been excluded de facto because several factors — the limited size of the industrial districts, the requirement that any quarry pit be set back 500 feet from property lines and street rights-of-way, and the existing land uses — combined to make such operations physically impossible or economically unfeasible.

In hearings before the Township’s Board of Supervisors, the Company presented evidence of the dimensions of the largest quarry pit that could be located in the largest industrial district. It also presented economic evidence of the cost of acquiring the various parcels of land in the district and other production costs, along with testimony of company officials that given these costs a quarry of such size would not yield enough stone to make it profitable. The Township presented different estimates of the sizes and configurations of quarry pits that could be located in the industrial zone. It also challenged the accuracy and the significance of the Company’s economic evidence in cross-examining the Company’s witnesses, but did not introduce its own evidence on these points.

The Supervisors rejected the Company’s economic evidence as unsubstantiated and self-serving. The Supervisors also interpreted the ordinance’s buffer zone requirements such that the land dedicated to the 500 foot setback need not be within the industrial district, thus making a substantially greater area available within the industrial zone to place a quarry pit. According to this interpretation, the Supervisors determined that sufficient stone reserves would be available to surpass the “break-even point” even according to the Company’s estimates, and thus that operation of a quarry was both geographically and financially feasible.

The Court of Common Pleas held that the Supervisors’ rejection of the Company’s economic evidence constituted a [482]*482manifest abuse of discretion and found that the Company had partially carried its burden of showing de facto exclusion. The court also found that the difficulty of acquiring the parcels that were already in use for residential and industrial purposes at the time the area was designated an industrial district, would present an obstacle to any attempt to locate a quarry there. The combination of these factors led the court “to hold that [the Supervisors] lacked substantial evidence to conclude that quarries are not excluded.” Opinion at 10.

The court further determined that the Supervisors committed an error of law in ruling that land outside the industrial zone could be committed to use as a buffer area for a quarry located in the industrial zone. Finding that a five hundred foot setback requirement was, in the language of the statute, “not reasonably related to the municipality’s authority to determine its physical growth pattern, protect the Commonwealth’s public natural resources, coordinate development with the provision of public services, or protect the character of the community,” the court held “that Section 1302(2)(c) [the setback provision] acts as an unconstitutional de facto exclusion of quarries from the Township.” Opinion at 12.

The next part of the court’s opinion was devoted to a determination of whether to grant the site-specific relief requested by the Company. Citing Fernley v. Board of Supervisors of Schuylkill Township, 509 Pa. 413, 425, 502 A.2d 585, 591 (1985), the court stated that site-specific relief was not automatic, but could be rejected if the Supervisors could show that the plan was incompatible with the proposed site. The court examined the five factors then found in Section 1011(2) of the Municipalities Planning Code.1 [483]*483Although it found “no evidence that the proposed quarry expansion would adversely affect the environment in any material way,” the court concluded “that the comprehensive and progressive residential character of the southwestern portion of the Township outweighs any environmental considerations, especially in light of the fact that the Conestoga Limestone Formation underlies the industrially zoned districts as well.” Opinion at 15. For this reason, the court held the Company’s site unsuitable for quarry operations and denied site-specific relief. The court went on to state that “[a]s only the five hundred foot setback limitation has been brought to issue and addressed by this Court, it would be erroneous to declare the entire Ordinance invalid where a severability provision exists.”2 Accordingly, the court held that Section 1302(2)(c) was to be stricken from the ordi[484]*484nance, leaving in its place the minimum setbacks required by state regulations.

The Company argues that the lower courts erred in interpreting Section 1011(2) and Femley as permitting the total denial of site-specific relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Apr. 24 Dec. Apl of: Charlestown Outdoor
Supreme Court of Pennsylvania, 2022
Seneca Resources Corp. v. City of St. Marys ZHB
Commonwealth Court of Pennsylvania, 2021
Bloomsburg Industrial Ventures, LLC v. Town of Bloomsburg
Commonwealth Court of Pennsylvania, 2020
Wimer Realty, LLC v. Township of Wilmington
206 A.3d 627 (Commonwealth Court of Pennsylvania, 2019)
L. Shortt and S. Shortt v. East Marlborough Twp. ZHB
Commonwealth Court of Pennsylvania, 2017
Leone v. Borough of Rochester
Commonwealth Court of Pennsylvania, 2015
In re the Bartkowski Investment Group, Inc.
106 A.3d 230 (Commonwealth Court of Pennsylvania, 2014)
Atiyeh v. BD. OF COM'RS OF TP. OF BETHLEHEM
41 A.3d 232 (Commonwealth Court of Pennsylvania, 2012)
Piper Group, Inc. v. Bedminster Township Board of Supervisors
30 A.3d 1083 (Supreme Court of Pennsylvania, 2011)
Township of Exeter v. Zoning Hearing Board
962 A.2d 653 (Supreme Court of Pennsylvania, 2009)
Ethan-Michael, Inc. v. Board of Supervisors of Union Township
918 A.2d 203 (Commonwealth Court of Pennsylvania, 2007)
Caln Nether Co., L.P. v. Board of Supervisors
840 A.2d 484 (Commonwealth Court of Pennsylvania, 2004)
Allegheny Energy Supply Co. v. Township of Blaine
829 A.2d 1254 (Commonwealth Court of Pennsylvania, 2003)
Hager v. West Rockhill Township Zoning Hearing Board
795 A.2d 1104 (Commonwealth Court of Pennsylvania, 2002)
Polay v. BOARD OF SUP'RS OF WEST VINCENT TOWNSHIP
752 A.2d 434 (Commonwealth Court of Pennsylvania, 2000)
County of Beaver v. Borough of Beaver Zoning Hearing Board
656 A.2d 157 (Commonwealth Court of Pennsylvania, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
605 A.2d 321, 529 Pa. 478, 1992 Pa. LEXIS 252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hr-miller-co-v-board-of-supervisors-pa-1992.