Houston-New Orleans, Inc. v. Page Engineering Company

353 F. Supp. 890, 1972 U.S. Dist. LEXIS 11139
CourtDistrict Court, E.D. Louisiana
DecidedNovember 14, 1972
DocketCiv. A. 67-1819
StatusPublished
Cited by30 cases

This text of 353 F. Supp. 890 (Houston-New Orleans, Inc. v. Page Engineering Company) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Houston-New Orleans, Inc. v. Page Engineering Company, 353 F. Supp. 890, 1972 U.S. Dist. LEXIS 11139 (E.D. La. 1972).

Opinion

ALVIN B. RUBIN, District Judge:

This is a suit by the owner of a barge against the supplier of equipment and against the repairman who installed it, both on a theory of negligence and for breach of warranty. Shortly after a new control panel was installed in a crane mounted on a barge, the VELMO-R, in May, 1967, the boom of the crane struck one of the spuds on the barge and caused extensive damage. Houston-New Orleans, Inc. (HNO), the owner of the dragline barge, had ordered the control panel from Page Engineering Co. (Page). Creole Electric Service (Creole) had installed it. HNO contends the damage resulted from defects in the panel supplied by Page and negligence in its installation by Creole. The defendants each contend the operator of the dragline was at fault and that HNO was at fault for operating it; and, alternatively, that the damage resulted from the fault of the other defendant.

The trial was repeatedly delayed, the facts have become hazy, the issues are complicated, the briefs are long. But, considered and reconsidered, the evidence now available points to the conclusion that the negligence of all three of the parties contributed to cause the damage, and, as such, damages ought to be shared under the principle of comparative negligence.

I — FACTS

A. UNCONTESTED FACTS

This much is uncontested. In February, 1967, the VELMO-R had a collision with another vessel. The dragline mounted on the barge was damaged, and it was necessary to replace its control panel. HNO ordered a new panel from Page. Meanwhile, it continued to operate the dragline with the original control panel (as repaired by Creole) aboard the barge, which was afloat in navigable waters. In May, HNO received the new control panel in New Orleans, shipped it to a borrow bit on the East Atchafalaya Levee System, near Bayou Sorrel, Louisiana, took the barge off its job, and floated it to the pit. Creole’s employees came there to install the new panel on Friday, May 26, 1967.

After Creole had installed the panel, it could not obtain the electrical test results required by Page’s specifications. The machine operators tested the machine and complained that it was sluggish in its swinging operation. In other words, the boom operated more slowly than the operators were accustomed to, and responded more slowly to a change of direction than it should have.

B. CONTROVERTED FACTS

At this point, accounts begin to conflict. I conclude however that the events were as follows: Creole’s electrician reported to HNO that there was a problem in connection with the control panel that he could not identify, the machine was sluggish, and it was necessary to be careful in its operation, but that it was operational and could be restored to duty. So the barge was floated back to its work site and operations were resumed.

The next day Creole’s superintendent checked the control panel, and reported to HNO’s President. He stated that he still could not reach proper test results, but he did not at any time suggest that this made it advisable to take the machine out of service. Creole, who had worked on the dragline before and rendered other services to HNO as a regular customer, knew that the machine was usually operated 24 hours a day and that there was a great loss of revenue when it was out of service, and was doubtless reluctant to take the firm stand that later events indicated would have been desirable, but Creole’s superintendent did caution the operators to be careful.

The boom on the dragline is controlled by electrical action, and stopped *894 by reverse electrical action; this first retards the swing then brings it to a stop. The resistors in the control panel govern the electrical current that causes reversal of the swing. Since they were not adequate when first installed, the machine functioned improperly. Sometime later it was discovered that Page had equipped the control panel with an improper set of resistors, and that this caused the sluggishness in the boom’s swing.

A short time after the call from Creole’s superintendent, the dragline boom hit the barge’s spud. The boom was damaged, and the crane was taken out of operation for repair. The old resistor bank was reinstalled, and the dragline worked properly. Thereafter Page supplied a new (and properly sized) resistor bank, it was installed by Creole, the readings required by the manufacturer’s specifications were reached, and the dragline has since operated uneventfully.

C. FURTHER FACT FINDINGS AND FACTUAL CONCLUSIONS

A preponderance of the evidence supports the following findings:

Because the resistors first supplied with the control panel were the wrong size, they could not be adjusted to reach specifications. This should have caused the electrician to suspect that the resistors supplied were not the correct ones. In addition, it would have been evident from visual examination by an electrician familiar with the old panel, as Creole’s employees were, that the resistors in the new panel were smaller than the ones that had been used before, and hence that they were possibly wrong. That fact could also have been discovered by comparing the serial numbers on the two sets of resistors. None of these observations were made, and the fact that improper resistors had been supplied was discovered only after the harm was done. Although Creole’s employees cautioned the dragline operators to be careful, they never recommended that the machine be kept idle, and, indeed, watched it in operation without suggesting that its return to service be delayed.

II. THE CAUSE OF THE CASUALTY

A moment before the damage occurred the dragline boom was in motion. The operator (who had replaced the operator present when Creole’s employees were on the site) took the steps to stop its swing, but perceived that it was not stopping properly. He immediately dropped the dragline bucket into the water to retard the boom’s swing and avoid the damage that might occur if the bucket itself continued to swing. Had the controls been operating properly the boom would have stopped. The crash was not the result of operational error but of the defective control panel. There is some evidence that his supervisor had not warned this operator to be careful, but he was aware of the sluggish operation and hence knew all that his supervisor did with respect to the operational problem.

The evidence does not demonstrate the precise nature of the defect in the control panel caused the casualty. But had there been a proper resistor bank it would not have occurred.

Judgment in law suits is not based on scientific certainty. It is based on a preponderance of the evidence. By that test operational fault is eliminated. The operator was a credible and convincing witness. He testified that the boom did not stop when he reversed, he dropped the bucket, the boom continued to travel, and struck the spud.

The post accident photographs can be interpreted in various ways — witness the elaborate geometry of the opposing briefs, each based on different supposed arcs and each purportedly demonstrating with the certainty of Euclidean proof of a geometric theorem that the event occurred in only one way, each of course different. But in my view the photographs tend to support the operator’s testimony.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penn Maritime, Inc. v. Rhodes Electronic Services, Inc.
41 F. Supp. 3d 507 (E.D. Louisiana, 2014)
In re the Complaint of ENSCO Offshore Co.
9 F. Supp. 3d 713 (S.D. Texas, 2014)
F.W.F., Inc. v. Detroit Diesel Corp.
494 F. Supp. 2d 1342 (S.D. Florida, 2007)
Saudi v. S/T MARINE ATLANTIC
159 F. Supp. 2d 492 (S.D. Texas, 2000)
Prestenbach v. Louisiana Power & Light
638 So. 2d 234 (Louisiana Court of Appeal, 1994)
Orbis Marine Enterprises, Inc. v. TEC Marine Lines, Ltd.
692 F. Supp. 280 (S.D. New York, 1988)
Jones v. Berwick Bay Oil Co., Inc.
697 F. Supp. 260 (E.D. Louisiana, 1988)
Ingram River Equipment v. Pott Industries, Inc.
573 F. Supp. 896 (E.D. Missouri, 1983)
Cunningham v. Rendezvous, Inc.
699 F.2d 676 (Fourth Circuit, 1983)
Lyons v. Parish of Jefferson
425 So. 2d 955 (Louisiana Court of Appeal, 1983)
Gerard Construction, Inc. v. Motor Vessel Virginia
480 F. Supp. 488 (W.D. Pennsylvania, 1979)
Miller Industries, Inc. v. Caterpillar Tractor Co.
473 F. Supp. 1147 (S.D. Alabama, 1979)
Todd Shipyards Corp. v. Turbine Service, Inc.
467 F. Supp. 1257 (E.D. Louisiana, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
353 F. Supp. 890, 1972 U.S. Dist. LEXIS 11139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/houston-new-orleans-inc-v-page-engineering-company-laed-1972.