Housing & Redevelopment Authority for Crookston v. Agassiz Construction, Inc.

476 N.W.2d 781, 16 U.C.C. Rep. Serv. 2d (West) 132, 1991 Minn. App. LEXIS 1031, 1991 WL 223086
CourtCourt of Appeals of Minnesota
DecidedNovember 5, 1991
DocketC6-91-600
StatusPublished
Cited by6 cases

This text of 476 N.W.2d 781 (Housing & Redevelopment Authority for Crookston v. Agassiz Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Housing & Redevelopment Authority for Crookston v. Agassiz Construction, Inc., 476 N.W.2d 781, 16 U.C.C. Rep. Serv. 2d (West) 132, 1991 Minn. App. LEXIS 1031, 1991 WL 223086 (Mich. Ct. App. 1991).

Opinion

OPINION

HUSPENI, Judge.

On appeal from summary judgment, appellants allege the trial court erred when it applied the UCC statute of limitations to this case and barred their third-party indemnification actions which were based on a breach of warranty that arose out of a sale of goods. We affirm.

FACTS

In March 1990, respondent Housing and Redevelopment Authority for Crookston, Mn (HRA) contracted with appellant Engineers-Architects, PC and Cal Marjamaa (Engineers/Architeets) to provide engineering and architectural services in remodeling a building. In May 1981, HRA contracted with appellant Agassiz Construction (Agassiz), a general contractor, to remodel the building.

*783 Agassiz ordered material for the building from C & B Sales, a company which has not responded to this lawsuit and which the parties believe has gone out of business. C & B ordered lumber from respondent Northwest Wholesale Lumber (NW Lumber). By specification, this lumber was to be specially treated with a fire retardant, and suitable for framing the exterior walls of the remodeling project. On June 25, 1981, NW Lumber delivered to Agassiz the load of lumber which purportedly met these specifications. Agassiz began construction August 31, 1981 and completed the project on October 1, 1982.

During an inspection of the building on September 18,1984 and again on March 13, 1986, HRA observed a discoloration in the stucco on the exterior of the building. Upon further investigation, HRA discovered that the lumber which NW Lumber had provided was meant for interior use, not exterior use as required here. As a result, the chemical reaction between the treated lumber and condensation caused the lumber to bleed and discolor the stucco. For purposes of summary judgment and this appeal, the parties agree to these facts and concede that no genuine issues of material fact exist in this case.

On August 13,1986, HRA sued appellant Agassiz for negligence and breach of warranties. On September 12, 1986, HRA amended its complaint to include appellant Engineers/Architects as defendants, alleging negligent supervision. Both appellants brought a third-party action for contribution and indemnification against NW Lumber on May 15, 1987, alleging negligence, breach of contract and breach of warranty. The trial court denied respondent NW Lumber’s first motion to dismiss. Upon reconsideration, however, the court found that Minn.Stat. § 336.2-725 (1990) governs this action, granted respondent’s second motion for summary judgment, and dismissed appellants’ complaint with prejudice.

ISSUES

1. Did the trial court err as a matter of law when it granted respondent’s motion for summary judgment based on its determination that the UCC statute of limitations bars appellants’ action for indemnification arising from a breach of warranty?

2. Does Minn.Stat. § 336.2-725 violate appellants’ constitutional right to due process?

ANALYSIS

I.

On appeal from summary judgment, the appellate court must determine whether genuine issues of material fact exist and whether the trial court erred in its application of the law. Niccum v. Hydra Tool Corp., 438 N.W.2d 96, 98 (Minn.1989). Since the parties concede that no genuine issues of material fact exist, this court need only review the trial court’s legal conclusions. When reviewing questions of law, this court need not defer to the conclusions of the trial court. Dahlheimer v. City of Dayton, 441 N.W.2d 534, 536 (Minn.App.1989), pet. for rev. denied (Minn. Aug. 15, 1989).

This case arises from a commercial transaction for the sale of lumber. The Uniform Commercial Code (UCC) provides the sole remedy for economic losses due to property damage resulting from a commercial transaction, and allows no recovery under tort theories of negligence or strict products liability. Hapka v. Paquin Farms, 458 N.W.2d 683, 688 (Minn.1990) (overruling broader holding of Superwood Corp. v. Siempelkamp Corp., 311 N.W.2d 159, 162 (Minn.1981) which allowed tort recovery of economic losses for “personal injury or damage to other property” arising out of commercial transactions). The UCC was intended to displace tort liability and thus provides “a complete and independent statutory scheme enacted for the governance of all commercial transactions.” Hapka, 458 N.W.2d at 688.

In Minnesota, the UCC statute of limitations for actions arising out of the sale of goods is codified at Minn.Stat. § 336.2-725 (1990):

(1) An action for breach of any contract for sale must be commenced within four *784 years after the cause of action has accrued.
# * * * % *
(2) A cause of action accrues when the breach occurs, regardless of the aggrieved party’s lack of knowledge of the breach. A breach of warranty occurs when the tender of delivery is made.

The cause of action underlying appellants’ claim for indemnity arises solely out of a sale of goods; Agassiz, as buyer, purchased the lumber from NW Lumber, the seller. Minnesota case law has held consistently that Minn.Stat. § 336.2-725 governs breach of warranty claims arising from such a commercial transaction. See City of Willmar v. Short-Elliott-Hendrickson, Inc., 475 N.W.2d 73, 79 (Minn.1991); Valley Farmers’ Elevator v. Lindsay Bros. Co., 398 N.W.2d 553, 556-57 (Minn.1987); TCF Bank & Sav., F.A. v. Marshall Truss Systems, Inc., 466 N.W.2d 49, 52 (Minn.App.1991), pet. for rev. denied (Minn. Apr. 29, 1991). Appellants’ cause of action for breach of warranty accrued when NW Lumber tendered delivery of the treated lumber in June 1981. Appellants brought their third-party claim in 1987, well beyond the statutory four-year limit. 1

Appellants and amicus curiae argue that an indemnification action coupled with the breach of warranty claim distinguishes this case from Hapka, removes it from the realm of regular breach of warranty cases governed by the UCC, and brings it within the provisions of Minn.Stat. § 541.051, subd. 1 (1990) which provides:

(a) Except where fraud is involved, no action by any person in contract, tort, or otherwise to recover damages for any injury to property, real or personal, or for bodily injury or wrongful death,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hydrite Chemical Co. v. Calumet Lubricants Co.
47 F.3d 887 (Seventh Circuit, 1995)
Minnesota Mining & Manufacturing Co. v. Nishika Ltd.
885 S.W.2d 603 (Court of Appeals of Texas, 1994)
City of Willmar v. Short-Elliott-Hendrickson, Inc.
512 N.W.2d 872 (Supreme Court of Minnesota, 1994)
City of Willmar v. Short-Elliott-Hendrickson, Inc.
498 N.W.2d 766 (Court of Appeals of Minnesota, 1993)
Chantilly Partners v. James A. Federline, Inc.
26 Va. Cir. 1 (Fairfax County Circuit Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
476 N.W.2d 781, 16 U.C.C. Rep. Serv. 2d (West) 132, 1991 Minn. App. LEXIS 1031, 1991 WL 223086, Counsel Stack Legal Research, https://law.counselstack.com/opinion/housing-redevelopment-authority-for-crookston-v-agassiz-construction-minnctapp-1991.