City of Willmar v. Short-Elliott-Hendrickson, Inc.

498 N.W.2d 766, 1993 WL 118559
CourtCourt of Appeals of Minnesota
DecidedJuly 15, 1993
DocketC8-92-1614
StatusPublished
Cited by3 cases

This text of 498 N.W.2d 766 (City of Willmar v. Short-Elliott-Hendrickson, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Willmar v. Short-Elliott-Hendrickson, Inc., 498 N.W.2d 766, 1993 WL 118559 (Mich. Ct. App. 1993).

Opinion

OPINION

NORTON, Judge.

Appellant Clow Corporation challenges trial court’s refusal to grant it summary judgment dismissing respondent Short-Elliott-Hendrickson, Inc.’s cross-claim. Appellant argues that the trial court should have dismissed respondent’s cross-claim as untimely under Minn.Stat. § 336.2-725 (1990). We reverse the trial court’s refusal to grant summary judgment but affirm the trial court’s holding that section 336.2-725 is constitutional.

*768 FACTS

In the mid-1970’s, the City of Willmar employed respondent Short-Elliott-Hen-drickson, Inc. (SEH) to recommend and design improvements to the City’s waste water treatment facility. SEH recommended that the City install a series of rotating biological contractors (RBCs) — large cylinders that rotate bacteria into and out of waste water. The City accepted respondent’s recommendation and construction began in 1981.

Adolfson & Peterson, Inc. (A & P) served as the general contractor for the project. Pursuant to a material subcontract with A & P, appellant Clow Corporation provided the RBCs. No contract was ever entered into between respondent and appellant. In addition to manufacturing the RBCs, appellant provided product information regarding the treatment capability of RBC units and recommended standards for the appropriate sizing of RBCs at the water treatment plant.

Construction at the site was substantially completed by September 1982. Shortly thereafter, the City began receiving complaints from nearby residents about offensive odors emanating from the facility. Respondent representatives concluded that they were caused by overloaded RBCs. Although the City later installed an air diffusion system suggested by respondent, the odor problem persisted.

In late 1987, the City served complaints on respondent, A & P, and appellant to recover damages for the faulty design and construction of the plant. The complaint alleged that respondent negligently designed improvements to the plant and that appellant negligently manufactured the RBCs and breached express and implied warranties in selling those units.

With its answer dated October 6, 1987, respondent served cross-claims against A & P and appellant, alleging negligence, breach of contract, and breach of warranties, and seeking contribution and/or indemnity for amounts ultimately owed or paid by respondent to the City.

Prior to trial, all defendants moved for summary judgment on statute of limitations grounds. The trial court granted all of the motions, whereupon the City, after entering into a Pierringer settlement with A & P, appealed as to respondent and appellant. [Pierringer v. Hoger, 21 Wis.2d 182, 124 N.W.2d 106 (1963) ]. On appeal, this court held that Minn.Stat. § 541.051 (1986) barred the City’s claim against appellant but that material issues of fact regarding the City’s reasonable reliance on statements made by respondent remained, requiring remand on the issue of equitable estoppel.

On review of the court of appeals’ decision, the supreme court held that the City’s claims against appellant were governed by the statute of limitations set forth in Minn. Stat. § 336.2-725(2) (1992) and dismissed the City's claim against appellant as untimely. City of Willmar v. Short-Elliott-Hendrickson, Inc., 475 N.W.2d 73, 79 (Minn.1991). The court found that the City’s claims against appellant accrued in November 1982 and were not filed within four years of that date as required by section 336.2-725(2). The supreme court upheld the court of appeals’ remand on the City’s claim against respondent.

On remand, appellant moved for summary judgment dismissing respondent’s cross-claims for contribution and indemnity. Appellant contended that respondent’s contribution and indemnity claims had their basis in the same sales transaction as the City’s claim against appellant; thus, argued appellant, section 336.2-725(2) also applied to bar respondent’s contribution and indemnity claims. Respondent argued that the appropriate limitations period for its cross-claim was in section 541.051, not section 336.2-725. Respondent also argued that section 336.2-725 was unconstitutional under the facts of this case.

The trial court declined to dismiss respondent’s cross-claim against appellant pursuant to section 336.2-725. In distinguishing Housing & Redev. Auth. for Crookston, Minn. v. Agassiz Constr., Inc., 476 N.W.2d 781 (Minn.App.1991), the trial court noted that appellant not only manufactured the RBCs but also provided consultation services and assisted in testing the equipment. Thus, the court felt that it *769 was not faced with a pure sale of goods. On June 24, 1992, the trial court filed an amended order holding that, pursuant to. Minn.Civ.App.P. 103.03(h), whether application of section 336.2-725 was proper and constitutional was “important and doubtful.”

ISSUES

I. Did the trial court err in refusing to dismiss respondent’s cross-claim against appellant?

II. Is application of Minn.Stat. § 336.2-725 (1990) to bar respondent’s cross-claim against appellant constitutional?

ANALYSIS

I.

The present dispute involves interpreting the scope of Minn.Stat. § 336.2-725 (1990). As a question of law, the trial court’s interpretation of the statute is reviewable de novo. McClain v. Begley, 465 N.W.2d 680, 682 (Minn.1991).

Minn.Stat. § 336.2-725 provides:

(1) An action for breach of any contract for sale must be commenced within four years after the cause of action has accrued. * * *
(2) A cause of action accrues when the breach occurs, regardless of the aggrieved party’s lack of knowledge of the breach. A breach of warranty occurs when tender of delivery is made, except that where a warranty explicitly extends to future performance of the goods and discovery of the breach must await the time of such performance the cause of action accrues when the breach is or should have been discovered.

(emphasis supplied)

Perhaps the principal case construing the scope of section 336.2-725 is Hapka v. Paquin Farms, 458 N.W.2d 683 (Minn.1990). There, the supreme court held that the Uniform Commercial Code controls exclusively with regard to commercial transactions involving property damage only. Id. at 688. Hapka’s scope was clarified in Lloyd F. Smith Co. v. Den-Tal-Ez, Inc., 491 N.W.2d 11, 16 (Minn.1992), which held that a non-U.C.C. tort remedy is allowed where a defective product causes damage to other property

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eagan East Ltd. Partnership v. Powers Investigations, Inc.
554 N.W.2d 621 (Court of Appeals of Minnesota, 1996)
City of Willmar v. Short-Elliott-Hendrickson, Inc.
512 N.W.2d 872 (Supreme Court of Minnesota, 1994)
Patz v. St. Paul Fire and Marine Ins. Co.
817 F. Supp. 781 (E.D. Wisconsin, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
498 N.W.2d 766, 1993 WL 118559, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-willmar-v-short-elliott-hendrickson-inc-minnctapp-1993.