Hooks Smelting Co. v. Planters' Compress Co.

79 S.W. 1052, 72 Ark. 275, 1904 Ark. LEXIS 125
CourtSupreme Court of Arkansas
DecidedMarch 5, 1904
StatusPublished
Cited by29 cases

This text of 79 S.W. 1052 (Hooks Smelting Co. v. Planters' Compress Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hooks Smelting Co. v. Planters' Compress Co., 79 S.W. 1052, 72 Ark. 275, 1904 Ark. LEXIS 125 (Ark. 1904).

Opinion

Riddick, J.

(after stating the facts). This is an action brought by the Hooks Smelting Company of Philadelphia against the Planters’ Compress Company of Helena to recover $520.87 as the price of two bronze worms and other castings which plaintiff made for the defendant company. The defendant set up, among other things, that the plaintiff was informed that the worms were needed by the 1st day of September, and that unless they were received the compress could not be run, and great loss would result to the defendant, and that the plaintiff thereupon agreed that it would ship the worms on or before the 1st of September, but that it failed to.ship them until the 30th of that month, and that when they were received they proved to be too large to go under the sector or arms of the compress, and for that reason were worthless, and that, as a result of the failure of the plaintiff to make the worms in accordance with the directions given it, and to deliver them as it agreed to do, defendant’s compress was stopped for several months, and defendant was put to considerable expense in other ways, the loss aggregating, in all, the sum of $7,322.59, for which it asked judgment. The result of the trial was that, while plaintiff asked judgment for the sum of $520.87, judgment was rendered against it for the sum of .$5=450-

An examination of the bill of particulars filed with the complaint in connection with the evidence will show that the profits which the plaintiff might reasonably have expected to make on this contract did not probably exceed one or two hundred dollars, for we must remember that its business was smelting, and that the pattern making and finishing which make up nearly half the bill were done by other parties, upon whose work it does not appear that plaintiff expected any .profit. We are not saying that these parties were not, under the facts of this case, in some sense agents or employees of plaintiff, so as to make it responsible for the character of their work. We are simply calling attention to the fact that it does not appear that plaintiff was to get a profit on their work, except by securing the contract to do the casting required, and that on the whole contract its expected profits did not probably exceed the amount named. And yet for the failure to properly perform this contract plaintiff is subjected to damages nearly ten times greater than the gross amount to be paid it for all the materials it furnished. While the fact that the damages are greater than ordinarily follow the breach of contracts to furnish materials of that value does not show that the judgment is wrong, it calls attention to the case as one somewhat out of the beaten track of damage cases, and we therefore proceed with some interest to examine the law and the evidence upon which the judgment is based.

The rule of law by which the defendant undertakes to support this judgment was first laid down in the case of Hadley v. Baxendale, 9 Exch. 341. In that case the plaintiffs were the owners of a steam mill. The shaft was broken, and they gave it to the defendant, a carrier, to take to an engineer, to serve as a model for a new one. On making the contract for shipment, the agent of the carrier was informed that the mill was stopped, and that the shaft must be sent immediately. He delayed its delivery, and in an action for a breach of the contract the owners of the mill claimed as specific damages the loss of profits while the mill was kept idle. It was held that, if the carrier had been informed that a loss of profits would result from delay on his part, he would have been answerable. But as, in the opinion of the court, it did not appear that he knew that the want of the shaft was the only thing which was keeping the mill idle, he could not be made responsible to such an extent. Now, we feel some doubt as to whether the learned court did not in that case refuse to follow its own rule. The court, it will be noticed, said that, if the agent of the carrier had been told that the mill could not run until the shaft was returned, and if that was the only cause for stopping the mill, the carrier would have been liable. But was not all this implied in what was told the agent? He was told that the mill shaft was broken, and the mill stopped, and that the shaft must be delivered to the engineer immediately, so that a new one could be made. It would seem that this was sufficient to give the agent notice that the stopping of the mill was the result of the broken shaft, or at least be sufficient to support a finding of a jury to that effect. If we look at what the court actually decided in that case, it seems itself to support the modification, subsequently engrafted in the rule as stated in that case, to the effect that mere notice is not always sufficient to make one liable for special damages. This modification we will notice further on.

Mr. Mayne in his work on damages says of this case of Hadley v. Baxendale that it has been supposed to lay down three rules in respect to the recovery of damages. “First, that damages which may fairly and reasonably be considered as naturally arising from the breach of the contract, according to the usual course of things, are always recoverable. Secondly, that damages which would not arise in the usual course of things from a breach of contract, but which do arise from circumstances peculiar to the special case, are not recoverable unless the special circumstances are known to the person who has broken the contract. Thirdly, that where the special circumstances are known, or have1 been communicated to the person who breaks the contract, and where the damage complained of flows naturally from the breach of the contract under those special circumstances, then such special damage must be. supposed to have' been contemplated by the parties to the contract, and is recoverable.” Mayne on Damages (1st Am. Hd.), § 14.

Now, the first two rules laid down by the decision in Hadley v. Baxendale have never been questioned or doubted, but the third rule, the one we are asked to enforce in this case, has often been criticised, and many cases could be cited where the courts have refused to apply it so broadly as stated in the principal case, for if thus applied it would in many cases result in obvious injustice. Suppose, for instance, that a large manufacturing establishment is driven by power from a single engine, and that, by reason of an accident to some small but important part of the engine or machinery, it becomes necessary to stop the operation of the whole plant until a new part can be made or the old one repaired. If thereupon a blacksmith or machinist is called in, and, for the price of a few dollars, undertakes to make the repairs, but through some mistake or unskillfulness the part supplied by him should fail to fit, requiring it to be remade and entailing still further delay, would any court hold that the blacksmith or machinist could be held liable for all the damages entailed by the delay when they were large, in the absence of a contract on his part to be thus liable, unless the notice and the circumstances under which he made the contract were such that he ought reasonably to have known that in the event of his failure to perform his contract the other party would look to him to make good the loss? Theoretically, under the third rule, as stated in Hadley v. Baxendale, the blacksmith, if he had notice, would be liable. ■but we know of no decision that has gone to that extent, but there are many cases in which such exorbitant claims for damages have been denied by the courts, on the ground that it would be clearly unjust to allow them.

In the case of Fleming v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deck House, Inc. v. Link
249 S.W.3d 817 (Court of Appeals of Arkansas, 2007)
Reynolds Health Care Services, Inc. v. HMNH, Inc.
217 S.W.3d 797 (Supreme Court of Arkansas, 2005)
Bank of America, N.A. v. C.D. Smith Motor Co.
106 S.W.3d 425 (Supreme Court of Arkansas, 2003)
Robertson v. White
633 F. Supp. 954 (W.D. Arkansas, 1986)
Kenford Co. v. County of Erie
108 A.D.2d 132 (Appellate Division of the Supreme Court of New York, 1985)
Morrow v. First Nat. Bank of Hot Springs
550 S.W.2d 429 (Supreme Court of Arkansas, 1977)
Hawkins v. Delta Spindle of Blytheville, Inc.
434 S.W.2d 825 (Supreme Court of Arkansas, 1968)
Carroll v. Jones
373 S.W.2d 132 (Supreme Court of Arkansas, 1963)
Bay Aviation Services Co. v. Southland Aviation, Inc.
211 F. Supp. 125 (W.D. Arkansas, 1962)
Southwestern Bell Telephone Company v. Norwood
207 S.W.2d 733 (Supreme Court of Arkansas, 1948)
Thurner Heat Treating Co. v. Memco, Inc.
30 N.W.2d 228 (Wisconsin Supreme Court, 1947)
Lamkins v. International Harvester Co.
182 S.W.2d 203 (Supreme Court of Arkansas, 1944)
Interstate Grocer Company v. Namour
148 S.W.2d 175 (Supreme Court of Arkansas, 1941)
Southwestern Bell Telephone v. Carter
25 S.W.2d 448 (Supreme Court of Arkansas, 1930)
Miles v. American Railway Express Co.
233 S.W. 930 (Supreme Court of Arkansas, 1921)
Sager v. Jung & Sons Co.
220 S.W. 801 (Supreme Court of Arkansas, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
79 S.W. 1052, 72 Ark. 275, 1904 Ark. LEXIS 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hooks-smelting-co-v-planters-compress-co-ark-1904.