Holtzman Oil Corp. v. Commonwealth

529 S.E.2d 333, 32 Va. App. 532, 2000 Va. App. LEXIS 416
CourtCourt of Appeals of Virginia
DecidedJune 6, 2000
Docket0422994
StatusPublished
Cited by27 cases

This text of 529 S.E.2d 333 (Holtzman Oil Corp. v. Commonwealth) is published on Counsel Stack Legal Research, covering Court of Appeals of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holtzman Oil Corp. v. Commonwealth, 529 S.E.2d 333, 32 Va. App. 532, 2000 Va. App. LEXIS 416 (Va. Ct. App. 2000).

Opinion

FITZPATRICK, Chief Judge.

Holtzman Oil Corp. (Holtzman) appeals a final circuit court judgment upholding a decision by the Commonwealth’s Department of Environmental Quality (DEQ) denying reimbursement from the Petroleum Storage Tank Fund (Tank Fund). 1 After the DEQ denied its request, Holtzman appealed pursuant to the Virginia Administrative Process Act (VAPA), Code §§ 9-6.14:1 through 9-6.14:25. The circuit court ruled that the agency’s decision was not “arbitrary or capricious resulting in a clear abuse of discretion.” The sole issue raised on appeal is whether the evidence supports the circuit court’s order affirming the DEQ’s decision denying reimbursement from the Tank Fund. For the following reasons, we affirm.

I. BACKGROUND

The evidence established that on November 5, 1993, Holtzman notified the DEQ of its intent to remove certain underground storage tanks from a gas station in Harrisonburg, Virginia. In December 1993, the tanks were replaced. During the tank removal process, Holtzman discovered “mildly contaminated soils but saw no evidence of a leaking tank or line during any part of the excavation.” Upon further investigation, the company learned that “the product lines had been replaced in the early 1980’s due to leaks.” Approximately 2,900 tons of soil were excavated from the Harrisonburg site and laboratory analysis of the “backfill material in the basins” showed the petroleum hydrocarbon level in the soil was 160 parts per million. Holtzman notified the DEQ of these findings on December 8,1993.

On December 15,1993, the DEQ informed Holtzman that, in accordance with applicable regulations, it was required to perform a “Release Investigation Report” upon a finding of *536 contaminated soils. That report, submitted by the company on January 31, 1994, disclosed that nine underground tanks had been removed from the site, no holes were found in any of the tanks, and samples of the soils alongside and beneath the tanks showed petroleum hydrocarbon levels ranging from 24 to 57 parts per million. A sample of “backfill material” from around the diesel tank showed petroleum hydrocarbon in the soil of 160 parts per million and samples of “backfill material” from the main excavation showed 129 and 42 parts per million. In February 1994, without prior notice to the DEQ, Holtzman incinerated the 2,900 tons of contaminated soil at a total cost of $140,705.

Based on the Release Investigation Report and addendum information, the Valley Regional Office of the DEQ found no “significant release” and that “the risk in the urban setting would be extremely low.” The regional office recommended “that the case should be closed.” In its letter dated October 20, 1994, the DEQ notified Holtzman that it was closing its investigation and that no further “corrective action” would be required unless “significant environmental or health/safety problems develop in this area.”

Pursuant to Code § 62.1-44.34:11, Holtzman made a formal request on March 22, 1995 for reimbursement from the Tank Fund for the clean-up costs. Holtzman alleged that the removal of the contaminated soil constituted an “abatement activity” within the meaning of Virginia Regulation 680-13-02 § 6.3(A)(4) and, based on its interpretation of the applicable regulations, the clean-up costs were reimbursable.

On July 18, 1995, the DEQ denied Holtzman’s request for reimbursement. In a letter dated October 11, 1995, the DEQ explained its reasons for denying the claim, stating:

[Rjeview of the file indicates that the denials stem from the excavation of soils without approval by the Regional Office.
* * * * * *
... [T]he Agency is required by law to determine whether the activities submitted for reimbursement were ap *537 •proved or would have been approved had they been timely presented to the Agency for consideration.
Valley Regional Office (VRO) files indicate that your client failed to contact VRO staff to determine whether soil removal would be approved. Moreover, VRO files indicate that the removal would not have been approved had your client timely requested such consideration. Among other things, (1) even the highest TPH result showed minimal contamination; (2) the site is in a location with public water, meaning there was no threat of a drinking water impact; and (3) there were no basements nearby, meaning there was no threat of a building vapor impact.

(Emphasis added).

Holtzman sought review by the DEQ’s Reconsideration Panel (Panel). In its opinion letter dated May 28, 1995, the Panel issued its final decision denying Holtzman’s request for reimbursement. The Panel considered the issue before it to be “whether the removal of the soil from the Rolling Hills site was necessary for corrective action.” Because Holtzman did not seek prior approval from the DEQ before incinerating the soil and consistent with the regulations and policy then in effect, the Panel determined whether the excavation would have been approved had the DEQ been properly notified. On reconsideration, the Panel affirmed the denial of Holtzman’s claim, stating the following:

Soil excavation and removal may be conducted when implementing a corrective action plan or as part of a Phase II initial abatement. The regulation and Agency guidance indicate that initial abatement activities do not normally include removal of soil with low levels of contamination, as the focus is instead on abatement of fire, vapor and explosion hazards.
The course of events at your site indicated that the soil was removed as part of site reconstruction and not as part of corrective action. The fact that the soil already had been excavated before you reported a release establishes that the soil removal was not conducted as an abatement activity. *538 Equally important, during the meeting you acknowledged that the soil was removed to allow for site reconstruction rather than for environmental considerations (corrective action).
Given the preceding facts, we must conclude that the soil excavation was not a necessary, approvable corrective action activity. Because the soil excavation was not a necessary corrective action activity, the subsequent disposal activity also was not a necessary corrective action activity. Thus, costs incurred as a result of the soil excavation are not approved for reimbursement.

On July 31, 1996, Holtzman appealed the DEQ’s final decision to the circuit court. The circuit court affirmed the DEQ’s decision, stating:

In reviewing the record, I must afford the agency decision a presumption of official regularity, and I must take into account the experience and specialized competence of the [Board] and DEQ. I am not to substitute my own judgment for that of the agency. While I find Holtzman’s position quite reasonable in this case, I cannot find that the agency’s decision was arbitrary or capricious resulting in a clear abuse of discretion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commissioner, Virginia Department of Social Services v. Fulton
683 S.E.2d 837 (Court of Appeals of Virginia, 2009)
COMM. DEPT. OF SOC. SER. v. Fulton
683 S.E.2d 837 (Court of Appeals of Virginia, 2009)
Board of Supervisors v. State Building Code Technical Review Board
663 S.E.2d 571 (Court of Appeals of Virginia, 2008)
Loudon Hospital Center v. Robert B. Stroude, M.D.
650 S.E.2d 879 (Court of Appeals of Virginia, 2007)
LOUDOUN HOSP. CENTER v. Stroube
650 S.E.2d 879 (Court of Appeals of Virginia, 2007)
Palmer v. Commonwealth of Virginia Marine Resources Commission
628 S.E.2d 84 (Court of Appeals of Virginia, 2006)
Bowman Apple Products Co. v. Commonwealth
70 Va. Cir. 148 (Shenandoah County Circuit Court, 2006)
Jones v. West
616 S.E.2d 790 (Court of Appeals of Virginia, 2005)
7-Eleven, Inc. v. Department of Environmental Quality
590 S.E.2d 84 (Court of Appeals of Virginia, 2003)
Scott Ayers v. Virginia Marine Resource Commn, etal
Court of Appeals of Virginia, 2003
City of Virginia Beach v. Marine Resource Commn
Court of Appeals of Virginia, 2003
Brabham Petroleum Co. v. Virginia Alcoholic Beverage Control Board
61 Va. Cir. 36 (Virginia Circuit Court, 2003)
May Dept. Store Co v. CW, DEQ, etc
Court of Appeals of Virginia, 2002
7-11, Inc. v. Virginia Deptartment of Environmental Quality
56 Va. Cir. 276 (Richmond County Circuit Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
529 S.E.2d 333, 32 Va. App. 532, 2000 Va. App. LEXIS 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holtzman-oil-corp-v-commonwealth-vactapp-2000.