Hoff v. Lester

168 P.2d 409, 25 Wash. 2d 86, 164 A.L.R. 751, 1946 Wash. LEXIS 362
CourtWashington Supreme Court
DecidedApril 18, 1946
DocketNo. 29768.
StatusPublished
Cited by22 cases

This text of 168 P.2d 409 (Hoff v. Lester) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoff v. Lester, 168 P.2d 409, 25 Wash. 2d 86, 164 A.L.R. 751, 1946 Wash. LEXIS 362 (Wash. 1946).

Opinion

*88 Beals, J.

Plaintiff in this action, G. C. Hoff, verified his complaint, July 7, 1943, alleging that he was engaged in the business of drilling wells and owned a complete well-drilling machine and equipment; that, March 8, 1943, plaintiff contracted with defendants Lester to drill a well upon a tract of land belonging to them, and, accordingly, moved his drilling equipment to the site of the proposed operation; that, June 20, 1943, the defendants refused to permit plaintiff to enter upon their property for the purpose of removing his drilling equipment and refused to permit plaintiff to take possession thereof; that the drill had not been taken for a tax or under execution; that its value was forty-five hundred dollars; and that the property was capable of earning for plaintiff the sum of fifty dollars a day, which sum plaintiff alleged was his past and continuing damages.

Plaintiff asked for a writ of replevin, commanding the sheriff to deliver the property to the plaintiff, or, in the alternative, for a judgment against defendants for forty-five hundred dollars. He also demanded judgment for eight hundred fifty dollars by way of accrued damages and for fifty dollars a day for each additional day possession of the property was withheld from plaintiff.

By their answer, the defendants admitted that they were husband and wife, and the owners of the land upon which plaintiff was to drill a well, at their order. They denied that they had refused to allow plaintiff to remove his drilling equipment and that they had wrongfully retained possession thereof. They also denied that the property was worth more than twenty-five hundred dollars, or that its use was worth more than fifteen dollars a day.

By affirmative defenses, the defendants alleged that plaintiff had agreed to drill a well for them, had partially performed the contract, and had then abandoned it, to defendants’ damage in a considerable sum.

Plaintiff replied to the affirmative defenses contained in defendants’ answer with denials, and, thereafter, February 8,1944, defendants filed an amended answer, in tenor similar to their original answer save that they specifically denied *89 that they had ever withheld the drilling equipment from plaintiff, and alleged that

“ . . . there has been no time since the said well drill has been on the premises of the defendants that he could not have moved it off without any hinderance on the part of the defendants, either by force or threats, or intimidation, or any threats to institute legal proceedings.”

Plaintiff did not, at the time of the institution of the action, or later, claim immediate delivery of the drilling equipment by filing an affidavit and bond in accordance with Rem. Rev. Stat., § 707 [P.P.C. § 92-5] et seq., and the property remained in the possession of the defendants at all times during the pendency of the action.

The action was tried to the court, sitting without a jury, and resulted in the entry of findings of fact, which may be summarized as follows:

The court found that defendants were husband and wife and the owners of the land referred to in plaintiff’s complaint; that the plaintiff was the owner of a complete well-drilling machine and equipment, and that, March 7,1943, he entered into a contract to drill a well upon defendants’ property and moved his equipment to the site of the proposed operation; that, July 1,1943, plaintiff sought to remove his equipment from defendants’ property, and that defendants refused to allow plaintiff to take possession of his machinery; that plaintiff instituted this action in replevin, July 7, 1943, asking for possession of the property and damages for its detention; that the reasonable rental value of the drilling equipment was forty dollars a day; that plaintiff did not, at the time of commencing his action, nor at any time thereafter, claim immediate delivery of the machinery by filing an affidavit and bond, and that the defendants were still retaining possession of the equipment upon their land; that the market value of the equipment was forty-five hundred dollars; that plaintiff was entitled to immediate possession thereof, together with damages in the sum of two hundred dollars for detention of the property up to the time of the institution of the action; and that, if possession of the property was not given to plaintiff, he should recover dam *90 ages in the sum of forty-five hundred dollars. The court further found that the property had not been taken for a tax, assessment, or fine, etc.

The court entered conclusions of law, in accordance with the findings of fact, followed by a judgment.

Plaintiff moved for a new trial, on the ground that the court had erred in assessing the amount of damages in plaintiff’s favor and, upon denial of the motion for a new trial, appealed to this court.

Error is assigned upon the refusal of the trial court to allow damages in favor of appellant for the wrongful withholding of the drilling equipment, from the date of the filing of appellant’s complaint to the entry of judgment. Appellant also assigns error upon the court’s ruling that appellant, not having filed an affidavit and bond with a claim for immediate delivery of the property, was not entitled to damages for the wrongful withholding of the property by respondents during the pendency of the action.

The only question here presented is whether appellant, having instituted his action in replevin, but not having claimed immediate possession of the property by filing an affidavit and bond pursuant to Rem. Rev. Stat., § 707 et seq., was entitled to damages for detention of the property during the pendency of the action, the trial court having found that the property in question belonged to appellant and was wrongfully detained by respondents. Respondents have not cross-appealed, and, no statement of facts having been filed, the matter is before us upon the court’s findings of fact, conclusions of law, and judgment.

The following facts are established: that appellant was the owner and entitled to possession of the well-drilling equipment; that, July 1, 1943, appellant sought to take possession of his property and that respondents refused to allow appellant to remove his property from their land; that, July 7, 1943, appellant instituted this action; that he at no time claimed immediate delivery of the property by filing an affidavit and bond, as he might have done, in accordance with the statute; that the respondents were, at the time of the entry of judgment, still retaining possession of appel *91 lant’s machinery; and that appellant was entitled to the immediate possession thereof, together with damages in the sum of two hundred dollars (computed at the rate of forty dollars per day for five days prior to the institution of the action), and for judgment for the value of the property, in the sum of forty-five hundred dollars, if possession of the property be not obtained by appellant. The court also found “that the reasonable rental value of the said well drill and equipment so withheld by defendants [respondents] is $40.00 per day.”

Rem. Rev. Stat., § 434 [P.P.C. § 62-17] reads as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensrude v. Sloss
209 P.3d 543 (Court of Appeals of Washington, 2009)
Doughty v. Sullivan
661 A.2d 1112 (Supreme Judicial Court of Maine, 1995)
Walker v. TRANSAMERICA TITLE INSURANCE
828 P.2d 621 (Court of Appeals of Washington, 1992)
Jet Boats, Inc. v. Puget Sound National Bank
721 P.2d 18 (Court of Appeals of Washington, 1986)
Simpson v. Gear
1986 OK 27 (Supreme Court of Oklahoma, 1986)
CULL. RK RIV. WAT. COND. CO. v. Gearhart
443 N.E.2d 1065 (Appellate Court of Illinois, 1982)
Culligan Rock River Water Conditioning Co. v. Gearhart
443 N.E.2d 1065 (Appellate Court of Illinois, 1982)
King v. City of Seattle
525 P.2d 228 (Washington Supreme Court, 1974)
Bates & Springer of Arizona, Inc. v. Friermood
507 P.2d 668 (Arizona Supreme Court, 1973)
MacPhail v. Sagner
293 A.2d 257 (Court of Appeals of Maryland, 1972)
Lake Village Implement Company v. Cox
478 S.W.2d 36 (Supreme Court of Arkansas, 1972)
Lew v. Goodfellow Chrysler-Plymouth, Inc.
492 P.2d 258 (Court of Appeals of Washington, 1971)
Gregory v. Padilla
379 P.2d 951 (Alaska Supreme Court, 1963)
Adams v. Thibault
297 P.2d 954 (Washington Supreme Court, 1956)
Ward v. Painters' Local Union No. 300
276 P.2d 576 (Washington Supreme Court, 1954)
Radley v. Raymond
209 P.2d 305 (Washington Supreme Court, 1949)
Hoff v. Lester
200 P.2d 515 (Washington Supreme Court, 1948)
Sullivan v. Boeing Aircraft Co.
187 P.2d 312 (Washington Supreme Court, 1947)
Olwell v. Nye & Nissen Co.
173 P.2d 652 (Washington Supreme Court, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
168 P.2d 409, 25 Wash. 2d 86, 164 A.L.R. 751, 1946 Wash. LEXIS 362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoff-v-lester-wash-1946.