Hoechst Celanese Corp. v. Arthur Bros., Inc.

882 S.W.2d 917, 1994 Tex. App. LEXIS 2215, 1994 WL 468026
CourtCourt of Appeals of Texas
DecidedAugust 31, 1994
Docket13-93-077-CV
StatusPublished
Cited by19 cases

This text of 882 S.W.2d 917 (Hoechst Celanese Corp. v. Arthur Bros., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoechst Celanese Corp. v. Arthur Bros., Inc., 882 S.W.2d 917, 1994 Tex. App. LEXIS 2215, 1994 WL 468026 (Tex. Ct. App. 1994).

Opinion

OPINION ON MOTION FOR REHEARING

KENNEDY, Justice.

After considering appellee’s motion for rehearing, we withdraw our opinion of July 21, 1994 and enter this opinion in its place. We otherwise deny the motion for rehearing. The appellant’s motion for rehearing was also overruled.

Arthur Brothers, Inc. (“ABI”) recovered damages against Hoechst Celanese Corporation (“HCC”) based on findings of fraud and promissory estoppel. The jury found that HCC lied when it induced ABI to accept a nine-month contract by representing that, if ABI improved over a nine-month period, ABI could retain its long-time role as maintenance contractor at HCC’s chemical plant in Bishop, Texas. By eight points of error, HCC appeals. We suggest a remittitur. If the remittitur is filed, we modify the judgment and affirm. If the remittitur is not filed, we must reverse and remand the entire case.

ABI began serving as maintenance contractor at the Bishop plant for Celanese around 1960. In 1985, ABI earned the maintenance contracts at Celanese plants in the Texas cities of Bishop, Pampa, Bay City, and Corpus Christi. ABI outbid competitors including the Mundy Company. Mundy maintained several Celanese plants including the Clear Lake plant near Houston.

The German company Hoechst took over Celanese in 1987, changing the name to Hoechst Celanese Company. In 1988, HCC created a task force to consider hiring a regional maintenance contractor. The task force included the maintenance supervisors at HCC’s Texas plants, among them Bishop’s Dave Siemonsma and Clear Lake’s Howard “Scotty” Wilmeth. The task force determined that a regional contractor would serve HCC’s needs better than the patchwork of contractors then employed. The task force also decided that an individual facility could opt out of the regional contract if justified.

The task force received bids for a three-year contract from seven contractors. It whittled the list to three finalists: Fluor Daniel, ABI, and Mundy. ABI had the lowest bid, followed in order by Mundy and Fluor Daniel. HCC considered factors other than price and chose Mundy as the Texas contractor. The corporate office prepared a standby press release in April announcing the changeover for the Bishop plant.

Wilmeth, meanwhile, had become the manufacturing services manager at Bishop in October 1988. He supervised Siemonsma, among others. Both men felt Mundy had the clearly superior bid. Wilmeth preferred Mundy based both on the bids and on his experience with Mundy at Clear Lake (sev *921 enteen years, three of which he spent working closely with them as maintenance supervisor) contrasted with his six-month experience with ABI at Bishop. Wilmeth and Siemonsma wanted to go along with the regional recommendation and have Mundy as the contractor at Bishop.

The decision was not theirs alone to make, however. Under HCC’s corporate structure, a contract of this monetary magnitude required corporate-level approval. Bishop’s plant manager, Darrell Pausky, wrote to Ed Munoz at the corporate office in April, expressing concern about negative public reaction possibly attendant to ending the plant’s longstanding relationship with a local company (ABI was based in nearby Kingsville) in favor of an unknown outsider. Pausky acknowledged ABI’s relative weakness, but said he believed Bishop should allow ABI the opportunity to improve its performance. He enclosed a proposed nine-month contract and wrote that proposed areas of deficiency and expectations of improvement would be identified in a contract supplement. Munoz agreed with Pausky.

Wilmeth and Siemonsma then met with the owners of ABI, Aaron Starks, Larry Smith, and Dick Urban. The HCC managers expressed their concerns about ABI’s performance. Wilmeth even told them he preferred Mundy, and may have told them that he did not even consider ABI’s bid the third best of the bids received. Wilmeth and Siemonsma gave ABI a list of areas to improve. This list, entitled “Continued Improvement Plan,” became Schedule I of the contract. Schedule I listed six areas of improvement: foreman management skills, craftsman skills, crew mix management, company improvement, general, and action plans and schedules. Each of these areas had one to three enumerated expectations. The overall heading stated that “[c]ontractor [ABI] agrees to achieve satisfactory improvement progress in the following areas, and to furnish the company [HCC] with evidence of these improvements.”

The nature of the promised result of compliance with Schedule I essentially forms the basis of this lawsuit. Wilmeth insisted that he presented Schedule I as suggested improvements and not as an all-inclusive list. Both HCC managers contended they said that compliance would give ABI only the opportunity to be considered for extension. They denied making any guarantees. ABI’s Starks and Smith, by contrast, testified that Wilmeth told them that if ABI achieved significant-improvement in the nine months that they would get a contract for two years and three months. On further examination, Starks and Smith agreed with statements that compliance meant opportunity for renewal, but at other times reiterated that compliance guaranteed renewal. Everyone agreed that HCC was the sole judge of ABI’s compliance.

ABI’s owners agreed to the nine-month contract to begin May 1, 1993. They requested by letter of April 24, 1993 that Schedule I be included as part of the contract. The contract contained in Article 37 the following exclusionary clause:

(a) This Contract constitutes the entire agreement between Contractor and Company relating to the work. There are no previous or contemporaneous representations or warranties of Company or Contractor not set forth herein.
(b) Except as specifically provided herein, no modification, waiver, termination, rescission, discharge, or cancellation of this Contract or of any terms thereof shall be binding on Company unless in writing and executed by an officer or employee of Company specifically authorized to do so.

HCC president Tom Bohrer signed the contract; there was some evidence that this occurred as late as June 1989.

ABI considered moving supervisor Pat Ley from HCC’s Pampa plant to help Bishop comply with the contract. Ley came to Bishop on May 19, 1989 to talk to the owners about their plans. He testified that the HCC local managers told him that, if ABI complied with the contract (particularly Schedule I), then ABI most certainly would get the new contract. Ley agreed to move to Bishop with ABI rather than accept a position with HCC in Pampa.

ABI submitted a progress report pursuant to the contract on August 1, 1989.. The *922 report detailed ABI’s efforts to comply with Schedule I. The overview stated that ABI was undergoing a tremendous change in culture and the way it conducted its daily business. The report spoke of “a rebirth,” “a complete change of our business culture and value systems,” and “a change of our moral fiber.” The overview states, “The change will not occur quickly and, more importantly, will never be complete.”

The report detailed the large number of changes. Under Ley’s influence, ABI implemented a team management and quality control program modeled on HCC’s programs in Pampa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ISG State Operations, Inc. v. National Heritage Insurance Co.
234 S.W.3d 711 (Court of Appeals of Texas, 2007)
Military Highway Water Supply Corp. v. Morin
114 S.W.3d 728 (Court of Appeals of Texas, 2003)
Military Highway Water Supply Corporation v. Morin, Francisca
114 S.W.3d 727 (Court of Appeals of Texas, 2003)
City of Hidalgo v. James Wisdom
Court of Appeals of Texas, 2001
Rivas v. Cantu
37 S.W.3d 101 (Court of Appeals of Texas, 2000)
Eastman Chemical Co. v. Niro, Inc.
80 F. Supp. 2d 712 (S.D. Texas, 2000)
North American Refractory Co. v. Easter
988 S.W.2d 904 (Court of Appeals of Texas, 1999)
Ensley v. Cody Resources, Inc.
171 F.3d 315 (Fifth Circuit, 1999)
Gorges Foodservice, Inc. v. Huerta
964 S.W.2d 656 (Court of Appeals of Texas, 1998)
GTE Mobilnet of South Texas Ltd. Partnership v. Telecell Cellular, Inc.
955 S.W.2d 286 (Court of Appeals of Texas, 1997)
Miles v. Ford Motor Co.
922 S.W.2d 572 (Court of Appeals of Texas, 1996)
Fisher Controls International Inc. v. Gibbons
911 S.W.2d 135 (Court of Appeals of Texas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
882 S.W.2d 917, 1994 Tex. App. LEXIS 2215, 1994 WL 468026, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoechst-celanese-corp-v-arthur-bros-inc-texapp-1994.