Hochen Ex Rel. Estate of Hochen v. Bobst Group, Inc.

290 F.3d 446, 2002 U.S. App. LEXIS 9220, 2002 WL 975682
CourtCourt of Appeals for the First Circuit
DecidedMay 16, 2002
Docket00-1841
StatusPublished
Cited by30 cases

This text of 290 F.3d 446 (Hochen Ex Rel. Estate of Hochen v. Bobst Group, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hochen Ex Rel. Estate of Hochen v. Bobst Group, Inc., 290 F.3d 446, 2002 U.S. App. LEXIS 9220, 2002 WL 975682 (1st Cir. 2002).

Opinion

STAHL, Senior Circuit Judge.

Plaintiffs-appellants Ismael Hochen (“Hochen”) and Richard Dufault (“Du-fault”) were injured on August 2, 1994, as a result of an explosion in a printing press at their place of employment, Avery Den-nison Corporation (“Avery”). 1 Hochen and Dufault subsequently brought suit against defendant-appellee, the Bobst Group, Inc. (“Bobst”), 2 claiming liability for negligence, failure to warn, and breach of warranty, in connection with Bobst’s activities related to the printing press in 1971 and 1972 and in 1994. In separate rulings, the district court granted Bobst’s motions for (1) partial summary judgment on all claims arising out of its activities in 1971 and 1972; (2) partial summary judgment on the breach of warranty and failure to warn claims arising out of Bobst’s activities in 1994; and (3) judgment as a matter of law on the remaining negligence claims. Appellants now ask us to review the first and third rulings as well as the district court’s decision to exclude testimony by their expert witness. We affirm.

I. BACKGROUND

In 1971 and 1972, Bobst designed and constructed the press in question, Press 8 (the “press”), following Avery’s custom specifications and requirements, and in *449 stalled it at Avery’s facilities in Framing-ham, Massachusetts. The press, which printed labels for a variety of products, weighed 38 tons, was approximately 85 feet in length, and was affixed to the plant’s floor, ceiling, walls and various utility systems. It operated in the following way: A spool of paper — the “web” — after entering through an “infeed,” was pulled through a number of print stations, and rewound after passing , through an “out-feed.” The outfeed pulled the web through and the, infeed followed. In the process, the paper was inked and then moved through a gas powered dryer before reaching the outfeed. Highly flammable solvents were used to keep the. printing ink liquid.

In 1994 Avery undertook a project to upgrade the press. Although Avery decided to conduct the upgrade with in-house employees, it requested that Bobst send field technicians to the plant for several days to work on the installation of two used pieces of equipment, an S-1480 Re-gistrón control system (the “S-1480”) and an R-820 infeed electronic system (the “R-820 infeed”). The S-1480 was an electronic registration device that helped identify the relative position to each other of successive colors being printed on a label and adjusted the print cylinders to ensure their proper alignment. The R-820 infeed electronic system was a part of the infeed that, along with a companion R-820 outfeed system, controlled the tension of the paper web as it passed through the press. For the press to operate correctly, the same tension of the web had to be maintained throughout the entire printing process. Tachometers on the press measured web speed and sent voltage signals that allowed different parts of the press to operate in a synchronized fashion. Bobst technicians installed one tachometer as part of a component of the S-1480 called an auto-sequencer. The parties disagree as to whether Bobst had a duty to synchronize the voltage signal of this tachometer with the voltage signals of other devices on the press — and specifically with the voltage signal from a tachometer in the outfeed unit — and as to whether the auto-sequencer was intended to be operational at all at the time of the installation.

The Bobst technicians worked at Avery from approximately June 26, 1994 to July 3, 1994. The parties strongly contest how Bobst’s services during this period should be characterized. Appellants argue that Bobst was hired to install, start up, and debug the S-1480 and R-820 infeed because they were the “experts” on these devices. Bobst counters that its field technicians were hired only to fill in a labor shortage arising out of vacations taken by Avery’s own employees and that Avery intended to complete the work with its own electricians and tradesmen. In any case, the record indicates that Avery discharged Bobst’s technicians shortly before the 4th of July weekend, at a time when the press was not operational, telling them that they would be called back if needed.

On August 2, 1994, an explosion in the press injured Hochen and Dufault. Appellants brought suit against Bobst, alleging that Bobst was liable for negligence, failure to warn, and breach of warranty in connection with its activities involving the design and installation of the press in 1971 and 1972 and involving the upgrade in 1994. With regard to the 1994 upgrade, appellants’ theory was essentially that Bobst failed to correct voltage problems with the press’s tachometers, leading to problems with web tension. Avery employees testified that, on the day of the explosion, the web had so much slack that it was dipping into one of the ink pans before shooting into the dryers and appellants argued that the flammable solvents in the ink caused the explosion in the *450 dryer. However, the record evidence indicates that there were other problems with the press on the day of the explosion, including the fact that fan blades in the exhaust fan above the print unit where the explosion occurred had been installed backwards by Avery employees, preventing solvents from being exhausted out of the dryer.

On December 5, 1997, the district court granted Bobst’s motion for partial summary judgment on all claims arising out of any deficiency or neglect by Bobst in the design, construction, or installation of the press in 1971 and 1972, holding that these claims were barred by Massachusetts’s six-year statute of repose, Mass. Gen. L. ch. 260 § 2B, concerning improvements to real estate. Hochen v. Bobst Group, Inc., No. 96-11214-DPW, R. Doc. 56 (D.Mass. Dec. 5, 1997). The parties thereafter consented to proceed before a magistrate judge for trial and entry of judgment pursuant to 28 U.S.C. § 636(c). On May 10, 2000, the magistrate judge further entered summary judgment in favor of Bobst on the breach of warranty and failure to warn claims related to Bobst’s activities in 1994. Hochen v. Bobst Group, Inc., No. 96-11214-RBC, R. Doc. 234 (D.Mass. May 10, 2000).

The negligence claims relating to the 1994 upgrade — the only claims to survive the two summary judgment motions — went to trial before a jury in May 2000. On May 19, 2000, in a bench ruling, the magistrate judge excluded the testimony of appellants’ expert witness, Daniel Harwood, on these claims and granted Bobst’s motion for judgment as a matter of law on the issue of negligence, thereby disposing of the case. Hochen v. Bobst Group, Inc., No. 96-11214-RBC, R. Doc. 264 (D.Mass. May 19, 2000).

Here, appellants ask us to review three of the district court’s rulings: (1) the order granting summary judgment to Bobst on claims held to be barred by the statute of repose; (2) the ruling excluding testimony by appellants’ expert witness; and (3) the ruling granting Bobst’s motion for judgment as a matter of law on the negligence claims. Appellants do not appeal the summary judgment ruling in favor of Bobst on the breach of warranty and failure to warn claims related to Bobst’s activities in 1994.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Laurie Ortolano v. P City of Nashua, et al.
2025 DNH 022 (D. New Hampshire, 2025)
Ortolano v. City of Nashua, NH
D. New Hampshire, 2025
Hunt v. Covidien LP
D. Massachusetts, 2024
Bannon v. Godin
99 F.4th 63 (First Circuit, 2024)
Doucette v. Jacobs
D. Massachusetts, 2022
Williams v. Kawasaki Motors Corp., U.S.A.
30 F.4th 66 (First Circuit, 2022)
Schlis v. Target Corporation
D. New Hampshire, 2021
Potvin v. Speedway LLC
264 F. Supp. 3d 337 (D. Massachusetts, 2017)
King v. Pierce Manufacturing, Inc.
608 F. App'x 18 (First Circuit, 2015)
Pacific Indemnity Co. ex rel. Higgins v. Dalla Pola
65 F. Supp. 3d 296 (D. Massachusetts, 2014)
Softub, Inc. v. Mundial, Inc.
53 F. Supp. 3d 235 (D. Massachusetts, 2014)
Rothbaum v. Samsung Telecommunications America, LLC
52 F. Supp. 3d 185 (D. Massachusetts, 2014)
United States v. Espinal-Almeida
699 F.3d 588 (First Circuit, 2012)
Nna v. American Standard, Inc.
630 F. Supp. 2d 115 (D. Massachusetts, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
290 F.3d 446, 2002 U.S. App. LEXIS 9220, 2002 WL 975682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hochen-ex-rel-estate-of-hochen-v-bobst-group-inc-ca1-2002.