Hipskind Heating & Plumbing Co. v. General Industries, Inc.

194 N.E.2d 733, 136 Ind. App. 647, 1963 Ind. App. LEXIS 292
CourtIndiana Court of Appeals
DecidedDecember 17, 1963
Docket19,689
StatusPublished
Cited by8 cases

This text of 194 N.E.2d 733 (Hipskind Heating & Plumbing Co. v. General Industries, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hipskind Heating & Plumbing Co. v. General Industries, Inc., 194 N.E.2d 733, 136 Ind. App. 647, 1963 Ind. App. LEXIS 292 (Ind. Ct. App. 1963).

Opinions

Pfaff, J.

This is an appeal from a judgment of the Allen Superior Court No. 3, denying plaintiff-appellant relief in an action brought for foreclosure of a mechanic’s lien upon certain real estate owned by the appellee.

The cause was submitted for trial before the court upon the issues formed by appellant’s amended complaint and appellee’s answer thereto. At the close of appellant’s evidence, appellee moved for a directed verdict against the plaintiff-appellant, which was granted by the court, and judgment was entered thereon that the plaintiff take nothing by its complaint and that the plaintiff pay the costs of the action.

Appellant filed its motion for a new trial setting forth as cause therefor that the decision of the court is contrary to law, which motion was subsequently overruled by the court. The sole assignment of error in this appeal is the court’s overruling of appellant’s motion for a new trial.

The motion made by the defendant-appellee at the conclusion of the plaintiff-appellant’s evidence operates or has the same effect as a demurrer to the plaintiff’s evidence. Smith v. Switzer (1933), 205 Ind. 404, 409, 186 N. E. 764; Roop, Adm’r. v. [650]*650Woods (1962), 184 Ind. App. 88, 186 N. E. 2d 439, 440; Abernathy v. McCoy (1926), 91 Ind. App. 574, 600, 154 N. E. 682 (Transfer denied). It is to be tested by the same rules of law as is a request for a peremptory instruction to a jury. The sole question presented to the court is, therefore, whether or not the evidence introduced in behalf of the plaintiff, assuming it to be true, and considering as proved all facts which the evidence proves, or by legitimate inference tends to prove, establishes the plaintiff’s case as laid. Smith v. Switzer, supra; Abernathy v. McCoy, supra.

On appeal this court, in reviewing the trial court’s action, may consider only the evidence and reasonable inferences which may be drawn therefrom most favorable to the plaintiff-appellant, to determine if there is any evidence from which it may be reasonably inferred that the plaintiff-appellant was entitled to relief. Hill v. Rogers (1951), 121 Ind. App. 708, 712, 99 N. E. 2d 270 (Transfer denied).

In reviewing the evidence in the record before us, we believe that the appellant’s evidence tended to prove the following material facts:

At some time during the month of March of 1958, there was a parol agreement entered into between appellant and appellee whereby the former agreed to install a fire sprinkler system throughout an entire manufacturing plant building owned by the latter. That certain preliminary work necessary to the installation was begun on March 17, 1958, and that actual installation of the system was commenced on May 13, 1958. The system was to be installed and connected to the city water supply in conformance with certain regulations [651]*651and requirements of fire protection companies and the Underwriters’ Manual. Pursuant to the agreement between the parties, approval was obtained from the Indiana Rating Bureau prior to commencing performance of the contract. Upon completion of the work, the requirements of the Indiana Rating Bureau required that a test for leaks in the system be conducted by putting a 200-pound hydrostatic test on all pipe, including the underground. A new system would be inspected by the Bureau after it had been installed.

At various times prior to May 13, 1958, modifications were made to the original agreement, which limited the extent of the sprinkler system to be installed. The final contract price for the system, as modified, was set at $18,814. A proposed written contract, setting forth the nature of the undertaking and embodying all terms and conditions thereof, was signed by appellant and presented to appellee for signature at some time after May 23, 1958, one clause of which provided for monthly progress payments by appellee equal to ninety per cent of the value of labor and materials incorporated in the work and of materials stored at the work site.

At all times between May 13,1958, and June 16,1958, appellant rendered performance according to the agreement, as modified, installing the system in accordance with the general usage in the trade relating to the installation of the type of system in the type of building. The sprinkler system was designed to fit the particular building owned by the appellee and consisted mostly of piping, hangers to hang the piping and the sprinkler heads. On June 16, 1958, the building was totally consumed by fire.

As of the date of the fire, approximately forty per [652]*652cent of the contract had been performed, thirty-five to forty per cent of rco the city water supply in conformance with certain regulations and requirements of fire protection companies and the Underwriters’ Manual. Pursuant to the agreement between the parties, approval was obtained from the Indiana Rating Bureau prior to commencing performance of the contract. Upon completion of the work, the requirements of the Indiana Rating Bureau required that a test for leaks in the system be conducted by putting a 200-pound hydrostatic test on all pipe, including the underground. A new system would be inspected by the Bureau after it had been installed.

At various times prior to May 13, 1958, modifications were made to the original agreement, which limited the extent of the sprinkler system to be installed. The final contract price for the system, as modified, was set at $18,814. A proposed written contract, setting forth the nature of the undertaking and embodying all terms and conditions thereof, was signed by appellant and presented to appellee for signature at some time after May 23,1958, one clause of which provided for monthly progress payments by appellee equal to ninety per cent of the value of labor and materials incorporated in the work and of materials stored at the work site.

At all times between May 13, 1958, and June 16, 1958, appellant rendered performance according to the agreement, as modified, installing the system in accordance with the general usage in the trade relating to the installation of the type of system in the type of building. The sprinkler system was designed to fit the particular building owned by the appellee and consisted mostly of piping, hangers to hang the piping and the sprinkler [653]*653heads. On June 16, 1958, the building was totally consumed by fire.

. As of the date of the fire, approximately forty per cent of/the contract had been performed, thirty-five to forty.per cent of the physical equipment had been put into the building, and forty-five per cent of the labor had been furnished. None of the underground water supply, which was to run from the property line to the building, had been installed; nor had any part of the valve pit or any of the underground pipe leading to the building.

The total value of preliminary work done, which was necessary to the installation of the system and of materials lost in the fire, including the cost of installation, was approximately $7,400. On or about June 27, 1958, appellant submitted an itemized statement of work done and materials furnished, up to the date of the fire, to the appellee. At some time within thirty days from the date of the fire appellant made demand upon appellee for payment for the work that had been done up until the fire. Since all salvageable parts not yet installed were returned to appellant’s inventory, no charge therefor was included in appellant’s demand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swami, Inc. v. Franklin Drywall II, LLC
Indiana Court of Appeals, 2013
Marshall County Redi-Mix, Inc. v. Matthew
458 N.E.2d 219 (Indiana Supreme Court, 1984)
Marshall County Redi-Mix, Inc. v. Matthew
447 N.E.2d 1165 (Indiana Court of Appeals, 1983)
Driscol v. Delphi Community School Corp.
290 N.E.2d 769 (Indiana Court of Appeals, 1972)
Hipskind Heating & Plumbing Co. v. General Industries, Inc.
204 N.E.2d 339 (Indiana Supreme Court, 1965)
Hipskind Heating & Plumbing Co. v. General Industries, Inc.
194 N.E.2d 733 (Indiana Court of Appeals, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
194 N.E.2d 733, 136 Ind. App. 647, 1963 Ind. App. LEXIS 292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hipskind-heating-plumbing-co-v-general-industries-inc-indctapp-1963.