Swami, Inc. v. Franklin Drywall II, LLC

CourtIndiana Court of Appeals
DecidedApril 29, 2013
Docket10A01-1208-MF-398
StatusUnpublished

This text of Swami, Inc. v. Franklin Drywall II, LLC (Swami, Inc. v. Franklin Drywall II, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swami, Inc. v. Franklin Drywall II, LLC, (Ind. Ct. App. 2013).

Opinion

Pursuant to Ind. Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of Apr 29 2013, 8:27 am establishing the defense of res judicata, collateral estoppel, or the law of the case.

ATTORNEY FOR APPELLANTS: ATTORNEY FOR APPELLEE:

C. GREGORY FIFER STEPHEN W. VOELKER Applegate Fifer Pulliam LLC Voelker Law Office Jeffersonville, Indiana Jeffersonville, Indiana

IN THE COURT OF APPEALS OF INDIANA

SWAMI, INC., et al., ) ) Appellants-Defendants, ) ) vs. ) No. 10A01-1208-MF-398 ) FRANKLIN DRYWALL II, LLC, ) ) Appellee-Plaintiff. )

APPEAL FROM THE CLARK CIRCUIT COURT The Honorable Susan L. Orth, Special Judge Cause No. 10C01-0909-MF-715

April 29, 2013

MEMORANDUM DECISION - NOT FOR PUBLICATION

BRADFORD, Judge Appellant-Defendant Swami, Inc. contracted with Appellee-Plaintiff Franklin Drywall

II, LLC, for the completion of certain drywall work. Prior to execution of the contract terms,

Swami terminated the contract. Franklin Drywall filed a mechanics lien for the outstanding

funds it claimed to be owed by Swami and subsequently filed suit to foreclose on its lien.

Below, the parties disputed whether certain delays in completing the drywall work

were the fault of Franklin Drywall and whether the work was completed in an acceptable

fashion. Following a bench trial, the trial court found in favor of Franklin Drywall. The trial

court also awarded Franklin Drywall attorney’s fees. We conclude that the trial court’s

determination that Franklin Drywall was entitled to recover $48,681.60 was not clearly

erroneous, the trial court did not err in awarding attorney’s fees to Franklin Drywall, and the

trial court erred in finding that a certain mortgage debt should not be considered to be a lien

against the property in question. Consequently, we affirm in part, reverse in part, and remand

for further proceedings consistent with this memorandum decision.

FACTS AND PROCEDURAL HISTORY

Swami is a Georgia corporation which owns certain real estate in Clark County,

where, in early 2009, it planned to build a Days Inn Hotel (the “Property”). On January 14,

2009, representatives for Swami and Franklin Drywall entered into a contract (the

“Contract”) for the completion of certain drywall work at the Property by Franklin Drywall.

For the most part, Swami was represented in the relevant negotiations and interactions by

Umang Bhatt (“U. Bhatt”) and Ramesh Bhatt (“R. Bhatt”), and Franklin Drywall was

represented by its owner, Adrian Franklin. The relevant portions of this Contract appear

2 below, verbatim:1

(1) All work shall be performed in accordance with commercial code and standard adopted by Clark County, State of Indiana and requirements of the authorities having jurisdiction. Also this work to be performed and material must be use as Owner and Wyndham corp. (Days and Suites) final approval. Subcontractor shall be responsible for all OSHA rules. (2) This agreement consist of conditions of the contract (General, Supplementary and other conditions), Drawing, Specifications, Addenda, issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement. These form the contract, and are as fully a part. Of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements either written or oral. An enumeration of the contract documents, other than modification, appears in Item No 11 (3) Scope of Work (The Work of this Contract) Attach Exhibit “A” All work shall be completed in timely fashion as specified in Exhibit “A” (4) Total Contract Sum Total price for labor, materials, equipments and tools for this contract is $106,000 **** (6) If the Subcontractor defaults or neglects to carry out the work in an accordance with this agreement and fails to perform in satisfactory manners, the Owner will notified to the Subcontractor. The Subcontractor may commence and continue correction in timely manner. If work does not performed in accordance with commercial code and standard or no reply from the Subcontractor within 2 days, Owner my get work done by other agent at expense of this the Subcontractor. In such case the Owner may cancel this agreement by written notification to the Subcontractor without prejudice to the other remedies the Owner may have. **** (10) Any alteration and/or deviation from the drawing and specification involved extra cost shall be in writing and shall be approved by the all parties before proceeding the work. (11) The Subcontractor warrants to the Owner that all materials, equipment and Fixtures under this agreement will be good quality and new. The Subcontractor guarantees also all work done under this agreement against defective and/or fault workmanship for a period of year from completion of the 1 All correspondence between the parties appears verbatim.

3 project. Such defective work and/or equipment and fixture shall be replaced or corrected without any additional cost to the Owner. **** EXHIBIT “A’ Scope of Work 1. Preparation for Drywall **** [2] H There shall be knock down finish in all guest rooms, bathrooms, pantry, manager room, work area, exercise room and vending area (three floors hallways, lobby, registration and elevator entrance will be wallpaper. Rest of area knockdown) **** Total price for labor, materials, equipments, tools, other supply and services including taxes $106,000.00[3] **** Timetable for starting and completion 1. After completion of all require rough in and getting inspected owner shall give five days to subcontractor notice to commence work. During this time subcontractor shall order materials. Owner and subcontractor shall acknowledge date and time of this notice. 2. Subcontractor shall have 2 weeks to hang all drywall and 2 weeks to complete all dry wall work. Penalties 1. Both party understand that there shall be total seven weeks (35 days) to complete this work once owner give notice to commence work. There shall be $ 500.00/week penalties after 35 days of contract. This penalty clause does not prejudice other remedies the Owner may have.

Plaintiff’s Ex. 4, Appellants’ App. Vol. 1, pp. 143-46. The contract also provided a schedule

by which Franklin Drywall was to be paid.

On April 14, 2009, Franklin sent a letter to Umag Parag, a representative of Swami,

which stated as follows:

2 “Knock down” is a term of art used by drywall appliers. After the drywall is hung, a powdered mix is mixed with water and sprayed on the wall. This gives a “splatter effect.” Once the mixture is sprayed on the wall, a drywall knife is used to apple pressure to the applied mix to achieve the desired texture. 3 The parties added a handwritten sentence which was initialed by both parties and reads as follows: “Except Owner will supply all paint for knock down.” Appellants’ App. p. 145.

4 I am writing this letter to inform you that Franklin Drywall II, LLC is not a painting contractor. We were hired to hang, finish, splatter the walls and popcorn the ceiling. You requested that paint be placed in the drywall mud at your cost for the paint. I have no problem placing paint in the mud for the walls but you must understand that if we have to paint the walls and ceilings, there will be a charge of $2.50 a finished square foot for labor only. This is per floor. (71’ x 184’).

Plaintiff’s Ex. 6. On or about April 15, 2009, U. Bhatt responded, in writing, to the April 14,

2009 letter from Franklin. In this writing the parties initialed a sentence that read: “Your will

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Briles v. Wausau Insurance Companies
858 N.E.2d 208 (Indiana Court of Appeals, 2006)
Gibson-Lewis Corp. v. Northern Indiana Public Service Co.
524 N.E.2d 1316 (Indiana Court of Appeals, 1988)
Clark's Pork Farms v. Sand Livestock Systems, Inc.
563 N.E.2d 1292 (Indiana Court of Appeals, 1990)
Nelson v. Marchand
691 N.E.2d 1264 (Indiana Court of Appeals, 1998)
Millner v. Mumby
599 N.E.2d 627 (Indiana Court of Appeals, 1992)
Hipskind Heating & Plumbing Co. v. General Industries, Inc.
194 N.E.2d 733 (Indiana Court of Appeals, 1963)
Leas v. Patterson
38 Ind. 465 (Indiana Supreme Court, 1872)
Argonaut Insurance Co. v. Jones
953 N.E.2d 608 (Indiana Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Swami, Inc. v. Franklin Drywall II, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swami-inc-v-franklin-drywall-ii-llc-indctapp-2013.