Highway Commission v. . Rand

143 S.E. 851, 195 N.C. 799, 1928 N.C. LEXIS 214
CourtSupreme Court of North Carolina
DecidedJune 23, 1928
StatusPublished
Cited by5 cases

This text of 143 S.E. 851 (Highway Commission v. . Rand) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highway Commission v. . Rand, 143 S.E. 851, 195 N.C. 799, 1928 N.C. LEXIS 214 (N.C. 1928).

Opinion

This was a civil action brought by the plaintiff, the State Highway Commission, against R. G. Rand and Fidelity and Deposit Company of Maryland, for the recovery of the sum of $63,510.50 for alleged breach of the contract sued on.

On 27 July, 1923, the plaintiff and the defendant, R. G. Rand, entered into a contract for the construction of a certain road leading from Waynesville, N.C. to Pigeon River, in Haywood County, known as State Highway Project No. 940, "being approximately 7.13 miles long and approximately estimated to cost $80,380.00." Prior to this time the plaintiff had contracted the construction of this same road to Alexander Patton, and the contract between the plaintiff and the defendant Rand referred to the Alexander Patton contract and made certain of its provisions parts of the contract sued on. Following the execution of the contract sued on, to wit, on 28 July, 1923, the defendant Rand entered into an indemnity or guaranty bond in the sum of $40,000 with the defendant, Fidelity and Deposit Company of Maryland as its surety, with the usual conditions, and the Surety Company was made a party defendant for the purpose of making it liable for the alleged breach of the contract with Rand. The defendants denied any breach of the contract on the part of Rand, alleging that the plaintiff breached the contact by placing without defendants' consent, and without giving the notices required by the contract, men and equipment in charge of one end of the road, thereby rendering it impossible for the defendant Rand to perform and complete the contract on his part. For this alleged breach of the contract on the part of the plaintiff, the defendant Rand pleaded a counterclaim and sought recovery of the plaintiff for $20,722 damages.

The issues submitted to the jury and their answers thereto, were as follows:

"1. Did the defendant, R.G. Rand, commit a breach of his contract with the plaintiff, executed 27 July, 1923, as alleged in the complaint? Answer: Yes. *Page 801

"2. Did the defendant, Fidelity and Deposit Company of Maryland, commit a breach of its indemnity bond, executed for its codefendant, R. G. Rand, on 27 July, 1923, all alleged in the complaint? Answer: Yes.

"3. What damages, if any, is the plaintiff entitled to recover of the defendants by reason of such breach? Answer: $24,222, with interest from 12 July, 1924.

"4. Did the plaintiff commit a breach of its contract with the defendant, R. G. Rand, executed 27 July, 1923, as alleged in the answer? Answer: No.

"5. Did the plaintiff commit a breach of its contract with the defendant Fidelity and Deposit Company of Maryland, as alleged in the answer? Answer: No.

"6. What damages, if any, is the defendant, R. G. Rand, entitled to recover of the plaintiff by reason of his counterclaim? Answer: Nothing."

DEFINITION OF TERMS

"Engineer" — The State Highway Engineer of the State of North Carolina, duly authorized by the State Highway Commission, acting either directly or through authorized assistants by whom all explanations and directions necessary for the satisfactory prosecution and completion of the work will be given.

Quantities Are Approximate Only. The foregoing quantities are approximate only, being given as a factor for the computation of the total amount of bids, upon which basis such bids are to be computed. The State Highway Commission does not expressly or by implication agree that the actual amount of work and materials will correspond therewith, and reserves the right to increase or decrease the amount of any class or portion of the work and materials as may be deemed necessary or expedient by the engineer.

Examination of Plans, Site, etc. Before submitting a proposal, each bidder should make a careful examination of the attached conditions, specifications and contract, and fully inform himself as to the quality of materials and character of work required, and should further make a careful examination of the source of supply for materials, and should his proposal be accepted, he will be responsible for each and every error in his proposal resulting from his failure or neglect to observe or comply with these instructions.

Additional Work. The contractor shall perform such work, in additional quantities other than those designated in the approximate estimate, as may be deemed necessary to complete fully the roadway as planned and contemplated, and shall receive for such additional work payment in full at the prices shown on the contract and in the same manner as if such work had been included in the original estimate of quantities. *Page 802 Progress of Work. The contractor shall within ten (10) days after the award of contract begin and promptly and efficiently prosecute the work with a force adequate to complete the project for which he has contracted within the time fixed therein for completion. Failure to comply with this requirement may result in the annulment of the contract as hereinafter provided.

Character of Workmen and Equipment. The contractor shall at all times employ sufficient labor and equipment for prosecuting the several classes of work to full completion in the manner and time specified. Any person employed by the contractor whom the engineer may deem incompetent or unfit to perform the work shall be at once discharged; such persons shall be employed again on any work which is under the jurisdiction of the State Highway Commission. Failure by the contractor to provide adequate equipment may result in the annulment of the contract as hereinafter provided.

Engineer's Decision Final. It is mutually agreed between the parties to the contract that to prevent all disputes and misunderstandings between them in relation to any of the provisions contained in these specifications, or their performance by either of said parties, the engineer shall be a referee to decide all matters arising or growing out of said contract, between them, and his decisions shall be final and binding upon both parties.

Time of Completion. In computing the time allowance for completing the work, the engineer will allow an additional number of working days over and above the time allowance mentioned in the proposal equal to the number of working days lost by the contractor after starting the work, because the conditions which the engineer considers such as to prevent the work, and during which days work was actually suspended or materially impeded. The basis for computing any extra time allowance will be the weather record kept by the engineer or his assistants. If the satisfactory execution and completion of the contract shall require work or material in greater amounts or quantities than those set forth in the contract, the contract time shall be increased in the same proportion ass the additional work bears to the original work contracted for. No allowance shall be made for delay or suspension of the prosecution of the work due to fault of the contractor.

Failure to complete Work on Time. Should the contractor fail to complete the work within the time allowance mentioned in the proposal subject to the above modifications, the engineer will thereafter deduct from any moneys due or becoming due to the contractor an amount equal to the cost of maintaining the necessary force of engineers and inspectors during the additional time, together with an additional sum *Page 803

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salem Towne Apartments, Inc. v. McDaniel & Sons Roofing Co.
330 F. Supp. 906 (E.D. North Carolina, 1970)
Wilson v. Wilson
134 S.E.2d 240 (Supreme Court of North Carolina, 1964)
Childress v. C. W. Myers Trading Post, Inc.
100 S.E.2d 391 (Supreme Court of North Carolina, 1957)
Pappas v. . Crist
25 S.E.2d 850 (Supreme Court of North Carolina, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
143 S.E. 851, 195 N.C. 799, 1928 N.C. LEXIS 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/highway-commission-v-rand-nc-1928.