Childress v. C. W. Myers Trading Post, Inc.

100 S.E.2d 391, 247 N.C. 150, 1957 N.C. LEXIS 662
CourtSupreme Court of North Carolina
DecidedNovember 20, 1957
Docket394
StatusPublished
Cited by34 cases

This text of 100 S.E.2d 391 (Childress v. C. W. Myers Trading Post, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Childress v. C. W. Myers Trading Post, Inc., 100 S.E.2d 391, 247 N.C. 150, 1957 N.C. LEXIS 662 (N.C. 1957).

Opinion

Rodman, J.

Notwithstanding the reduction of the contract to writing, the parties are not in agreement as to the terms of the original contract. Was the house to be 30 feet or 28 feet wide? The writing is specific as to length but silent as to width. Was the fireplace to be installed over a full-size basement as the writing says, or was the fireplace to be installed in a full-sized basement and the house insulated overhead ? If plaintiffs’ version of the contract is correct, defendant has admittedly breached the contract. Neither of these conditions has been met.

Did the parties subsequently and by parol agree, (a) to change the color of the tile in the bathroom, (b) to change the color of the brick and mortar on the exterior, and (c) to extend time for the completion of the house? If the parties did not agree to these changes, the contract has admittedly been breached.

Did defendant fail to do the work in a first-class manner by providing defective and inadequate foundations and support for the house or roof?

*154 If the defendant breached its contract in some but not all of these particulars, was the breach of such a character as to justify a rescission, restoring to plaintiffs their property or its value, or could plaintiffs be fairly compensated by an award of damages ?

These questions arose on the pleadings and the evidence. They required answers before the rights of the parties could be determined. The court elected to submit only two issues to the jury, namely breach and damages. This restriction, it seems to us, unnecessarily complicated the problem of correctly instructing the jury.

That portion of the contract binding the parties to buy and sell had to be in writing because the statute so provides, but the portion relating to the kind of dwelling to be erected, its size, the materials to be used, and the time for completion could rest in parol, and this is true notwithstanding the provisions of Section 3 of the written contract.

“The provisions of a written contract may be modified or waived by a subsequent parol agreement, or by conduct which naturally and justly leads the other party to believe the provisions of the contract are modified or waived. Mfg. Co. v. Lefkowitz, 204 N.C. 449, 168 S.E. 517; Bixler v. Britton, 192 N.C. 199, 134 S.E. 488. This principle has been sustained even where the instrument provides for any modification of the contract to be in writing. Allen v. Bank, 180 N.C. 608, 105 S.E. 401.” Whitehurst v. FCX Fruit and Vegetable Service, 224 N.C. 628, 32 S.E. 2d 34.

Defendant alleged in its answer and offered evidence to support its allegation that the delay in completing the house was approved bjr plaintiff. Touching this question and the materiality of delay as affecting the rights of the parties, the court charged the jury: “Now, members of the jury, one of the provisions in the written contract was as to the time that the house was to be completed. The question, whether a contract must be performed at or within the exact time specified therein, is usually expressed in the inquiry as to whether the time is of the essence of the contract. Where the time is of the essence of a contract and there has been a failure of performance at or within the time promised, a breach of the contract results, which brings some of the consequences attendant upon a breach. The right to recover on a contract is conditioned upon performance within the time limit, where time is of the essence.

“Now, members of the jury, the plaintiffs say and contend that in this contract time is of the essence; that there wasn’t any point in putting that in the contract if it didn’t mean some *155 thing, and that certainly the defendant didn’t deliver in accord with those terms.”

The quoted portion of the charge was made the subject of exceptions by defendant. Following these statements of the law and contentions of the plaintiffs the court charged the jury that the defendant contended that plaintiffs had waived the provision of the contract requiring delivery by 21 August. It then charged: “Now, members of the jury, the Court charges you that if you are satisfied from this evidence and by its greater weight that this contract was breached on the part of the defendant, that the defendant couldn’t deliver according to the terms of the contract, then it would be your duty to answer that first issue Yes. If you are not so satisfied, you would answer it No.”

Dealing with defendant’s assertion of verbal modifications and waiver as to manner and time of construction, the Court charged the jury: “Now, members of the jury, the Court instructs you that, although the written contract between the parties, that is, Plaintiffs’ Exhibit A, is the written contract and provided that any substantial variations from the terms of the contract should be in writing, it was nevertheless permissible for the parties to the written agreement to waive that, or any other provision of the contract, and orally to agree to change the plans and specifications for the house, to be constructed by the defendant. In other words, members of the jury, if, after the written instrument was signed by the parties, they orally agree to changes that toere not substantial changes, that that would be all right; it would be considered as a part of the contract.” (Italics added.)

The quoted portion of the charge in effect told the jury only nonsubstantial changes in the contract could be made by parol and only such of these as related to plans and specifications.

Time for completion is not normally regarded as a part of the plans or specifications for the construction of a dwelling nor is time normally a substantial or vital element in a contract of purchase and sale. Douglass v. Brooks, 242 N.C. 178, 87 S.E. 2d 258; Cadillac-Pontiac Co. v. Norburn, 230 N.C. 23, 51 S.E. 2d 916; Crawford v. Allen, 189 N.C. 434, 127 S.E. 521; Davis v. Martin, 146 N.C. 281; Scarlett v. Hunter, 56 N.C. 84; Bryson v. Peak, 43 N.C. 310.

“As a general rule, time is not of the essence of a building or construction contract, in the absence of a provision in the contract making it such. Failure to complete the work within the specified time does not ipso facto terminate the contract, but only subjects the contractor to damages for the delay.” 9 Am. Jur. 36.

*156 If the parties verbally assented to extend the time for the completion of the building to October, the parties would be bound thereby notwithstanding Section 3 of the contract which required “substantial variations from the terms” to be in writing. It makes no difference whether the extension of time for completion be denominated a substantial or a nonsubstantial variation.

Did the parties agree to substitute another shade of green for the “nile green” called for as the color of the tile to be used in the bathroom? If so, was this a material or substantial change which could only be effected by written agreement under the rule laid down by the court in its charge?

Defendant admits that the tile used in the bathroom is not nile green.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Jones
Court of Appeals of North Carolina, 2025
Three Reasons, LLC v. JAB-C, LLC
W.D. North Carolina, 2024
The Town of Forest City v. Florence Redevelopment Partners
Court of Appeals of North Carolina, 2024
Gallaher v. Ciszek
2022 NCBC 67 (North Carolina Business Court, 2022)
Geiger v. Cent. Carolina Surgical Eye Assoc.s, P.A.
Court of Appeals of North Carolina, 2014
GRE Properties Thomasville LLC v. Libertywood Nursing Center, Inc.
761 S.E.2d 676 (Court of Appeals of North Carolina, 2014)
42 East, LLC v. D.R. Horton, Inc.
722 S.E.2d 1 (Court of Appeals of North Carolina, 2012)
Hardin v. KCS International, Inc.
682 S.E.2d 726 (Court of Appeals of North Carolina, 2009)
Nakell v. Liner Yankelevitz Sunshine & Regenstreif, LLP
394 F. Supp. 2d 762 (M.D. North Carolina, 2005)
Loomis v. Hamerah
538 S.E.2d 593 (Court of Appeals of North Carolina, 2000)
Camp v. Leonard
515 S.E.2d 909 (Court of Appeals of North Carolina, 1999)
Ackerman v. McMillan
442 S.E.2d 618 (Court of Appeals of South Carolina, 1994)
Mutual Benefit Life Insurance v. City of Winston-Salem
395 S.E.2d 705 (Court of Appeals of North Carolina, 1990)
Eastline Corp. v. Marion Apartments, Ltd.
524 So. 2d 582 (Mississippi Supreme Court, 1988)
Opsahl v. Pinehurst Inc.
344 S.E.2d 68 (Court of Appeals of North Carolina, 1986)
Town of Nags Head v. Tillett
336 S.E.2d 394 (Supreme Court of North Carolina, 1985)
Johnson v. SMITH, SCOTT & ASSOCIATES, INC.
335 S.E.2d 205 (Court of Appeals of North Carolina, 1985)
Pearce v. American Defender Life Insurance
330 S.E.2d 9 (Court of Appeals of North Carolina, 1985)
Biggers v. Evangelist
321 S.E.2d 524 (Court of Appeals of North Carolina, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
100 S.E.2d 391, 247 N.C. 150, 1957 N.C. LEXIS 662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/childress-v-c-w-myers-trading-post-inc-nc-1957.