Higginson v. Westergard

604 P.2d 51, 100 Idaho 687, 1979 Ida. LEXIS 518
CourtIdaho Supreme Court
DecidedNovember 27, 1979
Docket12771
StatusPublished
Cited by83 cases

This text of 604 P.2d 51 (Higginson v. Westergard) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Higginson v. Westergard, 604 P.2d 51, 100 Idaho 687, 1979 Ida. LEXIS 518 (Idaho 1979).

Opinion

DONALDSON, Chief Justice.

R. Keith Higginson, Director of the Idaho Department of Water Resources (department), originally brought this action in the district court in March, 1976 to compel defendant Golden C. Westergard to remove a gravel dike allegedly interfering with the flow of the Salmon River adjacent to property owned by Westergard in Custer County. The department appeals a district court judgment in Westergard’s favor.

On or about March 27, 1975, Westergard applied to the Department of Water Resources for a permit to conduct a streambed alteration. The purpose of the permit was to place gravel fill and rip rap rock on about 325 yards of eroded bank along riparian lands owned by Westergard on the east side of the Salmon River.

On his application, Westergard indicated that he would use a gravel bar, located in the west side of the river, as a source of fill material to be placed against the eroded east bank and then place the rip rap rock over the gravel. The application also stated that a caterpillar type tractor would be used to move the gravel and place it along the bank. Westergard’s application also stated that he would be working below the water surface, and intended to control the resulting turbidity and pollution by diverting as much water as possible around the work area. The application stated that diversion was to be accomplished by means of a temporary channel to be constructed through the gravel bar.

On April 25,1975, Kenneth Dunn, Administrator of the Operations Division of the Department, approved Westergard’s application, subject to certain conditions of which (5) and (7) are pertinent:

“(5) Water must be diverted around the work area during construction; the water to be returned to its original channel after construction is completed. . (7) The expiration date of this permit shall be May 30, 1975.”

On May 13, 1975, work on the stream alteration project was begun by Elmer Whiting, who was hired by Westergard. Using his tractor, Whiting windrowed gravel from the west gravel bar and from gravel out of the middle of the channel, thus in effect creating a temporary dike. He then began the process of pushing it over to the east bank of the river, the site of the erosion. Three days later, apparently in response to telephone calls from neighbors, the department’s regional supervisor, Mike Steel, arrived at the location of the stream alteration to investigate.

Upon arriving at the scene, Steel, upon viewing the high stage of the river and without prior notice to Westergard or his agent Whiting, ordered Westergard to remove the tractor from the river immediately. The parties are in dispute as to the precise nature of Steel’s order, with the *689 department claiming that Westergard was ordered to stop work only on the dike, with work on the bank project still permitted, while Westergard claims he was ordered out of the river at both places for an indefinite period of time.

As a result of being ordered from the river, Westergard never completed work on the bank project and the dike was not removed from the river. When it became apparent that the river would not wash the dike out, the department on January 29, 1976, directed Westergard to remove the dike. When Westergard failed to comply with the order, the department filed suit in the district court, seeking a decree enjoining him to do so.

Upon the department’s ex parte application Westergard was ordered to show cause why he should not be required to remove the dike. At the time of the hearing on the order to show cause, it was agreed by both parties to proceed to a trial on the merits that same day.

Thereafter, the district court by letter advised the parties of his opinion that the department had wrongfully interfered with the permitted work being performed by Westergard and was accordingly entitled to no relief. The department’s motion for new trial and alternatively, for reconsideration of the district court’s decision, was denied. The court’s decision in the form of amended findings of fact and conclusions of law was entered, finding that the department had acted without reasonable justification in ordering Westergard to terminate his work and that the department’s interruption of the work caused the channel alteration of which the department now complained. The court also found that the department failed to show irreparable harm from the presence of the dike in the stream and entered judgment for Westergard. The department appeals.

The department contends that there are three issues on appeal: (1) whether Westergard was in violation of his stream channel permit; (2) whether the record contains sufficient evidence to support the district court’s findings of fact and conclusions of law; and (3) assuming that Westergard was in violation of his stream channel permit, whether a mandatory injunction ordering Westergard to remove the dike from the river is a proper remedy under the Stream Channel Alteration Act, I.C. § 42-3801 et seq., or at common law.

In determining whether Westergard was in violation of his permit, we are limited on appeal to a review of those factual findings made by the lower court. I.R.C.P. 52(a); King v. H. J. McNeel, Inc., 94 Idaho 444, 489 P.2d 1324 (1971). Such findings of fact made by the trial court will not be set aside unless clearly erroneous. I.R.C.P. 52(a); Marshall Bros., Inc. v. Geisler, 99 Idaho 734, 588 P.2d 933 (1978); Matter of Estate of Courtright, 99 Idaho 575, 586 P.2d 265 (1978).

When findings of fact are challenged, the appellant has the burden of showing error, and the reviewing court will review the evidence in a light most favorable to the respondent. Glenn Dick Equipment Co. v. Galey Construction Co., Inc., 97 Idaho 216, 541 P.2d 1184 (1975); accord, Furness v. Park, 98 Idaho 617, 570 P.2d 854 (1977). In this case the trial court found that Westergard’s work conformed to the conditions of the permit. To determine whether such a finding was erroneous, a review of the permit and an examination of the record is in order.

Rule 6.1 of the Rules and Regulations for Stream Channel Alterations, provides that “all work shall be done in accordance with the application submitted and subject to any conditions specified on the permit.” Rules and Regulations, Department of Water Resources, State of Idaho, Stream Channel Alterations, Rule 6.1, 1978. 1 As noted in the department’s brief, the application form used by the department provides *690 for departmental action to be noted on the back page of the application, and the approved application becomes the permit.

The department argues that Westergard’s work was not in compliance with either item No. 10 of the submitted application or with condition No. 5 of the permit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Nathan David Neal
362 P.3d 514 (Idaho Supreme Court, 2015)
Northwest Farm Credit Services v. Lake Cascade Airpark, LLC
331 P.3d 500 (Idaho Supreme Court, 2014)
Alaska Public Offices Commission v. Stevens
205 P.3d 321 (Alaska Supreme Court, 2009)
State v. Mercer
138 P.3d 308 (Idaho Supreme Court, 2006)
Muchow v. State
128 P.3d 938 (Idaho Supreme Court, 2006)
Mallonee v. State
84 P.3d 551 (Idaho Supreme Court, 2004)
Gillihan v. Gump
99 P.3d 1083 (Idaho Court of Appeals, 2003)
Zattiero v. Homedale School District No. 370
51 P.3d 382 (Idaho Supreme Court, 2002)
Roeder Holdings, L.L.C. v. Board of Equalization
41 P.3d 237 (Idaho Supreme Court, 2001)
Mulder v. Liberty Northwest Insurance
14 P.3d 372 (Idaho Supreme Court, 2000)
Rule Sales & Service, Inc. v. U.S. Bank National Ass'n
991 P.2d 857 (Idaho Court of Appeals, 1999)
State v. Arrasmith
966 P.2d 33 (Idaho Court of Appeals, 1998)
Ada County v. Gibson
893 P.2d 801 (Idaho Court of Appeals, 1995)
Rhodes v. Industrial Commission
868 P.2d 467 (Idaho Supreme Court, 1993)
Dolph v. Hecla Mining Co.
810 P.2d 249 (Idaho Supreme Court, 1991)
State v. Missamore
803 P.2d 528 (Idaho Supreme Court, 1990)
Mead v. Arnell
791 P.2d 410 (Idaho Supreme Court, 1990)
In Re Western Acceptance Corp., Inc.
788 P.2d 214 (Idaho Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
604 P.2d 51, 100 Idaho 687, 1979 Ida. LEXIS 518, Counsel Stack Legal Research, https://law.counselstack.com/opinion/higginson-v-westergard-idaho-1979.