Hickman v. Layne

66 N.W. 298, 47 Neb. 177, 1896 Neb. LEXIS 589
CourtNebraska Supreme Court
DecidedFebruary 18, 1896
DocketNo. 6005
StatusPublished
Cited by20 cases

This text of 66 N.W. 298 (Hickman v. Layne) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hickman v. Layne, 66 N.W. 298, 47 Neb. 177, 1896 Neb. LEXIS 589 (Neb. 1896).

Opinion

Norval, J.

This action was brought upon the bond hereinafter mentioned by Isaac N. Hickman against John Layne and Fred W. Krone, partners as Layne & Krone, George Martin, N.. Westovér, George Sherer, A. B. Beach, J. E. Stockwell, N. N. Menard, Fred Voight, and W. Henegan to recover for materials alleged to have been sold and delivered to Layne & Krone by one John Ellis, and used by them in the erection, for the state, at Beatrice in 1887, a building for the institution for the feeble-minded. Layne & Krone entered into a written contract with the board of public lands and buildings to furnish the materials and labor and to erect said building for a stipulated price, payable as the work progressed on the monthly estimates of the superintendent of construction, which contract contained a provision to the effect that Layne & Krone should pay off and settle in [179]*179full with all parties entitled thereto claims that should become due by reason of labor and materials furnished or used in the construction of the building. A bond for the faithful compliance with the contract was given to the state by Layne & Krone, which was also signed by the other defendants, some of them as sureties and others as witnesses to its execution merely. This bond, with the exception of the parties, date, and amount of the penalty, being identical with the one involved in Sample v. Hale, 34 Neb., 220, will not be set out in this opinion. Subsequent to the execution of the bond and contract aforesaid John Ellis furnished the contractors the stone and concrete used in the building, amounting to $2,124.16, upon which has been paid $1,902.02, and no more, leaving a balance due therefor of $222.14. The account for the materials so furnished has been duly transferred by Ellis to this plaintiff, who brings this action to recover said balance against the principals and sureties upon said bond. Layne interposed no defense. The other defendants answered the petition by a general denial, and as a second defense alleged that prior to the furnishing of the materials, for which compensation is demanded, the firm of Layne & Krone had dissolved, said Krone retiring from the firm, of which plaintiff and his assignor had knowledge and notice, and that Layne alone is liable for the payment of said materials. By stipulation of the parties in open court the jury returned a verdict for Menard, Yoight, and Henegan, they having signed the bond as witnesses. The jury found for plaintiff against the defendant Layne for the full amount claimed, and also in favor of the other defendants.

[180]*180That the bond given to the state inured to the benefit of the subcontractors of Layne & Krone, and that such subcontractors could maintain an action for a breach of the conditions of the bond, is settled by repeated decisions of this court. (Sample v. Hale, 34 Neb., 220; Habig v. Layne, 38 Neb., 747; Lyman v. City of Lincoln, 38 Neb., 794; Doll v. Crume, 41 Neb., 655; Korsmeyer Plumbing & Heating Co. v. McClay, 43 Neb., 649; Kaufmann v. Cooper, 46 Neb., 644.) The first question, therefore, to be considered is whether the materials, for the value of which this suit is brought, were furnished by plaintiff’s assignor, Ellis, to the firm of Layne &. Krone or under a contract with them, or to John Layne alone on his individual account. The partnership of Layne & Krone was dissolved on November 9, 1887, the defendant Krone retiring from the firm, and the business was thereafter conducted by Layne in his own name, who completed the building. A considerable portion of the materials had already been furnished by Ellis at the date of said dissolution, and payment therefor has been made. The amount claimed in this .action is for a part of the materials delivered since November 9. It is claimed by plaintiff in argument that all the materials were delivered under a contract entered into by Ellis with Layne .& Krone about October 1, 1887, and during the ■existence of the partnership. This the defendant insists is incorrect. The testimony on behalf of the plaintiff adduced on the trial, and which is embodied in the bill of exceptions, fully sustains the theory and contention of the plaintiff. On the other hand, the inference could be properly drawn from portions of the testimony of the defendant Layne that no contract was made with his [181]*181firm, whereby it agreed to furnish any certain amount of stone for the erection of the building; that prices were named on the different kinds of stone, but the firm did not agree to take, nor did Ellis agree to deliver what stone should be required to complete the building or any part thereof; that the stone was ordered as it was needed from time to time; that after the dissolution in the name of Layne, and a portion of this was paid by the individual check of the latter.While the testimony of this witness is in some particulars weak and evasive, we cannot say that the jury were not warranted in finding-that the materials in dispute were not furnished under and in pursuance of a contract with the firm of Layne & Krone, although the preponderance of the evidence would have justified a different conclusion. In this connection it may not be amiss to state that' no express contract with Layne & Krone for the furnishing of the materials is averred in the petition, the allegation being that they were furnished at their request. It is true,as argued by counsel, that partners are not released from unfulfilled contracts and obligations by the dissolution of the firm. Such was the decision in Swobe v. New Omaha Thomson-Houston Electric Light Co., 39 Neb., 587. But this principle could only be invoked by the plaintiff in case he established that Layne & Krone agreed with Ellis to take from him all the stone required for the erection of the building, and all that was received was delivered under such agreement. The jury having found against the plaintiff on the facts, the principle of law invoked by plaintiff that partners cannot by dissolving release themselves from unfulfilled contracts is not applicable to the case ■ under consideration.

[182]*182Complaint is made in the brief of the third and fourth instructions given by the court on its own motion, and the refusal to give the plaintiff’s third, fourth, and sixth requests. The court’s charge consists of five separately numbered paragraphs, and the giving of them all, as well as the three requests refused, is assigned for error in the motion for a new trial as follows:

“5. The court erred in giving paragraphs of instructions numbered 1, 2, 3, 4, 5 on its own motion.
“6. The court erred in refusing to give paragraphs of instructions numbered 3, 4, and 6, asked by the plaintiff.”

The first and second instructions were properly given. The first briefly stated the nature of the action, and the second told the jury that, under the stipulation of the parties, they should return a verdict for Menard, Voight, and Henegan. There being no error in either of these instructions, the fifth subdivision of the motion for a new trial was not well taken. It is needless to cite authorities in support of this familiar rule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marquardt v. NEHAWKA FARMERS COOPERATIVE CO.
184 N.W.2d 617 (Nebraska Supreme Court, 1971)
Rath v. Sanitary Dist. No. 1 of Lancaster County
56 N.W.2d 741 (Nebraska Supreme Court, 1953)
Vaca v. State
34 N.W.2d 873 (Nebraska Supreme Court, 1948)
McDowell v. Parker
34 N.W.2d 366 (Nebraska Supreme Court, 1948)
Kling v. Crown Finance Corp.
146 P.2d 54 (California Court of Appeal, 1944)
Stow v. Bruce
1936 OK 417 (Supreme Court of Oklahoma, 1936)
J. I. Case Co. v. Hrubesky
251 N.W. 169 (Nebraska Supreme Court, 1933)
Brown v. McNair
1927 OK 89 (Supreme Court of Oklahoma, 1927)
Fulghum & Union Indemnity Co. v. State
109 So. 644 (Supreme Court of Florida, 1926)
Dawson v. United States
10 F.2d 106 (Ninth Circuit, 1926)
Barker v. Wheeler
99 N.W. 548 (Nebraska Supreme Court, 1904)
Cudahy Packing Co. v. Skoumal
125 F. 470 (Eighth Circuit, 1903)
Pickle Marble & Granite Co. v. McClay
74 N.W. 1062 (Nebraska Supreme Court, 1898)
Brumback v. American Bank
74 N.W. 264 (Nebraska Supreme Court, 1898)
Metropolitan National Bank v. Commercial State Bank
74 N.W. 26 (Supreme Court of Iowa, 1898)
Rohman v. Gaiser
73 N.W. 923 (Nebraska Supreme Court, 1898)
Whitney v. State
73 N.W. 696 (Nebraska Supreme Court, 1898)
Barritt S. King & Co. v. Murphy
68 N.W. 1029 (Nebraska Supreme Court, 1896)
Fitzgerald v. McClay
66 N.W. 828 (Nebraska Supreme Court, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
66 N.W. 298, 47 Neb. 177, 1896 Neb. LEXIS 589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hickman-v-layne-neb-1896.