Hi-Point Home v. Luman

Colorado Court of Appeals·Decided December 24, 2025·No. 24CA1291·Unpublished

Opinion

24CA1291 Hi-Point Home v Luman 12-24-2025 COLORADO COURT OF APPEALS

Court of Appeals No. 24CA1291 El Paso County District Court No. 22CV32033 Honorable Gregory R. Werner, Judge

Hi-Point Home Builders, LLC, a Colorado limited liability company, Plaintiff-Appellant, v. John Paul Luman and Nicole L. Luman, Defendants-Appellees.

JUDGMENT AFFIRMED

Division V

Opinion by JUDGE WELLING

Grove and Johnson, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e)

Announced December 24, 2025

Ranson & Kane PC, Jason P. Kane, Denver, Colorado, for Plaintiff-Appellant

Robinson & Henry, P.C., Alicia M. Reinken, Highlands Ranch, Colorado, for Defendants-Appellees

¶1 Hi-Point Home Builders, LLC (Hi-Point), appeals the trial court’s order denying its breach of contract claim against John and Nicole Luman for the construction and purchase of a home. We affirm.

I. Background

¶2 In June 2021, the parties entered into a contract whereby Hi- Point would construct a custom home for the Lumans for a purchase price of $1,087,000, plus the costs of any special designs or add-ons that the Lumans requested. The Lumans requested several such changes that, by May of 2022, had raised the price to $1,105,392. In conjunction with the execution of the contract, the Lumans paid Hi-Point $10,000 in earnest money and a $3,500 deposit for the land the house would be built on.

¶3 Because John Luman is a veteran, the Lumans intended to finance the purchase of the home through a Department of Veterans Affairs (VA) loan. The VA requires that every VA loan include an “escape clause.” A VA loan escape clause allows a homebuyer to cancel their contract — and recoup their earnest money — if the house being purchased appraises for less than the

sales price. The contract between the parties contained such a clause.

¶4 The house was to be completed by August 30, 2022. By June 2022, the Lumans had grown unhappy with some of Hi- Point’s work on the house. For example, the Lumans complained that lights, windows, a cabinet door, and rounded corners on the inside of the house weren’t what they wanted. Then, when it was time to install the septic system — a project that Hi-Point had budgeted at $18,000 — the quote came back at $66,000.

¶5 John Luman was upset about the discrepancy, and, on June 27, he sent an email to Hi-Point listing many of the Lumans’ complaints about the construction project, including the unexpectedly high septic system bid. Hi-Point responded to that email on the same day, explaining that (1) the Lumans had agreed to many of the details they complained about; (2) they could pay extra to change some of them; and (3) Hi-Point was trying to decrease the cost of the septic system.

¶6 Nevertheless, two days later, on June 29, John Luman sent another email purporting to terminate the contract between the Lumans and Hi-Point. The email read as follows:

This will serve as the official buyers termination notice for the purchase contract between Hi-Point Homes and John and Nicole Luman for [the] property [in] Colorado Springs, Co 80831. This notice is being provided in accordance with page 28, section 11.2 of such contract. Further documentation can be provided upon request.

¶7 After receiving the Lumans’ June 29 termination email, Hi- Point began making changes to the home that it believed would make the home easier to sell on the open market. Despite making significant changes following the Lumans’ termination email, Hi- Point also sent the Lumans a letter through counsel on July 15 stating that Hi-Point still expected the Lumans to fulfil their obligations under the contract.

¶8 On August 2, the Lumans arranged to have the house appraised by a VA appraiser, John Freeman. The adjusted purchase price at that time, including Hi-Point’s additional changes, was $1,106,400, and the VA escape clause gave the Lumans the right to terminate the contract if the home appraised below that amount. The Lumans provided Freeman with several other homes as comparables, but none of those comparables were priced over $1 million. Ultimately, Freeman appraised the home at

$1.1 million — $6,400 less than the sales price. Because the home appraised for less than the sales price, on August 17, 2022, the Lumans exercised their rights under the VA loan escape clause to terminate the contract.

¶9 In November 2022, Hi-Point sued the Lumans for breach of contract. The Lumans asserted counterclaims, alleging, among other things, that Hi-Point had breached the contract.1

¶ 10 In May 2023, the matter proceeded to a three-day bench trial on the parties’ competing breach of contract claims. The issues before the trial court included both parties’ claims that the other party had breached the contract. Hi-Point was able to sell the house to different buyers shortly before the trial began in May 2023 for $1,168,149.21. Still, at trial, Hi-Point claimed damages of $45,980.46 due to extra carrying costs.

¶ 11 In a thorough and detailed written order, the trial court determined that neither party breached the contract. In rejecting

1 The Lumans also asserted a claim against Hi-Point under the

Colorado Consumer Protection Act. That claim was dismissed, and the dismissal of that claim isn’t being appealed.

Hi-Point’s breach of contract claim against the Lumans, the court made extensive findings, including the following:

• The Lumans’ June 29 email purporting to terminate the contract was “ineffectual” in doing so because it wasn’t in compliance with the notice requirements of section 11.1.

• At all times preceding the June 29 email, the Lumans were in compliance with their contractual obligations, including having paid for every change they had requested to the design of the house.

• Following the June 29 email, the only performance under the contract that remained for the Lumans was to purchase the home. So the Lumans never materially breached the contract.

• After the Lumans’ last requested change to the original design of the house, the adjusted sales price was $1,105,392.

• After all the changes Hi-Point made to the home to make it more marketable, the adjusted sales price of the house was similar — $1,106,400.

• The VA loan escape clause allowed the Lumans to terminate the contract without suffering the penalty of losing their earnest money and without further obligation to purchase the house if it appraised for less than the sales price.

• The house appraised for $1.1 million, which was less than the sales price, permitting the Lumans to invoke the VA loan escape clause.

• Because the Lumans properly exercised their rights under the VA loan escape clause, they didn’t breach the contract.

• The Lumans would have purchased the home had it appraised at or above the sales price.

¶ 12 Based on these findings, the court entered judgment in favor of the Lumans and against Hi-Point on Hi-Point’s breach of contract claim against the Lumans. It also awarded the Lumans the $13,500 of earnest money they paid to Hi-Point when they signed the contract. Last, the court found that the Lumans were the prevailing parties and awarded them their costs associated with the litigation. Only Hi-Point appeals.

II. Issues On Appeal

¶ 13 Hi-Point argues that the trial court erred by (1) determining that the Lumans’ June 29 purported termination email wasn’t a material breach of the parties’ contract; (2) ruling that the Lumans weren’t barred from invoking the VA loan escape clause to terminate the contract due to their prior material breach; (3) failing to address Hi-Point’s argument that the Lumans violated their implied duty of fair dealing with respect to their invocation of the VA loan escape clause; and (4) determining that the Lumans were the prevailing party and awarding them their costs. We address and reject Hi-Point’s arguments in turn below.

A. The Lumans Didn’t Materially Breach the Contract

Free access — add to your briefcase to read the full text and ask questions with AI

Hi-Point Home v. Luman, (Colo. Ct. App. 2025).

Hi-Point Home v. Luman (Hi-Point Home v. Luman) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Leprino Foods Co. v. Factory Mutual Insurance
653 F.3d 1121 (Tenth Circuit, 2011)
Amoco Oil Co. v. Ervin
908 P.2d 493 (Supreme Court of Colorado, 1996)
Anderson v. Pursell
244 P.3d 1188 (Supreme Court of Colorado, 2011)
One Creative Place, LLC v. Jet Center Partners, LLC
259 P.3d 1287 (Colorado Court of Appeals, 2011)
Anderson v. Vail Corp.
251 P.3d 1125 (Colorado Court of Appeals, 2010)
Coors v. Security Life of Denver Insurance Co.
112 P.3d 59 (Supreme Court of Colorado, 2005)
GF Gaming Corp. v. Taylor
205 P.3d 523 (Colorado Court of Appeals, 2009)
Highlands Ranch University Park, LLC v. Uno of Highlands Ranch, Inc.
129 P.3d 1020 (Colorado Court of Appeals, 2005)
New Design Construction Co. v. Hamon Contractors, Inc.
215 P.3d 1172 (Colorado Court of Appeals, 2008)
People v. Heredia-Cobos
2017 COA 130 (Colorado Court of Appeals, 2017)
Jacqueline Gebert v. Sears, Roebuck & Co.
2023 COA 107 (Colorado Court of Appeals, 2023)