Heritage Construction Group, LLC v. Karen Vest

CourtCourt of Appeals of Tennessee
DecidedApril 30, 2024
DocketM2023-00028-COA-R3-CV
StatusPublished

This text of Heritage Construction Group, LLC v. Karen Vest (Heritage Construction Group, LLC v. Karen Vest) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heritage Construction Group, LLC v. Karen Vest, (Tenn. Ct. App. 2024).

Opinion

04/30/2024 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE December 5, 2023 Session

HERITAGE CONSTRUCTION GROUP, LLC v. KAREN VEST

Appeal from the Chancery Court for Maury County No. 19-655 Christopher V. Sockwell, Judge ___________________________________

No. M2023-00028-COA-R3-CV ___________________________________

A homebuilder sought to modify, correct, or vacate an arbitration award. It claimed the arbitrator exceeded his powers in failing to award attorney’s fees and penalties under its contract with the homeowner. The chancery court denied the requested relief and awarded the homeowner attorney’s fees for defending against the homebuilder’s motion. Discerning no error, we affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

W. NEAL MCBRAYER, J., delivered the opinion of the court, in which FRANK G. CLEMENT JR., P.J., M.S, and ANDY D. BENNETT, J., joined.

J. Brad Scarbrough, Nashville, Tennessee, for the appellant, Heritage Construction Group, LLC.

Kori Bledsoe Jones, Columbia, Tennessee, for the appellee, Karen Vest.

OPINION

I.

A.

Karen Vest signed a cost-plus contract with Heritage Construction Group, LLC for the construction of a custom home. The contract left a great deal to be desired. Among other problems, the contract described Heritage’s “plus” or “builder’s fee” as “twenty-two and one half (30%) percent of all construction costs.” The contract recited an estimate for completion of the home of $370,000 but included an attachment showing an estimate of $380,244.12. And the contract specified that the cost of labor and materials and the builder’s fee “would be drawn in accordance with guidelines reflected on Exhibit A,” but no guidelines were attached. Helpfully, the contract did provide that for each draw Heritage would deliver “a written construction draw request” and that Ms. Vest would have five days from receipt of the request to make payment to Heritage.

Despite the deficiencies, after payments by Ms. Vest of $470,233.26, a certificate of occupancy for the custom home was issued. Heritage’s sole member, Trevor Pennington, emailed Ms. Vest that “[y]our move in is legal. Have a great weekend in your new home.” And he posted pictures on Facebook of “another happy customer.” But Ms. Vest’s happiness was short-lived.

The next month Heritage made a demand for an additional $147,776.78 payment. When payment was not forthcoming, Heritage notified Ms. Vest that her occupancy of the home violated the contract and triggered “a penalty of $250.00 per day for each day” Heritage went unpaid. Later, Heritage recorded a mechanics’ and materialmen’s lien against the property, claiming $161,719.30 was still due under its contract with Ms. Vest. See Tenn. Code Ann. §§ 66-11-102(a), -112(a) (2022). The amount of the lien was calculated based on a builder’s fee of 30% and included interest and penalties. Heritage followed that up with a chancery court suit against Ms. Vest to enforce its lien. Id. § 66-11-126(1) (2022).

Although suit was filed, Heritage alleged that “[a]ll remaining claims and disputes between the parties are subject to arbitration pursuant to the Contract and [Heritage] does not waive enforcement of the arbitration provision by filing this action to enforce its Lien.” So, with the agreement of Heritage and Ms. Vest, the chancery court ordered the case stayed pending a final award in arbitration.

B.

By the time of the arbitration hearing, Heritage and Ms. Vest had stipulated to some important facts. They stipulated to $477,360.71 of the construction costs incurred by Heritage and that the builder’s fee was 22.5%. They also had significantly narrowed the issues.

The parties submitted basically three claims for the arbitrator to decide. First, Heritage claimed an additional $5,874.25 in construction costs that Ms. Vest disputed. Second, Heritage claimed that Ms. Vest breached the contract and that it was entitled to interest on the unpaid balance under the contract and a $250 per day penalty for each day Ms. Vest occupied the home. Third, both parties claimed entitlement to attorney’s fees and the costs of arbitration.

2 On the first claim, after the parties further compromised the amount in dispute, the arbitrator ordered Ms. Vest to pay $1,501.15 plus the associated builder’s fee. The arbitrator found that Heritage failed to carry its burden to prove entitlement to the remaining amounts in dispute.

In considering the second claim, the arbitrator began with the language of the contract, which provided Heritage would deliver written construction draw requests and Ms. Vest would have five days from receipt to pay. The arbitrator found Heritage’s “blatant disregard of this central payment provision and protocol in its own contract was astounding.” The arbitrator also found that Heritage had sought to enforce its claims for a final payment before Ms. Vest’s obligation to make a final payment had arisen. Heritage’s final payment demand was “yet another oral and unsubstantiated request.” And, when Ms. Vest made “continuing, repeated, and persistent requests for copies of actual invoices and/or an accounting to determine what she actually owed,” Heritage, through Mr. Pennington, essentially “held the invoices hostage by agreeing to provide them only upon the simultaneous receipt of a check” from Ms. Vest. The arbitrator determined that Heritage only complied with the contract when its attorney sent a demand letter a few weeks before filing suit to enforce its mechanics’ and materialmen’s lien. That letter covered “a binder containing a discernible accounting and itemization.”

The arbitrator found that Ms. Vest “obviously accepted the final accounting prepared and produced by [Heritage’s] counsel” except for the builder’s fee, which was asserted to be 30% in the letter, and the few disputed costs that were reserved for the arbitration hearing. She had failed to pay those amounts and instead placed the money in trust pending completion of arbitration. Alternatively, she had offered to release the funds if Heritage would accept them as a “final payment . . . and the complete amount due in this matter.” The arbitrator determined that the “appropriate, logical, and reasonable thing to do was to pay these funds to [Heritage] without conditions and simply reserve all . . . rights to contest the disputed builder’s fee and other charges being asserted against [Ms. Vest] in the pending arbitration.” So he concluded that Ms. Vest owed 18% interest on those amounts through the date of payment to Heritage.1

The arbitrator denied Heritage’s claim for a $250 per day penalty for Ms. Vest’s occupancy of the home, which had ballooned to over $100,000 by the arbitration hearing. By its terms, the contract prohibited Ms. Vest from taking possession of or occupying her home until Heritage had been fully paid. Violation of the clause “result[ed] in a penalty of $250.00 per day for each day of Owner’s wrongful possession or occupancy.” The arbitrator reasoned that the “penalty was precisely that, a penalty unenforceable under

1 The contract provided that, if Ms. Vest failed or refused to pay as required, unpaid construction costs would “draw interest at the lower rate of eighteen (18%) percent [sic] per annum or the maximum lawful contractual rate.”

3 Tennessee law,” but it was unnecessary to reach that issue because “[t]he evidence in this case unmistakably proved that [Heritage] expressly and clearly waived the . . . penalty.” It did so when Mr. Pennington emailed Ms. Vest that her “move in is legal,” gave her the keys without restrictions, and posted on his page about “another happy customer.” The arbitrator was unpersuaded by Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Steelworkers v. Enterprise Wheel & Car Corp.
363 U.S. 593 (Supreme Court, 1960)
Tina Marie Hodge v. Chadwick Craig
382 S.W.3d 325 (Tennessee Supreme Court, 2012)
Cracker Barrel Old Country Store, Inc. v. Epperson
284 S.W.3d 303 (Tennessee Supreme Court, 2009)
Federated Stores Realty, Inc. v. Huddleston
852 S.W.2d 206 (Tennessee Supreme Court, 1992)
Arnold v. Morgan Keegan & Co., Inc.
914 S.W.2d 445 (Tennessee Supreme Court, 1996)
Major League Baseball Players Assn. v. Garvey
532 U.S. 504 (Supreme Court, 2001)
Zeon Chems. v. United Food & Commercial Workers
949 F.3d 980 (Sixth Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Heritage Construction Group, LLC v. Karen Vest, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heritage-construction-group-llc-v-karen-vest-tennctapp-2024.