Henkels & McCoy, Inc. v. Adochio

906 F. Supp. 244, 1995 U.S. Dist. LEXIS 15729, 1995 WL 628177
CourtDistrict Court, E.D. Pennsylvania
DecidedOctober 26, 1995
DocketCiv. A. 94-3958
StatusPublished
Cited by5 cases

This text of 906 F. Supp. 244 (Henkels & McCoy, Inc. v. Adochio) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henkels & McCoy, Inc. v. Adochio, 906 F. Supp. 244, 1995 U.S. Dist. LEXIS 15729, 1995 WL 628177 (E.D. Pa. 1995).

Opinion

*247 MEMORANDUM

LOWELL A. REED, Jr., District Judge.

Plaintiff Henkels & McCoy, Inc. brings this action under N.J.Stat.Ann. § 42:2A-46(b) against nineteen limited partners of Red Hawk North Associates, L.P. (“Red Hawk”), a New Jersey limited partnership. Plaintiff alleges that these defendants have received cash distributions from Red Hawk in violation of the Red Hawk Agreement of Limited Partnership and the Red Hawk Limited Partnership Certificate. Plaintiff seeks to have these funds returned to Red Hawk in order that a judgment plaintiff has obtained against Red Hawk may be satisfied. This Court has jurisdiction over this case pursuant to 28 U.S.C. § 1332 as the parties are of diverse citizenship and the amount in controversy is in excess of $50,000, exclusive of interest and costs.

Currently before the Court are the motion by defendants for summary judgment and the cross-motion by plaintiffs for summary judgment. (Document Nos. 27, 30) For the following reasons, both motions will be denied.

I. FACTUAL BACKGROUND

The following facts are undisputed.

In 1987 or 1988, Red Hawk and Cedar Ridge Development Corporation (“Cedar Ridge”), a New Jersey corporation, entered into a “Joint Venture Agreement” in order to form a partnership which was given the name Chestnut Woods Partnership (“Chestnut Woods”). Red Hawk and Cedar Ridge were both general partners of Chestnut Woods. Chestnut Woods was formed for the purpose of developing and then selling certain real property located in Bucks County, Pennsylvania (the “Property”) which Cedar Ridge had previously arranged to purchase. Under the terms of the Joint Venture Agreement, Red Hawk agreed to provide $650,000 of capital for this development, and Cedar Ridge agreed to act as the Managing Partner and the General Contractor for the partnership and to assign the purchase agreement for the Property to the partnership.

On December 29, 1988, Cedar Ridge entered into a “Subcontract Agreement” with plaintiff; in that agreement, Cedar Ridge agreed to pay plaintiff a fixed price of $300,-270 for the installation of storm and sanitary sewer systems on the Property. The Subcontract Agreement identified Cedar Ridge solely as the General Contractor for the development project. No mention of the partnership connection between Cedar Ridge and Chestnut Woods was made in the agreement, and plaintiff was unaware that Cedar Ridge was a partner in Chestnut Woods when plaintiff entered into the agreement.

Plaintiff began work on the sewer systems project on January 16, 1989. Plaintiffs first two invoices to Cedar Ridge, sent in February and May of 1989, were paid in full by Cedar Ridge, with plaintiff receiving payment on April 6, 1989 and July 12, 1989 respectively. Plaintiffs August, September and November invoices were not paid in full, however; Cedar Ridge only paid $25,000 on the $215,174.50 August invoice and made no payments on the other two invoices, leaving a total unpaid balance of $237,943.50.

Also during 1989, Cedar Ridge made various cash payments to Red Hawk, and Red Hawk then distributed the bulk of those payments to its limited partners. On January 6, 1989, Cedar Ridge made a payment to Red Hawk in the amount of $78,750, and on January 11, 1989, Red Hawk in turn made a distribution to its limited partners in the amount of $76,923, leaving a balance of $1,904 in Red Hawk’s checking account. On April 4, 1989, Cedar Ridge made payment to Red Hawk in the amount of $215,000 and on the same day Red Hawk made distributions to its limited partners of $210,000, leaving a balance of $5,782 in Red Hawk’s checking account. And finally, on July 6, 1989, Cedar Ridge made a payment to Red Hawk in the amount of $215,000, and on either July 7, 1989 or July 10,1989, Red Hawk made distributions to its limited partners of $210,000, leaving a balance of $8,779 in Red Hawk’s checking account. Despite these low cash balances, it is undisputed that Red Hawk was solvent throughout 1989.

On March 16, 1990, Cedar Ridge sold its remaining assets to Red Hawk. Then in April 1990, G & A Development Corporation (“G & A”), the general partner for Red *248 Hawk, entered into an agreement with plaintiff for the payment of Cedar Ridge’s outstanding obligations to plaintiff, including $12,002.16 in interest on those obligations. Only two payments, $3,000 in April 1990 and $5,000 in June 1990, were made to plaintiff pursuant to this agreement, however.

On December 19, 1990, plaintiff brought suit in the United States District Court for the Eastern District of Pennsylvania against Cedar Ridge and Red Hawk, trading as Chestnut Woods. In its complaint, plaintiff made claims of breach of the Subcontract Agreement, breach of the April 1990 agreement, unjust enrichment, quantum meruit, and conspiracy to defraud. On October 15, 1991, judgement was entered for plaintiff and against Cedar Ridge and Red Hawk in the amount of $282,421.55, including interest. Plaintiff then discovered, however, that Cedar Ridge and Red Hawk were unable to satisfy this judgment, and to date the judgment has not been satisfied in whole or in part.

Plaintiff then brought suit in June 1992 against G & A in its capacity as general partner of Red Hawk for the amount of the previously obtained judgment. On August 12, 1992, default judgment was -entered against G & A in the amount of $282,424.55 1 plus interest at 6% per annum from October 15, 1991. After obtaining this default judgment, plaintiff learned that G & A was also unable to satisfy the judgment against it, and to date this second judgment has also not been satisfied in whole or in part. Plaintiff then filed the instant suit on June 27, 1994 seeking to have defendants return to Red Hawk the cash distributions they received in 1989 as limited partners so that Red Hawk could satisfy the judgment obtained by plaintiff against it.

II. DISCUSSION

Under Fed.R.Civ.P. 56(c), summary judgment may be granted when, “after considering the record evidence in the light most favorable to the nonmoving party, no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law.” Turner v. Schering-Plough Corp., 901 F.2d 335, 340 (3d Cir.1990). For a dispute to be “genuine,” the evidence must be such that a reasonable jury could return a verdict for the nonmoving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986).

Defendants argue that they are entitled to summary judgment because (1) plaintiffs claim against them is barred by New Jersey’s entire controversy doctrine, (2) creditors of limited partnerships lack standing to bring an action under N.J.Stat.Ann. § 42:2A-46(b), and (3) even if creditors do have such standing, plaintiff was not a creditor of Red Hawk when the distributions were made in 1989.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
906 F. Supp. 244, 1995 U.S. Dist. LEXIS 15729, 1995 WL 628177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henkels-mccoy-inc-v-adochio-paed-1995.