Hejran Hejrat Co. LTD

CourtArmed Services Board of Contract Appeals
DecidedApril 23, 2018
DocketASBCA No. 61234
StatusPublished

This text of Hejran Hejrat Co. LTD (Hejran Hejrat Co. LTD) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hejran Hejrat Co. LTD, (asbca 2018).

Opinion

.ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Hejran Hejrat Co. LTD ) ASBCA No. 61234 ) Under Contract No. W5J9JE- l l-C-O 115 )

APPEARANCE FOR THE APPELLANT: Joseph A. Hennessey, Esq. Chevy Chase, MD

APPEARANCES FOR THE GOVERNMENT: Thomas J. Warren, Esq. Acting Engineer Chief Trial Attorney Pietro 0. Mistretta, Esq. Aimee L. Rider, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE KINNER ON THE GOVERNMENT'S MOTION TO DISMISS

The Army Corps of Engineers (the Corps) moves to dismiss the appeal of Hejran Hejrat Co. LTD (HHL) for its failure to comply with the requirements for our jurisdiction pursuant to the Contract Disputes Act (CDA) 41 U.S.C. § 7103(b)(l).

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

After several rounds of price negotiations, the Corps awarded HHL a contract for lease of armored utility vehicles for use in Afghanistan (comp I. ,r,r 17-20; R4, tab 10). Corps personnel scheduled meetings to prepare for implementation of the contract (compl. ,r,r 25-26, 28). Prior to the second scheduled meeting, HHL was directed by the contracting officer to suspend all work because the contract was suspended, apparently due to a bid protest (compl. ,r,r 33, 35; R4, tab 30). The Corps took corrective action in response to the protest, which included obtaining resubmission of proposals without re-solicitation ( compl. ,r 40). On 8 August 2011, HHL was again awarded the contract, although the original award had only been suspended (compl. ,r 50; R4, tab 32). HHL informed the contracting officer that it incurred additional costs due to the time necessary for the corrective action, the reduction of the contract price, and a delay in the issuance of the notice to proceed ( comp I. ,r 54 ). There is no evidence whether the Corps considered HHL's concerns regarding additional costs. Instead, Modification No. POOOOl was issued 14 August 2011 (compl. ,r 53; R4, tab 11). The unilateral modification lifted the prior award suspension; decreased the contract price from $9,364,707 to $8,787,800; revised the performance work statement to reflect delays in government furnished equipment; declared that an equitable adjustment due to the suspension was not required and that the Corps was absolved of any claims due to that suspension (id.).

Before the end of the performance period, in July 2012, HHL was informed the Corps would not exercise an option on the contract ( comp I. 1 68; R4, tab 50). When asked for a final invoice and a release of claims to close out the contract, HHL informed the Corps that it was due additional payments and some vehicles were missing (compl. 174). HHL's requests for additional payment were made by submitting invoices (compl. 1174, 77; app. supp. R4, tab 79 at 451; R4, tabs 78-80). The invoices requested $4,137,964 of additional compensation (compl. 1177, 82). On 12 September 2013, a contracting officer, Sara Jackets, responded to HHL's three mv01ces:

This letter is in response to your three (3) invoices HHL-USACE/015, HHL-USACE/016 and HHL-USACE/016 submitted for contract W5J9JE-l 1-C-0I l5 on 22 August 2013. Although you used the word 'claim' and 'compensation' in your email and invoices, I have treated this as a request for equitable adjustment (REA) because it is not clear that you were seeking a contracting officer's final decision.

(R4, tab 59) Ms. Jackets asked HHL to inform her if the company intended to submit a claim or sought a contracting officer's final decision (id.). In a 31 January 2014 email, HHL specifically informed the Corps that it had not intended the email submitting its three invoices to be considered an REA (R4, tab 64 at 8-9). With respect to the 31 January 2014 email, however, HHL explained the purpose of that email: "We therefore ask you to treat this email together with the supporting documents as a REA. In the event that you decide to treat this email as REA and still reject our request for the adjustment of payments, we would then proceed with issuing a certified claim." (Id.) The email contained descriptions of the grounds for additional payment: "1. Compensation of cost reduction due to unfair reposting of solicitation and divulging of our company's awarded price and the loss of rental fee compensation for a period of two months"; "2. Compensation as result of modification # 4, Add and Remove Clause which resulted in early return of vehicles"; "3. Compensation Cost for 4 missing Armored vehicles plus rental fee for the 4 vehicle for a period 16 months"; "4. Revision of invoices for leasing"; "5. Cost for Unscheduled Maintenance" (id. at 9-12). HHL emphasized its intent that the email, with the submitted supporting documentation, be considered an REA: "We reiterate that this email together with the supporting documents be treated as a REA" (id. at 13). HHL did not request a contracting officer's final decision or provide a certification with that email (id.). HHL sent a similar email, forwarding revised invoices, on 16 April 2014 (compl. 182; R4, tab 64 at 6).

2 Notwithstanding its 31 January and 16 April 2014 emails, HHL asserts that it did not attempt to submit.an REA until March 2015 (compl. ,r,r 81, 83). In an email on 5 March 2015, HHL requested additional payment for the same five reasons, providing similar statements of fact and argument for each, primarily expanding its argument for its first ground (app. supp. R4, tab 98). HHL also submitted a "Sworn Statement in reference to (REA)" (app. supp. R4, tab 97). The swor[n] statement was executed by Dr. Amarkhil, the deputy managing director ofHHL. In that statement Dr. Amarkhil provides a signed "affidavit" that the following statement is true: "The clauses and points reflected in REA (Request for Equitable Adjustment) in reference to contract# W5J9JE-11-C-0115, to the best of my knowledge are true." (Id., emphasis in original)

In May 2015, HHL contacted the original contracting officer, Daniel Portillo, by email because it had not received a response to its REA ( compl. ,r 84 ). Mr. Portillo responded by email telling HHL "We should be providing you the Contracting Officer's final decision by the end of this week" (app. supp. R4, tab 101). Mr. Portillo immediately followed that message with an email that contained a PDF document titled "Response to REA" (app. supp. R4, tab 100). Whatever Mr. Portillo's response, HHL understood it to be an unsigned answer to its 16 April 2014 email, not a response to its "formal" REA submitted 5 March 2015 (compl. ,r 86; R4, tab 66). Mr. Portillo's response rejected HHL's invoices, but did not contain any indication that it should be considered a contracting officer's final decision (R4, tab 66). In either event, HHL again clarified that neither its January or its March email were intended to be a claim (app. supp. R4, tab 107) ("I would like to know if there is any time frame during which we could accept the final decision or submit our claim."). Mr. Portillo informed HHL that it "may have a claim on the things discussed in our decision" (app. supp. R4, tab 108).

HHL continued to contact the Corps regarding its REA, sometimes through unusual sources (compl. ,r,r 95-99 (e.g. HHL sent messages to Corps headquarters via Facebook.)). In February 2016, Ms. Cherita Williams assumed responsibility for HHL's contract (compl. ,r 100). HHL pursued a decision from Ms. Williams. In her decision on 26 March 2017, she found no merit in the REA and advised HHL to follow the procedure in the contract's disputes clause (R4, tab 2 at 6). The government did not issue a contracting officer's final decision in accordance with the CDA on the REA. HHL responded to Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Hejran Hejrat Co. LTD, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hejran-hejrat-co-ltd-asbca-2018.