Heine Safety-boiler Co. v. Francis Bros. & Jellett

105 F. 413, 1900 U.S. App. LEXIS 4752
CourtU.S. Circuit Court for the District of Eastern Pennsylvania
DecidedDecember 21, 1900
DocketNos. 1 and 44
StatusPublished

This text of 105 F. 413 (Heine Safety-boiler Co. v. Francis Bros. & Jellett) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heine Safety-boiler Co. v. Francis Bros. & Jellett, 105 F. 413, 1900 U.S. App. LEXIS 4752 (circtedpa 1900).

Opinion

DALLAS, Circuit Judge.

The first stated action was brought to recover the contract price of two boilers; tbe other for tbe recovery of damages for the alleged nonconformity of those boilers with tbe requirements of the contract under which they were furnished. The two cases were tried together, and in each there was a verdict for the Heine Safety-Boiler Company. Francis Bros. & Jellett have filed separate motions for new trial, but, as the controlling question is the same in both cases, these motions may be disposed of in a single opinion.

Francis Bros. & Jellett had contracted to do certain of the work required in the reconstruction of the Rittenhouse Building, on Arch street, Philadelphia. Their contract provided that they should furnish two water-tube boilers. They accordingly invited bids from several boiler makers, including the Heine Company, to whom they wrote as follows:

“Philadelphia, April 1st, 1899.
“Heine Safety-Boiler Works, Bourse Building, Philadelphia — -Gentlemen: Please name us your best figures for furnishing and erecting, together with connections to stack, the boilers called for in the Rittenhouse Building, N. W. Cor. 7th & Arch St. Your bid, to receive our consideration, must reach us not later than April 11th. Plans and specifications can be seen at onr drawing room, N. W. Cor. Marshall & Willow Sts.
“Yours, very truly, Francis Bros. & Jellett, Incorporated,
“S. A. Jellett, Mgr.”

The plans and specifications referred to in this letter were those which accompanied the contract between Francis Bros. & Jellett and tbe owner of the property. They were seen by the Heine Company, but they, instead of simply bidding thereon, addressed a letter to Francis Bros. & Jellett, dated April 10, 1899, in which they said:

[414]*414“We inclose you herewith detail specifications and proposition covering the two.Heine safety boilers to be erected in the Rittenhouse Building, 7th & Arch Streets, Philadelphia. * * *”

After the receipt by them of this letter and the inclosure it mentioned, Francis Bros. & Jellett sent a contract, executed by themselves, to the Heine Safety-Boiler ’Company, for execution by them. To- this contract specifications were annexed, which were the same as those of the contract between the owner of the property and Francis Bros. & Jellett; and the first two paragraphs of the contract itself were as follows:

“This agreement, entered into this first day of May, A. D. eighteen hundred and ninety-nine, by and between the Heine Boiler Company, of St. Louis, Missouri, party o-f the first part, and Francis Brothers & Jellett, Incorporated, a corporation of the state of Pennsylvania, party of the second part, witnesseth: That for and in consideration of the payments and covenants herein mentioned to be made and performed by the said party of the second part the said party of the first part doth hereby agree and covenant to furnish all materials and apparatus for, and to build, construct, and finish, complete, ready for use, two (2) water-tube boilers, with their setting, damper regulator, etc., called for in specifications prepared by Francis Brothers & Jellett, Incorporated, consulting engineers, dated March 15th, 1899, to. be erected in the Rittenhouse Building, 707 & 709 Arch St., Philadelphia. The whole of- said work is to be erected, constructed, and finished in conformity with the plans and specifications above referred to; both plans and specifications being understood as forming part of this agreement. All work called for by these plans add specifications is to be erected under the direction and supervision of Mr. Oliver Earnshaw, engineer for Mr. Henry O. Lea, owner of the building;”

After the word “agreement,” immediately preceding the last sentence contained-in the above extract, the Heine Company inserted an asterisk, and at the foot of the contract they placed another, and there added these words: “Except the changes in details of construction covered by our proposition and specifications dated 4/10/99, and attached hereto.” They then attached the “specifications and proposition” which had been inclosed with their letter of April 10, 1899, signed the contract as thus altered, and' returned it to Francis Bros. & Jellett, who thereupon, under date of May 9, 1899, wrote to- the Heine Company, saying:

“We are in receipt of contract for boilers, Rittenhouse Building, and note that you have made certain additions. * * * The second one, just above the signature, we would like to know what you mean, — ‘Except the changes in detail and construction covered by our proposition and specifications dated 4/10/99, attached hereto.’ Please specify what these changes ‘in- detail and construction’ are, so that we may know what you mean by this section. Let us have this at once, and oblige. You will recollect that our signature was attached to this contract before these changes were made, and they are not binding on us unless we are satisfied after getting this detail from you.”

To this letter the Heine Company replied as follows:

“5/10/99.
“Messrs. Francis Bros. & Jellett, 704 Arch Street, Philadelphia, Pa. — Dear Sirs: Answering your favor of the 9th, in which you ask what we mean by ‘except the changes in details and construction covered by our proposition and specifications dated 4/10/99, attached hereto,’ would say that we refer simply to the minor details in which the construction of the Heine boiler differs from your- general specifications, and these details are set forth in our specification sheet dated 4/10/99. For instance, especially in regard to [415]*415the testing and inspecting of the metal, the punching and reaming of the rivet and tube boles, and the caulking of the seams; also the guaranties which we make, and the amount of work which we include in our bid. . This proposition of ours of the 4/10, with the modified price, is what you accepted, and naturally it should bear a prominent part in the total contract. Trusting this is satisfactory to you, we remain,
“Very truly yours, Heine Safety-Boiler Co.”

To this letter Francis Bros. & Jellett made no reply, and under this state of Uie contractual relations between the parties, the Heine Company did put two boilers into the Itittenhouse Building.

I instructed the jury that a certain part of the specifications which Francis Bros. & Jellett had annexed to the contract was wholly superseded by the specifications which the Heine Company after-wards attached thereto. The part of the Francis Bros. & Jellett specification which, with the related provision respecting “tests,” was held to have been superseded, is as follows:

“Boilers. There will bo two (2) new boilers erected in boiler room of new building, set singly as shown; each boiler having a capacity of one hundred and forty (140) nominal horse power, and must be capable of evaporating forty-two hundred (4,200) pounds of water from and at 212 degrees Fahrenheit per hour, with ordinary firing.”

The part of the Heine Company specification which was held to have superseded the foregoing is as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Canal Co. v. Hill
82 U.S. 94 (Supreme Court, 1872)
Reed v. Insurance Co.
95 U.S. 23 (Supreme Court, 1877)
Heryford v. Davis
102 U.S. 235 (Supreme Court, 1880)
Rainey v. Hogsett
100 F. 207 (Third Circuit, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
105 F. 413, 1900 U.S. App. LEXIS 4752, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heine-safety-boiler-co-v-francis-bros-jellett-circtedpa-1900.