Heidelberg Materials NE v. Blue Rock Construction

CourtSuperior Court of Pennsylvania
DecidedApril 14, 2025
Docket875 EDA 2024
StatusUnpublished

This text of Heidelberg Materials NE v. Blue Rock Construction (Heidelberg Materials NE v. Blue Rock Construction) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heidelberg Materials NE v. Blue Rock Construction, (Pa. Ct. App. 2025).

Opinion

J-A25020-24

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

HEIDELBERG MATERIALS : IN THE SUPERIOR COURT OF NORTHEAST, LLC F/K/A HANSON : PENNSYLVANIA AGGREGATES PENNSYLVANIA, LLC : : : v. : : : BLUE ROCK CONSTRUCTION, INC. : No. 875 EDA 2024 : Appellant :

Appeal from the Order Entered February 19, 2024 In the Court of Common Pleas of Northampton County Civil Division at No(s): C-48-CV-2021-09261

BEFORE: OLSON, J., DUBOW, J., and SULLIVAN, J.

MEMORANDUM BY DUBOW, J.: FILED APRIL 14, 2025

Appellant, Blue Rock Construction, Inc. appeals the February 19, 2024

order entered in the Northampton County Court of Common Pleas, granting

summary judgment to Appellee, Heidelberg Materials Northeast, LLC, f/k/a

Hanson Aggregates Pennsylvania, LLC, in this case brought under the

Mechanics’ Lien Law of 1963.1 After careful consideration, we affirm.

The relevant factual and procedural history is as follows. Centerpoint

Willowbrook, LLC (“Owner”) engaged Appellant as the general contractor for

a construction project on Owner’s real property (the “Project”). Appellant then

contracted with Dobrinski Brothers, Inc., which, in turn, subcontracted with

____________________________________________

1 49 P.S. §§ 1101-1902. J-A25020-24

Appellee for labor and materials related to the construction of parking lots and

entrance ways on the Project.

On December 8, 2021, Appellee filed a mechanics’ lien claim against

Owner’s property to secure payment of $395,829.89 owed for materials and

labor provided by Appellee on the Project. Relevantly, Appellee averred that

it last furnished labor and materials for the Project on July 8, 2021, which

would render the lien claim timely under the Mechanics’ Lien Law. 2

In January 2022, Appellant and Appellee filed a Joint Stipulation to

permit Appellant to intervene and to discharge the lien claim against Owner’s

property. Importantly, Appellant waived its defenses in the following

stipulation:

[Appellant] stipulates that the amount of the liens accurately represent work performed or materials furnished by [Appellee], the mechanics[’] lien is valid, and [sic] waives any defenses.

Joint Stipulation, 1/18/22, at ¶ 8. On January 18, 2022, the court adopted

the stipulation. On March 23, 2022, Appellee filed a complaint to enforce the

mechanics’ lien.

On June 15, 2022, new counsel for Appellant served on Appellee

requests for admission seeking to determine whether the lien claim was

untimely. Specifically, Appellant contended that the July 8, 2021 invoice relied

upon by Appellee to establish the timeliness of the lien did not involve

Appellee’s work on the Project but was merely an accounting adjustment. ____________________________________________

2See 49 P.S. § 1502(a)(1) (requiring the filing of a lien claim within six months after completion of work).

-2- J-A25020-24

Appellee responded by invoking the Joint Stipulation in which Appellant agreed

that the lien was valid and waived any defenses. Appellant then filed a Motion

to Determine the Sufficiency of Plaintiff’s Answers to Requests for Admissions.

On September 19, 2022, with its discovery motion pending, Appellant

answered Appellee’s complaint and asserted affirmative defenses as new

matter. Appellee filed preliminary objections in the nature of a demurrer to

the new matter based again on the Joint Stipulation.

On October 17, 2022, the court partially granted Appellant’s Motion to

Determine the Sufficiency of [Appellee’s] Answers to Requests for Admission

but subsequently granted reconsideration. On June 5, 2023, the trial court

denied the previously granted portions of Appellant’s discovery motion and

sustained Appellee’s preliminary objections, dismissing with prejudice

Appellant’s affirmative defenses. In support of both holdings, the court relied

on Appellant’s waiver of defenses in the Joint Stipulation, which it recognized

was “the law of the case.” Order, 6/5/23, at 5 n.5.

On July 21, 2023, Appellee filed a motion for summary judgment, which

the court granted on February 19, 2024.3 Relying on the June 5, 2023 order

finding that Appellant waived its defenses, the court opined that permitting

Appellant’s challenges would “undermine the parties’ Joint Stipulation, which

would also undermine the very agreement that permitted [Appellant’s]

3 President Judge Craig A. Dally issued the October 2022 and the June 2023

orders, while Judge Jennifer T. Sletvold issued the February 2024 order granting summary judgment.

-3- J-A25020-24

intervention in the first instance.” Order, 2/19/24, at 6 (unpaginated). The

court also rejected Appellant’s argument that its issues implicated non-

waivable subject matter jurisdiction.

On March 15, 2024, Appellant filed a notice of appeal, and the trial court

and Appellant subsequently complied with Pa.R.A.P. 1925.

Appellant raises the following issues on appeal:

1. A trial court abuses its discretion when it exercises judgment that is manifestly unreasonable. The court denied [Appellant] the opportunity to take discovery relevant to the validity of the Joint Stipulation, the timeliness of a mechanics’ lien claim, and the subject matter jurisdiction of the court. Did the court abuse its discretion in so doing?

2. It is a violation of a party’s right to procedural due process for a court not to afford a party with a full opportunity to present evidence. The court denied [Appellant] any opportunity to challenge i) the validity of [Appellee’s] mechanics’ lien claim and of an agreement in which [Appellant] purported to waive all defenses thereto; and ii) the subject matter jurisdiction of the court. Did the court violate [Appellant’s] procedural due process rights?

3. Any issue going to the subject matter jurisdiction of the trial [court] cannot be waived by the parties by agreement or stipulation. In granting [Appellee’s] motion for summary judgment, the court found that [Appellant] did not have the ability to challenge the subject matter jurisdiction of the court because [Appellant] waived all defenses to the underlying mechanics’ lien claim. Did the court err in finding that [Appellant] could not challenge the subject matter jurisdiction of the court?

4. A mechanics’ lien claim is fatally and incurably defective if it is untimely filed. There is a genuine issue of material fact concerning when [Appellee] last furnished labor or materials and, thus, whether its Lien Claim was void ab initio and unenforceable. Did the court err in granting [Appellee’s] motion for summary judgment under these circumstances?

Appellant’s Br. at 5.

-4- J-A25020-24

This case involves a mechanics’ lien claim, which is a statutory remedy,

unknown at common law, that permits a contractor or subcontractor to obtain

a priority lien on property for labor and materials that the claimant invested

in that property. See Terra Firma Builders, LLC v. King, 249 A.3d 976,

983 (Pa. 2021); see also El-Gharbaoui v. Ajayi, 260 A.3d 944, 961 (Pa.

Super. 2021). As mechanics’ liens are “extraordinary remedies[,]” “a

contractor seeking the benefit of the lien must judiciously adhere to the

requirements of the Mechanics’ Lien Law in order to secure a valid and

enforceable lien.” Terra Firma Builders, LLC, 249 A.3d at 983 (citation and

internal quotation marks omitted).

Appellant’s first two issues challenge the portion of the June 5, 2023

order denying Appellant’s discovery request. Appellate courts generally

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Summers v. CERTAINTEED CORP.
997 A.2d 1152 (Supreme Court of Pennsylvania, 2010)
In Re Administrative Order No. 1-Md-2003
936 A.2d 1 (Supreme Court of Pennsylvania, 2007)
Day v. Civil Service Commission
931 A.2d 646 (Supreme Court of Pennsylvania, 2007)
Tyler v. King
496 A.2d 16 (Supreme Court of Pennsylvania, 1985)
Tindall v. Friedman
970 A.2d 1159 (Superior Court of Pennsylvania, 2009)
Mellish v. Hurlock Neck Duck Club, Inc.
886 A.2d 1151 (Commonwealth Court of Pennsylvania, 2005)
McNeil v. Jordan
894 A.2d 1260 (Supreme Court of Pennsylvania, 2006)
Osial v. Cook
803 A.2d 209 (Superior Court of Pennsylvania, 2002)
In Re: Est. of: Schumacher, R., Sr.
133 A.3d 45 (Superior Court of Pennsylvania, 2016)
Carlino East Brandywine v. Brandywine Village
2021 Pa. Super. 147 (Superior Court of Pennsylvania, 2021)
El-Gharbaoui, A. v. Ajayi, A.
2021 Pa. Super. 146 (Superior Court of Pennsylvania, 2021)
Smithson, R. v. Columbia Gas
2021 Pa. Super. 157 (Superior Court of Pennsylvania, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Heidelberg Materials NE v. Blue Rock Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heidelberg-materials-ne-v-blue-rock-construction-pasuperct-2025.