Heat Exchangers, Inc. v. Map Construction Corp.

368 A.2d 1088, 34 Md. App. 679, 21 U.C.C. Rep. Serv. (West) 123, 1977 Md. App. LEXIS 553
CourtCourt of Special Appeals of Maryland
DecidedFebruary 7, 1977
Docket519, September Term, 1976
StatusPublished
Cited by4 cases

This text of 368 A.2d 1088 (Heat Exchangers, Inc. v. Map Construction Corp.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heat Exchangers, Inc. v. Map Construction Corp., 368 A.2d 1088, 34 Md. App. 679, 21 U.C.C. Rep. Serv. (West) 123, 1977 Md. App. LEXIS 553 (Md. Ct. App. 1977).

Opinion

Menchine, J.,

delivered the opinion of the Court.

Map Construction Corporation (Map) brought suit against Heat Exchangers, Inc. (Heat) and another 1 in the Circuit Court for Montgomery County for alleged breach of contract. Heat filed a counterclaim against Map alleging breach of contract. 2

The original action and the counterclaim were tried together in a bench trial with judgment nisi and absolute entered in favor of Map against Heat for $31,640.48 in the original suit and judgment nisi and absolute entered in favor of Map for costs against Heat in the counterclaim.

The appeal by Heat raises in this Court the single following issue:

“Did the lower court err by failing to determine whether the failure of Heat Exchangers, Inc. to timely deliver was excused by ‘commercial impracticality’?”

Heat’s contention on appeal rests upon the provisions of the Annotated Code of Maryland CL § 2-615 that reads as follows:

“§ 2-615. Excuse by failure of presupposed conditions.
Except so far as a seller may have assumed a greater *681 obligation and subject to the preceding section on substituted performance:
(a) Delay in delivery or nondelivery in whole or in part by a seller who complies with paragraphs (b) and (c) is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
(b) Where the causes mentioned in paragraph (a) affect only a part of the seller’s capacity to perform, he must allocate production and deliveries among his customers but may at his option include regular customers not then under contract as well as his own requirements for further manufacture. He may so allocate in any manner which is fair and reasonable.
(c) The seller must notify the buyer seasonably that there will be delay or nondelivery and, when allocation is required under paragraph (b), of the estimated quota thus made available for the buyer.”

Map argues alternatively:

1. That the issue suggested on this appeal was not raised or decided below and is not before us under Rule 1085; and

2. That the evidence failed to establish excuse by failure of presupposed conditions under § 2-615.

Maryland Rule 1085

The record contains testimony indicating that appellant relied in part on the provisions of § 2-615, supra. Although the trial judge made no specific reference to that section in his oral opinion, he did make reference generally to the Uniform Commercial Code and we think his decision implies that he found that § 2-615 furnished no justification for Heat’s failure to perform. Under these circumstances, Maryland Rule 1085 is not applicable. Panamerican Co. v. Broun, 238 Md. 438, 447, 209 A. 2d 575, 579-80 (1965); Kent v. *682 Mer. Safe Dep. & Tr. Co., 225 Md. 590, 593, 171 A. 2d 723, 725 (1961).

The Impact of § 2-615

This section of the Uniform Commercial Code has not been the subject of appellate interpretation in Maryland. The Official Comment upon the section begins as follows:

“Prior uniform statutory provision: None.
Purposes:
1. This section excuses a seller from timely delivery of goods contracted for, where his performance has become commercially impracticable because of unforeseen supervening circumstances not within the contemplation of the parties at the time of contracting.”

Certain facts are not in dispute and fairly may be summarized as follows:

In November, 1973, contract discussions took place between Airpac Systems, Inc. (Airpac), manufacturer’s representative for Heat, and Map. On April 4, 1974, after bids had been received by Map from Heat and another company, Map signed a purchase order for 398 custom designed air conditioning units and essential plumbing connections (hereinafter described as risers), to be assembled and installed by Pleat in a multi-story apartment building to be constructed by Map. The bid price of Heat was $199,500.00. In the latter part of April, 1974, Heat submitted drawings and specifications for the units and risers.

On May 7,1974, The Whalen Company (Whalen), that had been the unsuccessful second bidder, advised Map that the proposed drawings and specifications furnished by Heat indicated a possible infringement of a patent owned by Whalen. Heat thereafter gave Map a letter of indemnification against a suit for patent infringement. Nonetheless, Heat with the concurrence of Map, decided to change the original design of the units so that the risers connecting the units from floor to floor would be placed outside of rather than within the unit cabinets.

*683 On June 4, 1974» Heat undertook to assemble and install the units as redesigned. Map received and accepted Heat’s undertaking on June 10, 1974. The acceptance document, prepared by Heat, bore the notation “Thank you for your order we will ship on or about Aug. 25, 1974.” On July 1, 1974, Map requested that risers and equipment for the first five floors be released for shipment as soon as possible with “the balance of the equipment for the anticipated delivery date of 25 August 1974.” No shipments were made.

On August 22,1974, Airpac wrote Map advising that Heat was requesting a price increase of $10,154.00. On June 18, 1974, Heat had informed Airpac (its representative) that such a price increase would be necessary. This suggested increase was not disclosed to Map, however, until August, apparently because of fear that the contract might be cancelled by Map.

On August 30,1974, Map by telephone agreed to the price increase but requested early delivery of the shipment. On September 3, 1974» Map formally approved and returned to Heat a document showing agreement by the parties to the price change. Heat had endorsed on that document a notation declaring that “riser section assemblies will precede equipment shipments and should leave the factory within the next week to ten days.” No shipments were made by Heat.

On September 6, 1974, Map sent a letter to Heat stating, inter alia, that “It is imperative that we get the first five floors of equipment by the end of this month.” Heat did not demur.

On September 10, 1974, Map, by telephone, repeated to Heat that delivery must occur before the end of September. On September 27th, Heat informed Map that the risers would be shipped “next week for sure.” No shipment was made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ecology Services, Inc. v. Granturk Equipment, Inc.
443 F. Supp. 2d 756 (D. Maryland, 2006)
Rockland Industries, Inc. v. E+ E (US) INC.
991 F. Supp. 468 (D. Maryland, 1998)
Offen v. County Council for Prince George's County
625 A.2d 424 (Court of Special Appeals of Maryland, 1993)
Montgomery County v. Maryland Soft Drink Ass'n
377 A.2d 486 (Court of Appeals of Maryland, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
368 A.2d 1088, 34 Md. App. 679, 21 U.C.C. Rep. Serv. (West) 123, 1977 Md. App. LEXIS 553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heat-exchangers-inc-v-map-construction-corp-mdctspecapp-1977.