Healy Tibbitts Builders, Inc. v. Director, Office of Workers' Compensation Programs

444 F.3d 1095, 2006 WL 962530
CourtCourt of Appeals for the Ninth Circuit
DecidedApril 13, 2006
Docket04-70575
StatusPublished
Cited by1 cases

This text of 444 F.3d 1095 (Healy Tibbitts Builders, Inc. v. Director, Office of Workers' Compensation Programs) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Healy Tibbitts Builders, Inc. v. Director, Office of Workers' Compensation Programs, 444 F.3d 1095, 2006 WL 962530 (9th Cir. 2006).

Opinion

SILVERMAN, Circuit Judge.

The Longshore and Harbor Workers’ Compensation Act does not cover “all those who breathe salt air,” but neither is it limited to Popeye. The decedent in this case was killed near the water’s edge while excavating a utility line trench, a job that was part of a project to renovate three submarine berths at Pearl Harbor. We hold today that the Benefits Review Board reasonably concluded that the decedent was a “harbor worker” covered by the Act even though his specific job was not uniquely maritime in nature.

I. Background

Berthing wharves are large, concrete decks that extend from shore over navigable waters, and are used to accommodate submarines and other vessels while they are in port. Healy Tibbitts Builders, Inc. entered into a contract with the United States Navy to replace each 28-foot-long deck with a 50-foot-long deck, as measured from the land to the water’s edge where the submarines dock. The contract required rerouting utility lines that provided power and communication capabilities to the old berths by digging trenches and installing a new underground concrete *1097 duct bank, along with several new manholes. This “main duct bank,” which encases conduit through which the electrical and communication cables run, runs parallel to the shoreline at a variable distance of 40 to 75 feet from the water’s edge.

The contract contemplated that the new utility lines would run from nearby electrical substations on the naval base (outside the construction area), through the main duct bank and to shore power mounds on the berths. Shore power mounds are large box-shaped receptacles that ships can plug into while in port. To accomplish this, the contract also required installation of “secondary feeders,” which are additional duct banks that run off the main duct bank to the shore power mounds.

Healy Tibbitts subcontracted with John Mannering to build the main duct bank. According to the contract’s terms, Mannering was to: (i) demolish existing duct banks and manholes; (ii) excavate for installation of new electrical and communication duct banks and manholes; (iii) install concrete for duct banks after ducts and rebar are installed by others; and (iv) restore surfaces by backfilling and compacting over duct banks and manholes.

Decedent Finefeuiaki Maumau was hired by Mannering and began work on the project sometime in May 2001. On the day in question, fifteen weeks into the project, his job was to dig a trench. Maumau died when a steel trench shield that supported the sidewalls of the excavated trench fell on him. Mannering completed its work on the project four weeks later.

Darlette Maumau, decedent’s surviving spouse, and Shelly Dagget, the mother of his two children, sought benefits under the Longshore and Harbor Workers’ Compensation Act. The District Director of the Department of Labor’s Office of Workers’ Compensation Programs (“OWCP”) referred this case to an Administrative Law Judge, who conducted an evidentiary hearing on May 23, 2002. In his decision, the ALJ relied on past decisions in which the Benefits Review Board had interpreted the Act to cover construction workers involved in the construction of a dock used to house a submarine repair facility and other maritime facilities. The ALJ concluded that it was irrelevant that Maumau’s specific job duties did not involve the loading and unloading of ships or were not “inherently maritime” in nature.

The ALJ awarded $1,166.78 per week in benefits. The ALJ considered the fact that Maumau earned $17,501.76 on the submarine berths project, and would have earned an additional $4,667.14 had he been there the last four weeks of the job. The ALJ computed Maumau’s average weekly wage by dividing $22,168.90 (the total he could have earned on the project) by 19 weeks, the duration of Mannering’s work on the project.

The Benefits Review Board affirmed. In ruling that Maumau was a “harbor worker” covered by the Act, the Board held that the relevant inquiry was whether the project on which he was working was connected to the servicing of ships, as opposed to whether his specific job duties were of a uniquely maritime nature. The Board also concluded that Maumau “in all likelihood would have continued to work ... at the same wage as he was earning at the time of his injury.” Healy Tibbitts and Mannering petitioned for review.

II. Analysis

To qualify for benefits, an individual must be an “employee” as that term is defined in the Act. 1 The Act defines “em *1098 ployee” as “any person engaged in maritime employment, including any longshoreman or other person engaged in longshoring operations, and any harbor-worker including a ship repairman, shipbuilder, and ship-breaker.” 33 U.S.C. § 902(3).

The claimants do not assert that Maumau was a longshoreman, that he was engaged in longshoring operations, or that he was a ship repairman, shipbuilder or shipbreaker. Instead, the controversy in this case centers on the terms “maritime employment” and “harbor worker,” both of which the Act leaves undefined.

A. The Director’s interpretation of “harbor worker” is reasonable and consistent with the Act’s remedial purpose.

The Director of the OWCP urges an interpretation of “harbor worker” that would extend coverage to any worker, like Maumau, directly engaged in the construction of a maritime facility, even if the worker’s specific job duties are not maritime in nature. We accord “considerable weight” to the Director’s interpretation of the Act, even when its interpretation is advanced in litigation. See Mallott & Peterson v. Dir., OWCP, 98 F.3d 1170, 1172 (9th Cir.1996) (“This deference extends not only to regulations articulating the Director’s interpretation, but also to litigating positions asserted by the Director in the course of administrative adjudications .... ”). If the Act is “easily susceptible” to the Director’s interpretation, we “need go no further.” Id. (internal quotations omitted). The Act, as remedial legislation, “should be liberally construed.” Ramos v. Universal Dredging Corp., 653 F.2d 1353, 1358-59 (9th Cir.1981) (courts should “ ‘take an expansive view’ ” of the Act’s coverage (quoting Ne. Marine Terminal Co. v. Caputo, 432 U.S. 249, 268, 97 S.Ct. 2348, 53 L.Ed.2d 320 (1977))).

We adopt the Director’s interpretation of “harbor worker” because it is reasonable and consistent with the remedial purpose behind the Act. Significantly, it already has been held that the Act covers those who repair the equipment with which ships are loaded and unloaded. See Chesapeake & Ohio Ry. Co. v. Schwalb, 493 U.S. 40, 47, 110 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
444 F.3d 1095, 2006 WL 962530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/healy-tibbitts-builders-inc-v-director-office-of-workers-compensation-ca9-2006.