Healy Long & Jevin, Inc. v. CQSA Construction, LLC d/b/a Post General Contracting, LLC and BKV Group DC

CourtDistrict Court, E.D. Pennsylvania
DecidedNovember 18, 2025
Docket2:25-cv-03156
StatusUnknown

This text of Healy Long & Jevin, Inc. v. CQSA Construction, LLC d/b/a Post General Contracting, LLC and BKV Group DC (Healy Long & Jevin, Inc. v. CQSA Construction, LLC d/b/a Post General Contracting, LLC and BKV Group DC) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Healy Long & Jevin, Inc. v. CQSA Construction, LLC d/b/a Post General Contracting, LLC and BKV Group DC, (E.D. Pa. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA HEALY LONG & JEVIN, INC., CIVIL ACTION Plaintiff, NO. 25-3156

v.

CQSA CONSTRUCTION, LLC d/b/a POST GENERAL CONTRACTING, LLC. and BKV GROUP DC, Defendants. Baylson, J. November 18, 2025 MEMORANDUM RE: MOTION TO DISMISS Plaintiff Healy Long & Jevin, Inc. (“Healy”), a construction company, brings claims for breach of contract, unjust enrichment, negligent misrepresentation, and violation of the Pennsylvania Contractor and Subcontractor Payment Act (“CASPA”) against Defendants CQSA Construction, LLC (“CQSA”), doing business as Post General Contracting, LLC (“Post”), and BKV Group DC following work on a construction project. For the reasons below, CQSA’s Motion to Dismiss is DENIED. I. FACTUAL ALLEGATIONS1 On November 19, 2021, Healy and Post2 entered a written contract to perform construction work (hereinafter “Contract”) for a project located at 1001-29 South Broad Street and 1301 Washington Avenue, Philadelphia, Pennsylvania (the “Project”). Compl. ¶ 6, ECF 1. Post was the Project’s general contractor. Id.

1 For purposes of this Motion, the Court accepts as true all factual allegations in the Complaint. Doe v. Univ. of Scis., 961 F.3d 203, 208 (3d Cir. 2020). 2 Healy alleges that Post entered the Contract and later assigned its rights, title, and interest in the Project to CQSA after the completion of Healy’s work. Compl. ¶ 11, ECF 1. Throughout the Project, Post represented to Healy that the Project should follow the Project Schedule. Id. ¶ 8. However, Healy experienced significant delays caused by Post and its agents, id. ¶¶ 13–14, which disrupted the Project, extended Healy’s performance period, and reduced efficiency—resulting in damages of $13,948,769.30. Id. ¶¶ 16–17. Moreover, despite Healy’s

performance, Post has refused to pay Healy the Contract’s outstanding balance. Id. ¶ 12. II. PROCEDURAL HISTORY On June 20, 2025, Healy filed a Complaint asserting claims for breach of contract, unjust enrichment, and violation of the CASPA against CQSA, and a claim for negligent misrepresentation against BKV. Compl., ECF 1. On July 11, 2025, CQSA filed a motion to dismiss (the “Motion”) under Fed. R. Civ. P. 12(b)(6) arguing that Healy failed to satisfy the Contract’s condition precedent requiring mediation before initiating the lawsuit. ECF 4. On July 25, 2025, Healy filed a response in opposition to CQSA’s Motion. ECF 7. On August 1, 2025, CQSA filed a reply in further support of its motion. ECF 10. III. STANDARD OF REVIEW

To survive a motion to dismiss under Federal Rule 12(b)(6), a plaintiff must include sufficient facts in the complaint that, accepted as true, “state a claim to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007). A complaint is insufficient if it suggests only the “mere possibility of misconduct” or is a “[t]hreadbare recital[ ] of the elements of a cause of action, supported by mere conclusory statements,” Ashcroft v. Iqbal, 556 U.S. 662, 678–79 (2009) (citing Twombly, 550 U.S. at 555), and so it will not suffice if it is “devoid of further factual enhancement,” id. at 678 (citation omitted). Thus, in considering a motion to dismiss, the Court accepts all factual allegations as true and views them in a light most favorable to the plaintiff, Doe v. Univ. of Scis., 961 F.3d 203, 208 (3d Cir. 2020), but may not “assume that [the plaintiff] can prove facts that it has not alleged[,]” Twombly, 550 U.S. at 563 n.8 (quoting Associated Gen. Contractors of Cal., Inc. v. Carpenters, 459 U.S. 519, 526 (1983)). IV. DISCUSSION A. Parties’ Contentions Neither party disputes the Contract’s validity. Rather, CQSA asserts that “Healy failed to

satisfy the condition precedent requiring mediation before initiating the lawsuit,” and thus dismissal is appropriate. ECF 4 at 1. However, Healy argues that dismissal is not required because Healy did comply with the Contract and underwent mediation, which reached an impasse before this case was filed. ECF 7-1 at 4–6. Healy asserts that on February 20, 2025, it submitted a formal demand for mediation with all required submissions. ECF 7-1 at 4–5. On March 10, 2025, a mediator was appointed, and the mediator was accepted by both parties. Id. at 5. On April 8, 2025, Healy submitted a Statement of Claim and CQSA denied liability. Id. On June 17, 2025, after communications between the parties and mediator, the mediator formally advised all parties that mediation was no longer viable because the parties had reached an impasse. Id. After the mediator’s declaration, Healy initiated

litigation. Id. On the other hand, CQSA argues that a mediation was scheduled for July 8, 2025, and that the parties had no substantive settlement discussions, did not exchange proposals, that Healy did not make a good faith effort to engage in the process, and that the mediation never occurred. ECF 10 at 1. CQSA states that it followed the mediation schedule including by responding to the statement of claim and serving document requests, but that Healy failed to meet the discovery deadline and did not serve any discovery requests. Id. at 4. CQSA asserts that Healy had an ex parte discussion with the mediator, after which the mediator improperly declared an impasse. Id. at 2. B. Mediation Is Not a Condition Precedent to Filing Suit The Contract attached as Exhibit A to the Complaint states, The parties shall endeavor to resolve their Claims by mediation . . . . A request for mediation shall be made in writing, delivered to the other party to the Contract, and filed with the person of entity administering the mediation. The request may be made concurrently with the filing of binding dispute resolution proceedings but, in such event, mediation shall proceed in advance of binding dispute resolution proceedings, which shall be stayed pending mediation for a period of 60 days from the date of filing . . . . Compl. Ex. A § 15.3.2, ECF 1-3. The plain language of the Contract indicates the clear intention of the parties that a request for mediation be made, but that the request may be made concurrently with the filing of a lawsuit, and that if that happens, mediation shall proceed in advance of the lawsuit’s proceeds, which shall be stayed for 60 days. Id. .3 This language contrasts with other cases where courts have dismissed cases after finding that mediation was a condition precedent to litigation based on contractual language. See, e.g., McDonough v. Algorithm, Inc., 2024 WL 3691610, at *1 (W.D. Pa. Aug. 7, 2024) (finding mediation clause was condition precedent where it stated that party could proceed with litigation “only if a reasonable attempt at mediation is unsuccessful”); Brackenridge Constr. Co., Inc. v. Home Depot USA, Inc., 2009 WL 10690027, at *3 (W.D. Pa. July 22, 2009) (same). By contrast, the Contract’s language states that a “request may be made concurrently with the filing of court proceedings” and does not indicate that litigation can proceed only if the mediation is unsuccessful. Compl. Ex. A § 15.3.2, ECF 1-3 (emphasis

3 This language contrasts with other cases where courts have dismissed cases after finding that mediation was a condition precedent to litigation based on contractual language. See, e.g., McDonough v. Algorithm, Inc., 2024 WL 3691610, at *1 (W.D. Pa. Aug.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green Tree Financial Corp. v. Bazzle
539 U.S. 444 (Supreme Court, 2003)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Puleo v. Chase Bank USA, N.A.
605 F.3d 172 (Third Circuit, 2010)
Nino v. JEWELRY EXCHANGE, INC.
609 F.3d 191 (Third Circuit, 2010)
Jose Vilches v. The Travelers Companies, Inc
413 F. App'x 487 (Third Circuit, 2011)
Margaret Palcko v. Airborne Express, Inc.
372 F.3d 588 (Third Circuit, 2004)
Kaneff v. Delaware Title Loans, Inc.
587 F.3d 616 (Third Circuit, 2009)
Rudolph v. Alamo Rent a Car, Inc.
952 F. Supp. 311 (E.D. Virginia, 1997)
Sheldone v. Pennsylvania Turnpike Commission
104 F. Supp. 2d 511 (W.D. Pennsylvania, 2000)
John Doe v. University of the Sciences
961 F.3d 203 (Third Circuit, 2020)
Bruni v. City of Pittsburgh
824 F.3d 353 (Third Circuit, 2016)
Somerset Consulting, LLC v. United Capital Lenders, LLC
832 F. Supp. 2d 474 (E.D. Pennsylvania, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Healy Long & Jevin, Inc. v. CQSA Construction, LLC d/b/a Post General Contracting, LLC and BKV Group DC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/healy-long-jevin-inc-v-cqsa-construction-llc-dba-post-general-paed-2025.