Hcic Enterprises, LLC v. United States

United States Court of Federal Claims·Decided July 9, 2020·No. 18-1943·Published

Opinion

In the United States Court of Federal Claims No. 18-1943C (Filed: July 9, 2020)

)

HCIC ENTERPRISES, LLC, ) d/b/a HCI GENERAL CONTRACTORS, )

) Keywords: Motion to Amend; Futility;

Plaintiff, ) Bad Faith; Contracting Officer Final ) Decision

v. )

)

THE UNITED STATES, )

)

Defendant. )

) )

Frank V. Reilly, Fort Lauderdale, FL, for Plaintiff.

Robert C. Bigler, Trial Attorney, Commercial Litigation, Civil Division, U.S. Department of Justice, Washington, DC, for Defendant, with whom were Steven J. Gillingham, Assistant Director, Robert E. Kirschman, Jr., Director, Joseph H. Hunt, Assistant Attorney General.

OPINION AND ORDER

KAPLAN, Judge.

Plaintiff HCIC Enterprises, LLC (“HCIC”) has filed a second motion to amend its complaint. For the reasons set forth below, the motion is denied.

BACKGROUND

I. Relevant Facts 1

The Court’s prior opinions granting the government’s motion for partial summary judgment and denying HCIC’s first motion to amend its complaint contain a comprehensive discussion of the background of the present motion. See HCIC Enters., Inc. v. United States, 147 Fed. Cl. 118, 121–23 (2020); ECF No. 32 (order denying motion to amend complaint). To briefly recapitulate, on April 20, 2016, the Federal Bureau of Prisons (“FBOP”) awarded HCIC a contract worth $2,735,000 to replace roofs on some of the buildings at the Federal Correctional Institute (“FCI”) in Estill, South Carolina. Def.’s Cross Mot. for Partial Summ. J. & Resp. to

1 The facts set forth in this section are drawn from the parties’ pleadings and documents submitted in connection with the earlier motions filed in this case.

Pl.’s Mot. for Summ. J. App. (“Def.’s App.”) at 70, ECF No. 14-1 (February 14, 2019 Determination and Findings Authorizing Contract Termination for Default). Under the contract, the repairs were to be completed within one year. The contracting officer (“CO”) issued a notice to proceed on June 13, 2016, setting a completion date of June 13, 2017. Id.

The performance period was subsequently extended through four bi-lateral contract modifications—first by fifty-five days, then twenty-five days, then 180 days, and finally by 193 days to September 6, 2018. See Initial Compl. Ex. C, at 10–11, ECF No. 1. 2 Despite the extensions, HCIC failed to complete the work by September 5. Def.’s App. at 74. Instead, on September 6, 2018, HCIC filed a claim for an equitable adjustment, requesting another extension of the performance period, this time for 419 days, to October 30, 2019. See Initial Compl. Ex. C, at 10–12. In its claim, HCIC stated that between December 20, 2017 and September 5, 2018 (the period covered by the most recent modification of the contract) the project had incurred another 259 calendar days of delays which HCIC attributed to “the inability of the government to provide adequate staff to escort the necessary HCI[C] crews required to complete the project in the time allotted in the contract.” Id. at 11. HCIC requested $480,821.74 as compensation for additional costs incurred. Id. at 12. It also requested an additional award of $777,854.48 to cover its costs and profit for the additional 419 days it had requested to complete the project. Id.

The CO denied HCIC’s request for an equitable adjustment in a November 14, 2018 email. Id. Ex. D, at 19–20. He noted that the prior extensions “were executed as supplemental agreements and agreed to bi-laterally.” Id. at 19. Those modifications, he explained, “[were] considered complete equitable adjustments for each of the associated time periods.” Id. The CO acknowledged that HCIC was entitled to compensation for twelve days of delay during the most recent modification period “for time that FCI Estill could not accommodate the contractor” and that those days “w[ould] not be calculated in the liquidated damages that are currently accruing.” Id. Finally, the CO observed that HCIC was out of time to complete the project as of the date of his letter. Id. He advised HCIC that it had not provided information “that compels the Government to believe that additional adjustments are necessary or appropriate.” Id. at 19–20. He therefore denied HCIC’s request for a fifth extension of the deadline for completion of the project. Id. at 20.

On February 13, 2019, two months after HCIC filed the present action, it requested that the contract be terminated for convenience. Pl.’s Mot. for Leave to File 2d Am. Compl. Ex. B, ECF No. 29-3 (email exchange from HCIC president to CO seeking contract termination). Instead, the CO issued a “Determination and Findings Authorizing Contract Termination for Default” on February 14, 2019. Def.’s App. at 70. FBOP’s Administering Contracting Officer concurred in the recommended default termination, id. at 78, and the CO issued a Notice of Termination for Default on April 30, 2019, id. at 67–68.

2 Many of Plaintiff’s exhibits are contained in the same document as the initial complaint. The page numbers cited for these exhibits reflect the pagination assigned by the court’s electronic filing system. See Initial Compl., ECF No. 1.

II. Prior Proceedings

HCIC filed the present action on December 19, 2018. ECF No. 1. In its initial complaint, HCIC alleged that FBOP “breached the written agreement between the parties by failing to allow access to the site during normal working hours except during emergencies . . . [,] by failing to provide access to all roofs designated in the Statement of Work . . . [, and] by improperly denying HCI[C]’s claim” submitted to the CO. Initial Compl. ¶¶ 9–10, 12. HCIC further alleged that the CO’s denial of its request for an equitable adjustment was arbitrary and capricious “because there was no evidence in the administrative record to show that HCI[C] is or was the sole and proximate cause of the delayed completion date for the project.” Id. ¶ 14. It demanded an award of $480,821.74 “plus additional damages as will be shown to have been incurred after the date the claim was filed.” Id. ¶ 19.

On September 9, 2019, and before expiration of the discovery period, HCIC filed what it later clarified was a motion for summary judgment pursuant to Rule 56 of the Rules of the Court of Federal Claims (“RCFC”). See HCIC Enters., 147 Fed. Cl. at 123 (clarifying that HCIC sought a motion for summary judgment notwithstanding that its motion was stylized as a motion for judgment on the pleadings). The government filed a cross-motion for partial summary judgment on October 7, 2019 in which it sought a ruling that HCIC’s breach claim was based on a misinterpretation of the relevant provisions of the contract. Id.

The Court denied HCIC’s motion for summary judgment. Id. at 125. It observed that its denial was based on HCIC’s failure to identify what undisputed facts supported its claim, and its inability to “explain how the application of the legal standards it recite[d] entitle[d] it to judgment as a matter of law.” Id. at 124.

Free access — add to your briefcase to read the full text and ask questions with AI

Hcic Enterprises, LLC v. United States, (uscfc 2020).

Hcic Enterprises, LLC v. United States (Hcic Enterprises, LLC v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Assurance Company v. The United States
813 F.2d 1202 (Federal Circuit, 1987)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
Road & Highway Builders, LLC v. United States
702 F.3d 1365 (Federal Circuit, 2012)
Meyer Group, Ltd. v. United States
115 Fed. Cl. 645 (Federal Claims, 2014)
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
Anaheim Gardens v. United States
444 F.3d 1309 (Federal Circuit, 2006)