Hassett v. Dixie Furniture Co., Inc.

425 S.E.2d 683, 333 N.C. 307, 1993 N.C. LEXIS 52
CourtSupreme Court of North Carolina
DecidedFebruary 12, 1993
Docket39PA92
StatusPublished
Cited by15 cases

This text of 425 S.E.2d 683 (Hassett v. Dixie Furniture Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hassett v. Dixie Furniture Co., Inc., 425 S.E.2d 683, 333 N.C. 307, 1993 N.C. LEXIS 52 (N.C. 1993).

Opinion

WEBB, Justice.

The appellant’s first assignment of error deals with the jury instructions in regard to damages. The court instructed the jury that if it found the defendant had breached the 1 March 1986 contract, it could find that the plaintiff was entitled to recover as damages the total amount of the payments due to the plaintiff as if performance had been rendered under the contract.

There was evidence, some of it uncontradicted, that had the plaintiff performed he would have had a considerable amount of expense, including travel between his home in New Jersey and the defendant’s facilities in North Carolina, travel to visit dealers throughout the United States, and trips to the Far East to supervise production. The defendant says it was error not to instruct the jury that the damages must be reduced by the amount of expenses the plaintiff would have incurred if he had performed his duties under the contract. We agree that this was error.

A party injured by a breach of contract is entitled to be placed in the same position he would have occupied if the contract had been performed, insofar as this can be done by an award of money damages. Service Co. v. Sales Co., 259 N.C. 400, 131 S.E.2d 9 *313 (1963). He is not entitled to recover for any cost avoided by the breach of the contract. Professor E. Allan Farnsworth in his treatise on the law of contracts says:

[a breach of contract] may have a beneficial effect on the injured party by saving him the further expenditure that he would have incurred if he had performed. This saving will be referred to as cost avoided. If, for example, the injured party is a builder under a construction contract who stops work after the owner’s breach, the additional expenditure he has saved is cost avoided.

E. Allan Farnsworth, Contracts § 12.9, at 846 (1982).

We have applied this rule in Peasley v. Coke Co., 282 N.C. 585, 194 S.E.2d 133 (1973) and Tillis v. Cotton Mills and Cotton Mills v. Tillis, 251 N.C. 359, 111 S.E.2d 606 (1959), by holding that in order to determine damages costs avoided must be deducted from revenue which would have been received if the contract had not been breaehed.

The appellee argues that pursuant to Arnold v. Charles Enterprises, 264 N.C. 92, 141 S.E.2d 14 (1965), expenses he would have incurred if he had been allowed to complete the contract should not be deducted from the amount he would have received in order to determine damages. Arnold is not precedent for this case. In that case, we held that the plaintiff’s damages for the defendant’s breach of a contract by failing to appear for a concert as he had contracted to do did not have to be reduced by the plaintiff’s expected expenses. In that case, all expenses incurred by the plaintiff in performing his part of the contract had apparently been paid. There was nothing to be deducted from the damages awarded to the plaintiff.

In its second assignment of error, the defendant contends that the court erred when it failed to charge as requested by the defendant on its defenses of accord and satisfaction, compromise and settlement, estoppel, waiver, and ratification. The question raised by this assignment of error is whether there was sufficient evidence for a jury to find that any of these defenses apply.

An accord is a contract under which the obligee promises to accept a stated performance in satisfaction of the obligor’s existing duty.... Not until performance, which is called satisfac *314 tion, however, is the original duty discharged. Discharge in this way is therefore said to be by accord and satisfaction.

E. Allan Farnsworth, Contracts § 4.24, at 285 (1982) (footnote omitted); Allgood v. Trust Co., 242 N.C. 506, 88 S.E.2d 825 (1955); Sharpe v. Nationwide Mut. Fire Ins. Co., 62 N.C. App. 564, 302 S.E.2d 893, cert. denied, 309 N.C. 823, 310 S.E.2d 353 (1983).

Compromise and settlement is provided for by statute and is close kin to accord and satisfaction. N.C.G.S. § 1-540 provides:

In all claims, or money demands, of whatever kind, and howsoever due, where an agreement is made and accepted for a less amount than that demanded or claimed to be due, in satisfaction thereof, the payment of the less amount according to such agreement in compromise of the whole is a full and complete discharge of the same.

In support of its contention that there was sufficient evidence to submit to the jury on the defenses of accord and satisfaction and compromise and settlement, the defendant relies on the evidence that Mr. Young met with plaintiff and told him that he felt plaintiff had breached the contract by engaging in design services for another furniture manufacturer. Mr. Young testified that he informed the plaintiff that he considered the contract to be terminated and the defendant would stop making payments to the plaintiff. The parties discussed a settlement under which the defendant would continue to pay the plaintiff at the same rate of commission for four months at the end of which time the contract between the parties would be terminated. Mr. Young testified that the parties agreed to this accord.

Following the meeting between the plaintiff and Mr. Young, the plaintiff wrote a letter to Mr. Young setting forth his understanding of the terms of the agreement and asking that the defendant prepare a document incorporating its terms. The defendant had such a contract prepared and mailed an executed copy to the plaintiff. The plaintiff refused to sign the document because, he said, there were things in it which were not part of the agreement. The defendant paid to the plaintiff a commission for four months during which time the plaintiff performed no duties for the defendant.

We hold that this evidence would support a finding by the jury that the parties had reached an accord on the plaintiff’s claim against the defendant and the defendant had performed on this *315 agreement, making it an accord and satisfaction. The jury could find this accord and satisfaction from the evidence that the parties discussed a settlement under which the plaintiff would be relieved of all further duties under his contract with the defendant. The defendant’s evidence was that the parties agreed to this accord. The agreement was not put in writing and signed by both parties, but the plaintiff accepted the payments for four months and acknowledged by letter that the parties had agreed to an accord.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Carolina State Bar v. Gilbert
663 S.E.2d 1 (Court of Appeals of North Carolina, 2008)
Keyzer v. Amerlink, Ltd.
654 S.E.2d 833 (Court of Appeals of North Carolina, 2008)
Potter v. Hilemn Laboratories, Inc.
564 S.E.2d 259 (Court of Appeals of North Carolina, 2002)
Shore v. Farmer
515 S.E.2d 495 (Court of Appeals of North Carolina, 1999)
Robinson v. Powell
500 S.E.2d 714 (Supreme Court of North Carolina, 1998)
City of Winston-Salem v. Yarbrough
451 S.E.2d 358 (Court of Appeals of North Carolina, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
425 S.E.2d 683, 333 N.C. 307, 1993 N.C. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hassett-v-dixie-furniture-co-inc-nc-1993.