Harvesters Group, Inc. v. Westinghouse Elec. Corp.
This text of 527 So. 2d 257 (Harvesters Group, Inc. v. Westinghouse Elec. Corp.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
HARVESTERS GROUP, INC., et al., Appellants,
v.
WESTINGHOUSE ELECTRIC CORPORATION, Appellee.
District Court of Appeal of Florida, Third District.
Cooper, Wolfe & Bolotin and Maureen E. Lefebvre and Marc Cooper, Miami, for appellants.
Tew, Jorden & Schulte and Jeffrey A. O'Keefe, Fort Lauderdale, for appellee.
Before BARKDULL, HUBBART and BASKIN, JJ.
BASKIN, Judge.
Harvesters Group, Inc. [Harvesters], a general contractor on a public construction contract, and Fidelity & Deposit Company of Maryland [Fidelity], its surety, appeal from a final judgment in favor of Westinghouse Electric Corporation [Westinghouse], a supplier for a subcontractor on the project, a police station.
Harvesters subcontracted the electrical work on the police station under construction with Classic Electric Corporation [Classic], an electrical subcontractor. Classic purchased materials from Westinghouse. The materials needed to complete the project were delivered prior to the end of *258 1983. Westinghouse sent notices of nonpayment on June 17, 1983, August 19, 1983, September 21, 1983, and October 26, 1983. In February 1984, subsequent to the completion and occupancy of the police station, three parking lot lights malfunctioned. The police department reported the problem to Classic, and at Classic's request, Westinghouse replaced the ballasts on the lights. On May 9, 1984, Westinghouse sent a notice of nonpayment to Harvesters. When it failed to receive payment, Westinghouse filed an action seeking to recover on Harvesters' bond. Finding that Westinghouse had complied with both notice provisions of section 255.05(2), Florida Statutes (1983),[1] and was entitled to recover on the bond, the trial court entered final judgment in its favor. After due deliberation, we hold that the ninety-day notice furnished to Harvesters and its surety did not comply with notice requirements of section 255.05(2). We reverse the final judgment.
Because section 713.01(14), Florida statutes (1987), precludes claimants from obtaining liens on public property, section 255.05(1) provides a claimant who is not in privity with the general contractor on a public construction project a right of action against the contractor and its surety for unpaid materials or labor. See W.G. Mills, Inc. v. M & MA Corp., 465 So.2d 1388 (Fla. 2d DCA 1985); Blosam Contractors, Inc. v. Joyce, 451 So.2d 545 (Fla. 2d DCA 1984); Gorman Co. of Ft. Lauderdale, Inc. v. Frank Maio Gen. Contractors, Inc., 438 So.2d 1018 (Fla. 4th DCA 1983); Miami-Dade Water & Sewer Auth. v. Progress Supply, Inc., 389 So.2d 253 (Fla. 3d DCA 1980); State v. Clutter Constr. Corp., 132 So.2d 21 (Fla. 3d DCA 1961), aff'd, 139 So.2d 426 (Fla. 1962). Before instituting a lawsuit, however, a claimant must comply with notice requirements of section 255.05(2).[2]W.G. Mills; School Bd. v. Fasano, Inc., 417 So.2d 1063 (Fla. 4th DCA 1982); Fuller Indus., Inc. v. R. Terry Blazier & Son, Inc., 188 So.2d 2 (Fla. 2d DCA), cert. denied, 194 So.2d 617 (Fla. 1966); see Gergora v. R.L. Lapp Forming, Inc., 619 F.2d 387 (5th Cir.1980). Cf. National Gypsum Co. v. Travelers Indem. Co., 417 So.2d 254 (Fla. 1982); Pinewood Plumbing Supply Co., Inc. v. Centennial Constr., Inc., 489 So.2d 216 (Fla. 3d DCA 1986).
In United States ex rel. Light & Power Utilities Corp. v. Liles Constr. Co., 440 F.2d 474 (5th Cir.1971), the court considered the purpose of the notice provision in 40 U.S.C.A. § 270b(a), a provision similar to section 255.05(2):[3]
The [Miller Act] provides a method by which those who supply subcontractors may protect themselves. The protection *259 must be invoked within ninety days of the last delivery of goods. The reason for such a limitation is obvious. Contractors should not be compelled to wait around with their liabilities unknown or unsettled for an indefinite length of time, at the convenience of those who may wish to give notice of a claim.
Liles Constr., 440 F.2d at 478. See 3 S. Rakusin, Florida Mechanics' Lien Manual ch. 32 (1987); see also Fasano, Inc., 417 So.2d at 1065 ("Section 255.05(2) protects the contractor and the contractor's surety from having to account to unknown suppliers and subcontractors by putting the burden on the claimants to advise the contractor and surety of their participation on the project and to advise if they are not promptly paid.")
Harvesters and Fidelity contend that Westinghouse's notice of October 26, 1983, was premature because Westinghouse delivered materials after that date. They argue that the notice must be delivered within ninety days after the final furnishing of labor, services and materials not ninety days from substantial completion of performance. Under the plain language of the applicable statute, their position has merit.
[W]here the language in a statute clearly and unambiguously conveys legislative intent, it is unnecessary to resort to statutory construction. Courts should not depart from the plain language of the legislature. A second controlling principle of statutory construction is the rule that words of common usage should be construed in their plain and ordinary sense.
Seaboard System R.R. v. Clemente, 467 So.2d 348, 355 (Fla. 3d DCA 1985) (citations omitted). We direct our consideration, therefore, to section 255.05(2), which provides, in pertinent part:
A claimant who is not in privity with the contractor and who has not received payment for his labor, materials, or supplies shall, within 90 days after performance of the labor or after complete delivery of the materials or supplies, deliver to the contractor and to the surety written notice of the performance of the labor or delivery of the materials or supplies and of the nonpayment.
It is apparent from the plain and unambiguous language that the ninety-day notice must be delivered after delivery of materials is complete. Had the legislature intended the time to run from a substantially completed performance, it would have stated the law accordingly. See Coastal Caisson; Acadia Development Corp. v. Rinker Materials Corp., 419 So.2d 1142 (Fla. 3d DCA 1982), review denied, 431 So.2d 988 (Fla. 1983). Cf. 40 U.S.C.A. § 270b(a) (1986) (where a claimant must give written notice to the prime contractor within ninety days "from the date on which such person ... performed the last of the labor or furnished or supplied the last of the material for which such claim is made.") (Emphasis supplied); § 713.23(1)(e), Fla. Stat. (1987) (lienor required to serve written notice of nonpayment within ninety days of the failure to receive any payment due from delivery date for any materials); § 713.08(5), Fla. Stat. (1987) (claim of lien may be recorded at any time during the progress of the work but not later than ninety days after final furnishing of supplied materials). The record discloses, and the parties agree, that Westinghouse delivered materials to the project subsequent to October 26, 1983. We therefore agree that the October 26, 1983, notice to Harvesters and Fidelity was sent prior to complete delivery and thus did not meet statutory requirements.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
527 So. 2d 257, 13 Fla. L. Weekly 1384, 1988 Fla. App. LEXIS 2469, 1988 WL 56526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harvesters-group-inc-v-westinghouse-elec-corp-fladistctapp-1988.