Clutter Construction Corp. v. Baker Bros.

168 So. 2d 576
CourtDistrict Court of Appeal of Florida
DecidedOctober 29, 1964
DocketNo. F-166
StatusPublished
Cited by6 cases

This text of 168 So. 2d 576 (Clutter Construction Corp. v. Baker Bros.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clutter Construction Corp. v. Baker Bros., 168 So. 2d 576 (Fla. Ct. App. 1964).

Opinion

CARROLL, DONALD K., Acting Chief Judge.

The defendants in an action for materials furnished in the construction of a public building have appealed from a final summary judgment for the plaintiff entered by the Circuit Court for Leon County.

The issue before us for determination on this appeal is whether the court properly entered the said judgment; or, more precisely, whether, under the evidence before the court, the plaintiff sufficiently complied with Section 255.05(2), Florida Statutes, F.S.A., requiring a materialman to give written notice to the contractor of the delivery of the materials within 90 days “after complete delivery of materials and supplies. * * * ”

Sec. 255.05, sub-section (2), the critical statutory provision involved in this appeal, relates to the furnishing of materials in the construction of public buildings, and provides as follows:

“Any person supplying labor, material or supplies used directly or indirectly in the prosecution of the work to any subcontractor and who has not received payment therefor, shall, within ninety days after performance of the labor or after complete delivery of materials and supplies, deliver to the contractor written notice of the performance of such labor or delivery of such materials and supplies and the nonpayment therefor, and no action or suit for such labor or for such materials and supplies may be instituted or prosecuted against the contractor unless such notice has been given. No action or suit shall be instituted or prosecuted against the contractor or against the surety on the bond required in this section after one year from the performance of the labor or completion of delivery of the materials and supplies.”

[577]*577At a pre-trial conference the parties stipulated that there was no dispute as to the facts and that only a question of law remained for decision by the court

The undisputed facts pertinent to the issue of the plaintiff’s compliance with the quoted statute are essentially as follows:

On May 2, 1961, the defendant-appellant Clutter Construction Corporation, hereinafter referred to as Clutter, entered into a contract with the Board of Control of the State of Florida for the construction of the Molecular Biophysics Building on the campus of Florida State University in Tallahassee, Leon County, Florida. Thereafter Clutter, as principal, and the other defendant-appellant, Reliance Insurance Company, as surety, executed a performance and payment bond in favor of the State of Florida. Clutter as the general contractor then subcontracted the mechanical work on this project to one Virgil Reddick by a contract dated May 16, 1961.

Beginning on July S, 1962, the plaintiff supplied certain materials to the sub-contractor, Reddick, some of which were delivered to the job site and some delivered over the counter by the plaintiff’s employees at the plaintiff’s place of business in Tallahassee. Following the first sale on July S, 1962, there were twelve additional sales made by the plaintiff to Reddick during the rest of that month, IS of such sales in the next month, five in September, and one each on October 2, October 26, and December 28, 1962. At the said pre-trial conference the defendants admitted that all of the materials furnished by the plaintiff were utilized in the prosecution of Clutter’s contract for construction of the said Molecular Biophysics Building.

The last date mentioned above, December 28, 1962, is the critical date in the present consideration, for within 90 days after that date — to-wit, on February 18, 1963— the plaintiff notified Clutter as the general contractor by letter that the plaintiff had delivered material to be used in the project to the said sub-contractor but had not received payment therefor.

Whether the plaintiff’s giving of the just-mentioned written notice sufficiently complies with the requirements of the above-quoted provision of Sec. 2SS.0S, is the precise point for determination on this appeal. The appellants contend that the said notice was ineffectual under the statute because it was given more than 90 days “after complete delivery of materials and supplies. * * * ” An integral part of their contention, of course, is that the “complete delivery,” as contemplated by the statute, occurred prior to the sale of December 28, 1962, and that the said sale did not serve to extend the time for the giving of the notice contemplated by the said provision of Section 255.05.

In support of their contention the appellants rely upon the stipulation entered into by the parties at the pre-trial conference that the work was substantially completed on September 15, 1962, that the building was finally completed on November 1, 1962, and that any work done thereafter was in the nature of patching, correcting, or repairing. The appellants recognize, however, that Reddick’s contract with Clutter required him to make the necessary repairs after completion of the work called for in his said contract, and that Clutter was required by its contract with the Board of Control to make necessary repairs.

Reddick’s foreman testified in his deposition, which was before the court, that on December 28, 1962, he drove in one of Red-dick’s trucks to the plaintiff’s place of business and ordered three drill bits of an unusual size for use in installing in the said building a fire damper as required by the specifications of Reddick’s contract with Clutter; that he told the plaintiff’s salesman that the purchase should be billed to the biophysics job, and the invoice was so written; and that he was “reasonably sure” that the items then purchased were used at the said building.

[578]*578From the foregoing testimony and stipulation we think that the only conclusion that can be fairly drawn is that the items purchased by and delivered to Reddick’s foreman on December 28, 1962, though the items are seemingly minor in nature, were used in the patching, correcting, or repairing of the work which Reddick was required to perform by his contract with Clutter, in pursuance of his obligation thereunder to make necessary repairs after the completion of the work called for by that agreement. Upon the basis of this factual conclusion, the basic question before us is whether the plaintiff’s written notice of February 18, 1963, was delivered to Clutter “ * * * within ninety days * * * after complete delivery of materials and supplies * * * ” to Clutter’s sub-contractor, Reddick, within the contemplation of these quoted words of Section 255.05, Florida Statutes, F.S.A. Since the only delivery of materials taking place within the 90 days preceding February 18, 1963, was the delivery of the materials to Reddick’s foreman on December 28, 1962, the pinpointed question before us is whether the “complete delivery of materials and supplies” did not occur until the latter date.

To answer the last-stated question we must analyze, interpret, and apply the above-quoted provisions of Section 255.05 relating to a materialman’s written notice to the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burke Co. v. Bruce M. Ross Co.
585 So. 2d 382 (District Court of Appeal of Florida, 1991)
St. Paul Fire & Marine Insurance v. Test & Balance Corp.
37 Fla. Supp. 2d 7 (Florida Circuit Courts, 1989)
Harvesters Group, Inc. v. Westinghouse Elec. Corp.
527 So. 2d 257 (District Court of Appeal of Florida, 1988)
Coastal Caisson Drill v. Amer. Cas. Co.
523 So. 2d 791 (District Court of Appeal of Florida, 1988)
Clutter Construction Corp. v. Baker Bros.
173 So. 2d 146 (Supreme Court of Florida, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
168 So. 2d 576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clutter-construction-corp-v-baker-bros-fladistctapp-1964.