Burke Co. v. Bruce M. Ross Co.

585 So. 2d 382, 1991 Fla. App. LEXIS 8159, 1991 WL 156623
CourtDistrict Court of Appeal of Florida
DecidedAugust 15, 1991
DocketNo. 90-3577
StatusPublished
Cited by1 cases

This text of 585 So. 2d 382 (Burke Co. v. Bruce M. Ross Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burke Co. v. Bruce M. Ross Co., 585 So. 2d 382, 1991 Fla. App. LEXIS 8159, 1991 WL 156623 (Fla. Ct. App. 1991).

Opinion

WENTWORTH, Senior Judge.

This is an appeal from a summary judgment for appellees holding that section 255.05, Florida Statutes, requires that notice of nonpayment be given within 90 days from last physical delivery of rental equipment, rather than from last use of the rental equipment, for purposes of recovery under the public construction payment bond. We reverse and certify conflict with Moretrench American Corporation v. Taylor Woodrow Construction Corporation, 565 So.2d 861 (Fla. 2d DCA 1990).

In November, 1988, appellee Taylor Woodrow contracted with the City of Jacksonville to build the Jacksonville Pre-Trial Detention Facility. Pursuant to section 255.05, Florida Statutes, Woodrow posted a statutory bond issued by appellee American Home Assurance Company. Woodrow subcontracted some of the work to appellee Ross Company. Ross then entered into a contract with appellant Burke Company by which Burke agreed to rent to Ross certain equipment to be used by Ross in performing under its agreements with Taylor Woodrow.

On December 22, 1988, within 45 days of commencing performance under its contract (as required under section 255.05(2), Florida Statutes), Burke furnished Woodrow with notice of intent to look to the bond for payment. Appellant last deliv[383]*383ered additional rental equipment to the project on June 26, 1989. All or a portion of appellant’s equipment remained on the job available for use by the contractor through and until July 19, 1989. Within 90 days of July 19, 1989, appellant Burke provided appellees Taylor Woodrow and American Home Assurance Company with notice of nonpayment. Appellant’s notice of nonpayment was delivered within 90 days of the last date of use of its rental equipment on the project but not within 90 days of its last delivery of additional rental equipment.

Appellant instituted the action below in an effort to recover against the bond by filing a complaint alleging nonpayment by appellee Ross. The circuit court granted defendants/appellees motion for summary judgment on November 5, 1990. The court explained the basis for its decision:

The Second District Court of Appeal has recently addressed a similar situation involving rental equipment in Moretrench American Corp. v. Taylor Woodrow Construction Corp., 565 So.2d 861 (Fla. 2d DCA 1990) and found that the “complete delivery” language of § 255.05(2) meant the last day the equipment was physically delivered to the job site and declined to adopt the appellant’s contention that the 90-day period did not begin until the last day of the availability for use of the equipment on the job. As of the date of this order, no other district court of appeal has addressed this question and, therefore, this Court must follow that holding.

We recognize, as noted in opinions such as Streeter v. Sullivan, 509 So.2d 268 (Fla.1987), that “[ijnquiry into legislative intent may begin only where the statute is ambiguous on its face.” Id. at 271, citing State v. Egan, 287 So.2d 1, 4 (Fla.1973). Streeter went on to state, however, that where statutory provisions are “even slightly ambiguous, an examination of legislative history and statutory construction principles would be necessary.” Id. at 271. The threshold question presented, then, is whether section 255.05, Florida Statutes is facially ambiguous.

The relevant portions of the statute state:

Such bond shall be conditioned that the contractor perform the contract in the time and manner prescribed in the contract and promptly make payments to all persons defined in s.713.01 whose claims derive directly or indirectly from the prosecution of the work provided for in the contract.

Section 255.05(l)(a), Florida Statutes, (1989).

A claimant who is not in privity with the contractor and who has not received payment for his labor, materials, or supplies shall, within 90 days after performance of the labor or after complete delivery of the materials or supplies, deliver to the contractor and to the surety written notice of the performance of the labor or delivery of the materials or supplies and of the nonpayment.

Section 255.05(2), Florida Statutes, (1989) (emphasis added).

Prior to Moretreneh, supra, the second district court was called on to construe a different portion of section 255.05(2), and opined:

This section [255.05(2)] is intended to [provide] subcontractors and material-men on public work projects with the same type of protection which is available to subcontractors and materialmen on private projects under the Mechanics’ Lien Law.

Miller v. Knob Construction Company, 368 So.2d 891 (Fla. 2d DCA 1979) at 893, citing Winchester v. State, 134 So.2d 826 (Fla. 2d DCA 1962). In Miller, therefore, if only in dicta, the court suggests that section 255.05 should be read in pari mate-ria with section 713.01, the Mechanics’ Lien Law, the position rejected by the Mor-etrench court as unnecessary because of the clarity of section 255.05.

In Gergora v. R.L. Lapp Forming, Inc., 619 F.2d 387 (5th Cir.1980), the court noted that:

Section 255.05 states that notice must be within ninety days of “complete delivery” of materials, whereas the statute refers only to the “performance” of labor — and not complete performance — as beginning the ninety day period.
[384]*384We regard this variation in phraseology within the same statute as more ambiguous than meaningful. The statute is subject to at least two reasonable interpretations. Either the qualification that delivery of materials must be “complete” creates a different rule for severable material contracts than for severable labor contracts, or it merely emphasizes that materials must be delivered to the construction site ready for use before the period begins to run.

Id. at 389.

Thus, in Gergora, the Fifth Circuit construed section 255.05 according to similar language in the Miller Act, 40 U.S.C. section 270b, rejecting the contention that the notice period for unpaid fringe benefits ran separately from each day of the labor upon which the claim was based.

Appellee cites Harvesters Group, Inc. v. Westinghouse Electric Corporation, 527 So.2d 257 (Fla. 3d DCA 1988) for the proposition that the notice provision of section 255.05(2) is plain and unambiguous. While Harvesters surely holds the notice provision unambiguous, that case dealt with materials purchased, not leased. In Harvesters, the supplier, Westinghouse, made a number of deliveries of purchased materials during 1983. Westinghouse also sent notices of nonpayment for these materials, the last being sent on Oct. 26, 1983. Both parties stipulated, however, that Westinghouse delivered additional materials to the project subsequent to October 26, 1983. The court held that the notices of nonpayment were premature, and not in compliance with the notice provision of the statute which requires that the notice must be delivered after delivery of materials is complete. Id. at 259. Because of the factual dissimilarities, the decision in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor Woodrow Construction Corp. v. Burke Co.
606 So. 2d 1154 (Supreme Court of Florida, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
585 So. 2d 382, 1991 Fla. App. LEXIS 8159, 1991 WL 156623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burke-co-v-bruce-m-ross-co-fladistctapp-1991.