Hartland Group North Avenue

CourtVermont Superior Court
DecidedDecember 14, 2006
Docket120-06-05 Vtec
StatusPublished

This text of Hartland Group North Avenue (Hartland Group North Avenue) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartland Group North Avenue, (Vt. Ct. App. 2006).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re: Hartland Group, 237 North Ave. Project } Docket No. 120‐6‐05 Vtec (Appeal of Bjerke, et al.) } }

Decision and Order on Cross‐Motions for Summary Judgment

Appellants Alan Bjerke, Valerie Hockert‐Lotz, Edward Winant, Annelein

Beukenkamp‐Winant, James Bumpas and Molly Bumpas, appealed from the decision of

the Development Review Board (DRB) of the City of Burlington, granting Appellee‐

Applicant Hartland Group, LLC’s application for approval of a building housing twenty‐

five condominiums and a restaurant‐café at 237 North Avenue. Appellants are represented

by Appellant Alan A. Bjerke, Esq.; Appellee‐Applicant is represented by Ronald A. Shems,

Esq.; and the City is represented by Kimberlee J. Sturtevant, Esq.

The parties have moved for partial summary judgment on Questions 2, 3, 4, 8, 9 and

10 of Appellants’ Revised Statement of Questions. A related application for Act 250

approval of this project was granted; the Act 250 land use permit was not appealed. The

parties have also filed memoranda addressing the preclusive effect of the final Act 250

permit on the issues in this municipal appeal. The following facts are undisputed unless

otherwise noted.

Appellee‐Applicant proposes to redevelop an existing .65‐acre parcel1 of property,

1 The parcel as a whole encompasses an additional 0.05 acre strip of land on the westerly end of the original parcel (at the top of the cliff), purchased from the City in September 2004. However, a condition of the deed states that the additional parcel “will not be used to calculate allowable density, setbacks or lot coverage to meet zoning

1 currently improved with an existing 16,500 square‐foot commercial building, at 237 North

Avenue. Appellee‐Applicant proposes a twenty‐five‐unit condominium complex and a

forty‐seat restaurant‐café. Appellee‐Applicant’s parcel is located at the intersection of

North Avenue and Berry Street in a Residential Medium‐Density zoning district in the

City’s “Old North End” neighborhood.

The lot at 237 North Avenue is roughly rectangular, with the shorter dimension of

approximately2 ninety‐two feet fronting3 on the west side of North Avenue. The next street

intersecting with the west side of North Avenue to the north of Berry Street is Sunset Court.

The northerly lot line of the project parcel is bordered by three residential lots having

frontage on Sunset Court.

The southerly lot line of the project parcel is approximately 314 feet in length. It runs

for approximately 246 feet along the northerly side of Berry Street to the westerly side of

the intersection of Berry Street with Lakeview Terrace, where it makes an approximate

two‐foot jog to the north, and continues towards the west for approximately sixty‐eight feet

along the northerly side lot line of Appellants Hockert‐Lotz and Bjerke’s property. The

parcel’s westerly lot line runs at an angle along the top of the cliff above the adjacent city‐

requirements for the development” of the original 0.65‐acre lot. Accordingly, the calculations set forth in this decision are based upon the 0.65‐acre lot rather than the full 0.7‐acre lot. 2 All distances are approximate by scale measurement from the reduced‐size plans filed as exhibits to Appellee‐Applicant’s motion, and are used for descriptive rather than for quantitative purposes. 3 The lot’s orientation to the other surrounding streets and adjacent parcels has raised an issue, posed by Question 3 of the Statement of Questions, as to whether each of the property’s other lot lines should be treated as a front, a side or a rear lot line, for the purposes of determining which setback requirements are applicable to the new portions of the project. See discussion of Question 3, at pp. 13–16, below.

2 owned property to connect with the northerly lot line.

As shown on the lot coverage calculations submitted by Appellee‐Applicant on

sheet L1 of the proposed plans, the existing building and its associated paved and gravel

parking lot cover approximately 89% of the .65‐acre parcel. As shown on sheet E‐1 of the

proposed plans, the existing building itself is approximately 91ʹ in width, set back at a slant

approximately sixteen to twenty feet from the easterly lot line (the property’s frontage on

North Avenue). The existing single‐story building extends westerly at a shallow angle to

the lot line, approximately 146 feet along Berry Street to the entrance to the parking lot,

very close to the southerly lot line. The existing building is located very close to the

northerly lot line as well. The remaining segment of the existing building extends

approximately a further sixty feet westerly, but only occupies approximately the northern

half of the western side of the property. Some of the parking area to the west of the

existing building is paved, while the remainder is surfaced with gravel; the parking area

occupies most of the remaining lot area not covered by the existing building structure. A

chain link fence surrounds the southerly and westerly sides of the parking lot, access to

which is controlled by a gate.

The property of Appellants Bjerke and Hockert‐Lutz is adjacent to the southerly lot

line of the project property as that line extends westerly from the corner of Berry Street and

Lakeview Terrace. The northerly side of their house nearly abuts their northerly lot line.

The other Appellants own property on Sunset Court. The property of Appellants Winant

and Beukenkamp‐Winant is located at the westerly end of Sunset Court, adjacent to the

northerly lot line of the project property. Their existing detached garage abuts the

northerly lot line of the project property. The property of Appellants Bumpas is located

easterly of the Winant property on Sunset Court, also adjacent to the northerly lot line of

the project property. Their existing attached garage also nearly abuts the northerly lot line

of the project property.

3 The original building on the property, a 2,600 square‐foot two‐story portion of the

existing building nearest the northeast corner of the project property, was constructed in

1923. By 1928, the building had been expanded for use as an automobile dealership,

extending across the entire North Avenue frontage and towards the west along Berry

Street, with room for some parking along North Avenue in front of the building. The

building was in use as an automobile showroom and repair facility. The original auto

showroom contained a stepped, parapeted gable roof, which remains intact, as does the

remainder of the original service garage on the North Avenue side of the property. The

original auto showroom had two large windows facing North Avenue on the ground floor

showroom level, and a third window centrally located on the second floor above the door,

all of which remain in place at the present time. Some of the other windows facing North

Avenue and Berry Street have been bricked in, but windows along Berry Street near the

intersection with Lakeview Terrace, and near the intersection with North Avenue have

been left in place. The third addition to the building extended the building westerly and

added a loading dock on the westerly end of the building, and installed a parking lot with

access near the intersection of Berry Street and Lakeview Terrace.

The automobile dealership operated at the property through the adoption of zoning

in Burlington in 1971.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Appeal of Casella Waste Management, Inc.
2003 VT 49 (Supreme Court of Vermont, 2003)
Judicial Watch, Inc. v. State
2005 VT 108 (Supreme Court of Vermont, 2005)
Appeal of Weeks
712 A.2d 907 (Supreme Court of Vermont, 1998)
Levine v. Wyeth
2006 VT 107 (Supreme Court of Vermont, 2008)
Galanes v. Town of Brattleboro
388 A.2d 406 (Supreme Court of Vermont, 1978)
In Re Dunnett
776 A.2d 406 (Supreme Court of Vermont, 2001)
Preseault v. Wheel
315 A.2d 244 (Supreme Court of Vermont, 1974)
Sheehan v. Department of Employment & Training
733 A.2d 88 (Supreme Court of Vermont, 1999)
Granger v. Town of Woodford
708 A.2d 1345 (Supreme Court of Vermont, 1998)
Kalakowski v. John A. Russell Corp.
401 A.2d 906 (Supreme Court of Vermont, 1979)
Smith v. Town of St. Johnsbury
554 A.2d 233 (Supreme Court of Vermont, 1988)
Appeal of Gregoire
742 A.2d 1232 (Supreme Court of Vermont, 1999)
In Re Appeals of Letourneau
726 A.2d 31 (Supreme Court of Vermont, 1998)
In Re Kisiel
772 A.2d 135 (Supreme Court of Vermont, 2000)
In Re Central Vermont Public Service Corporation
769 A.2d 668 (Supreme Court of Vermont, 2001)
In Re Maple Tree Place
594 A.2d 404 (Supreme Court of Vermont, 1991)
Trickett v. Ochs
2003 VT 91 (Supreme Court of Vermont, 2003)
Will v. Mill Condominium Owners' Ass'n
2004 VT 22 (Supreme Court of Vermont, 2004)
In re Appeal of Korbet
2005 VT 7 (Supreme Court of Vermont, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Hartland Group North Avenue, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartland-group-north-avenue-vtsuperct-2006.