Hartland Group North Avenue

Vermont Superior Court·Decided August 31, 2007·No. 120-06-05 Vtec·Published

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

}

In re: Hartland Group, 237 North Ave. Project } Docket No. 120-6-05 Vtec (Appeal of Bjerke, et al.) } }

Decision and Order

Appellants Alan Bjerke, Valerie Hockert-Lotz, Edward Winant, Annelein Beukenkamp-Winant, James Bumpas and Molly Bumpas appealed from the decision of the Development Review Board (DRB) of the City of Burlington, granting Appellee-Applicant Hartland Group, LLC’s application for approval of a project consisting of twenty-five condominiums and a restaurant-café at 237 North Avenue. Appellants are represented by Paul S. Gillies, Esq. and Appellant Alan A. Bjerke, Esq.; Appellee-Applicant is represented by Brian Dunkiel, Esq. and Ronald A. Shems, Esq.; and the City is represented by Kimberlee J. Sturtevant, Esq.

Certain issues in this appeal were resolved on summary judgment.1 An evidentiary hearing was held in this matter before Merideth Wright, Environmental Judge, and a site visit was taken with the parties and their representatives. The parties were given the opportunity to submit written memoranda and requests for findings. Upon consideration

1 The decision and order on summary judgment issued in this matter on December 14, 2006, is hereby incorporated in this decision and will not be repeated except as necessary for clarity in this decision. As agreed by the parties at trial and reflected in their post-trial filings, the issues remaining for trial after the resolution of the summary judgment motion were Question 4 relating to the number of parking spaces required for the proposed café, waiver of a loading space, and waiver of parking spaces; Question 5, which contained subsections (a) through (e); Questions 6(a) and 6(b); and Question 9. Question 9 was resolved on the record on the first day of trial.

of the evidence as illustrated by the site visit, and of the written memoranda and requests for findings filed by the parties, the Court finds and concludes as follows.

Appellee-Applicant proposes to redevelop an existing .65-acre parcel2 of property, currently improved with an existing 16,500 square-foot commercial (warehouse) building, at 237 North Avenue. The building was originally in use as an automobile showroom and dealership. Appellee-Applicant proposes a twenty-five-unit condominium complex and a forty-seat restaurant-café. Appellee-Applicant’s parcel is located at the intersection of North Avenue and Berry Street in a Residential Medium-Density zoning district in the City’s “Old North End” neighborhood.

As more fully described and analyzed in the Decision and Order on summary judgment, the commercial warehouse use of the building is nonconforming but holds a valid permit. The proposed residential use is a conforming use in the district; the café is analyzed as a change of a preexisting nonconforming commercial warehouse use under §5.1.8. The café use proposed for the portion of the building fronting on North Avenue will be less harmful or detrimental to the neighborhood than the warehouse use as it is entitled to operate under its existing permit.

The project property is roughly rectangular, with the shorter dimension facing the west side of North Avenue. The next street intersecting with the west side of North Avenue to the north of Berry Street is Sunset Court. The northerly lot line of the project parcel is bordered by three residential lots having frontage on Sunset Court.

2 The parcel as a whole encompasses an additional 0.05 acre strip of land on the westerly end of the original parcel (at the top of the cliff), purchased from the City in September 2004. However, a condition of the deed states that the additional parcel “will not be used to calculate allowable density, setbacks or lot coverage to meet zoning requirements for the development” of the original 0.65-acre lot. Accordingly, the calculations regarding density, setbacks and lot coverage in this case have been based upon the 0.65-acre lot size rather than the full 0.7-acre lot size.

The southerly lot line of the project parcel runs approximately along the northerly side of Berry Street to the westerly side of the intersection of Berry Street with Lakeview Terrace, where it makes an approximate two-foot jog to the north, and continues towards the west along the northerly side lot line of Appellants Hockert-Lotz and Bjerke’s property. The parcel’s westerly lot line runs at an angle along the top of the cliff above the adjacent city-owned property.

Question 6(a) - Major Impact Development criterion §13.1.6(d) (soil erosion or reduction in the capacity of the land to hold water)

Appellee-Applicant has argued that the criterion in the Zoning Ordinance regarding soil erosion and the soil’s capacity to hold water is sufficiently similar to criterion 4 of Act 250 so that the positive conclusion in the unappealed Act 250 permit on soil erosion and the soil’s capacity to hold water should conclude this issue in this Court, based on principles of issue preclusion. Trepanier v. Getting Organized, Inc., 155 Vt. 259, 265 (1990); In re Stowe Club Highlands, 166 Vt. 33, 36-37 (1996). It is unnecessary to analyze all the criteria for applying issue preclusion in the present case, and especially “the legal standards and burdens employed in each action” and “the procedural opportunities available in each forum.” Trepanier, 155 Vt. at 265. Rather, the better practice in the present context is to reach the merits of the issue so that this Court’s conclusions are clear, based on the evidence presented in this proceeding.

For the purposes of determining runoff, the existing parking area acts as impervious surface even though is partly paved and partly of compacted gravel. Therefore, the impervious surface is not increased even though a greater proportion of the property will be covered with the building. Under current conditions, stormwater runs off the property uncontrolled.

The project proposes to collect stormwater falling on the building by conducting it

to roof drains and thence to stormwater detention tanks to be located below the floor slab of the parking garage. The tanks will be equipped with access for cleaning. Oil will be separated from the stormwater and the stormwater will be controlled by a slow-release orifice to provide twelve to twenty-four hours of detention time to minimize the effect of a storm on the City’s stormwater system. The project proposes to conduct stormwater falling on the westerly grassed area and ground-level patios to a shallow sedimentation basin located at the westerly end of the property. The proposed stormwater system will reduce the risk of soil erosion and other stormwater pollution after construction. In addition, the erosion prevention and sediment control plan proposed to be followed during construction will prevent unreasonable soil erosion during construction. The capacity of the land to hold water will be improved by the sedimentation tank system and the sedimentation basin. The proposal therefore meets §13.1.6(d) of the Zoning Ordinance.

Question 6(b) - Major Impact Development criterion §13.1.6(e) (unreasonable congestion or unsafe conditions with respect to use of the highways) and Question 5 - Design Review criterion § 6.1.10(d) as to traffic Appellee-Applicant has argued that the traffic criteria in the Zoning Ordinance are sufficiently similar to criterion 5 of Act 250 so that the positive conclusion in the unappealed Act 250 permit on traffic should conclude the issue in this Court, based on principles of issue preclusion. For the same reasons as with regard to Question 6(a), the Court will reach the merits of the issue based on the evidence presented in the present case.

The proposed residential use will generate approximately eleven to thirteen one-

Free access — add to your briefcase to read the full text and ask questions with AI

Hartland Group North Avenue, (Vt. Ct. App. 2007).

Hartland Group North Avenue (Hartland Group North Avenue) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Trepanier v. Getting Organized, Inc.
583 A.2d 583 (Supreme Court of Vermont, 1990)
In Re Stowe Club Highlands
687 A.2d 102 (Supreme Court of Vermont, 1996)