In Re Appeal of Casella Waste Management, Inc.

2003 VT 49, 830 A.2d 60, 175 Vt. 335, 2003 Vt. LEXIS 93
CourtSupreme Court of Vermont
DecidedMay 29, 2003
Docket02-324
StatusPublished
Cited by52 cases

This text of 2003 VT 49 (In Re Appeal of Casella Waste Management, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Appeal of Casella Waste Management, Inc., 2003 VT 49, 830 A.2d 60, 175 Vt. 335, 2003 Vt. LEXIS 93 (Vt. 2003).

Opinion

Amestoy, C J.

¶ 1. Appellants Sally Mole, Dale Guldbrandsen, Tim and Kerry Walker, and Ruth Fuller-White (“landowners” collectively) *336 appeal from a decision of the environmental court approving the construction of an access road connecting a solid waste transfer station owned by appellee Casella Waste Management, Inc. (“Casella”) to Route 7A in Manchester. Landowners assert that the access road constitutes an unauthorized extension of a pre-existing nonconforming use to an adjacent parcel because: (1) Manchester’s zoning ordinance does not allow the. extension of a nonconforming use onto land not previously occupied by the nonconforming use; and (2) the purpose of Vermont’s zoning statute is to eliminate nonconforming uses. Thus, landowners argue that the trial court erred by construing Manchester’s zoning ordinance to permit such a use. We affirm.

¶2. Casella owns and operates a solid waste transfer station located on a parcel of land straddling the Manchester/Sunderland town line. The transfer station functions as a pre-existing nonconforming use in the farming and rural residential zoning district in the town of Manchester. Waste hauling trucks travel to Route 7 or Route 7A via small, rural roads such as River Road and Richville Road in Manchester, or Sunderland Hill Road and Hill Farm Road in Sunderland.

¶ 3. In 1998, Casella applied to the State of Vermont District Environmental Commission # 8 for a permit to upgrade its transfer station and solid waste hauling operation. The Commission issued the permit on the condition that Casella either construct a new access road to the facility or implement a traffic mitigation plan in order to alleviate the adverse impacts of the commercial trucks on the rural road system. In January 1999, Casella submitted a plan to the Town of Manchester Zoning Board of Adjustment (ZBA) to construct an access road through an adjacent parcel of land providing direct access to Route 7A from the transfer station. The adjacent parcel was previously owned by E.C. Crosby and Sons, Inc., but Casella purchased it during the course of the permit application process.

¶ 4. Landowners, who live near the transfer station, opposed Casella’s proposed access road. After conducting hearings to review the project, the Manchester ZBA approved the plan to construct the access road and issued Casella a permit in June 1999. The ZBA found that the proposed access road would “improve public health, safety, and welfare by removing large truck traffic from the back roads of Manchester and Sunderland.”

¶ 5. In the summer of 1999, both parties filed notices of appeal to the environmental court. Casella appealed two conditions imposed by the ZBA’s decision granting permission to build the access road. *337 Landowners cross-appealed, arguing that the ZBA’s decision was invalid. Prior to trial, landowners moved for summary judgment, asserting that Vermont law prohibits Casella from extending its nonconforming use onto land not previously subject to such use unless Casella obtained a variance, and that in any event Casella would not be eligible to obtain a variance. The motion for summary judgment was denied. Evidentiary hearings were held over a three-day period in the fall of 2001. Following post-trial briefing in which landowners renewed their request that Casella’s application be denied and judgment be entered in their favor as a matter of law, the environmental court issued a final decision approving Casella’s application on July 5, 2002. This appeal followed.

¶ 6. Zoning ordinances are interpreted according to the general rules of statutory construction. In re Weeks, 167 Vt. 551, 554, 712 A.2d 907, 909 (1998). Thus, we first look to the plain meaning of the ordinance. In re Stowe Club Highlands, 164 Vt. 272, 279, 668 A.2d 1271, 1276 (1995). If the plain meaning “resolves the conflict without doing violence to the legislative scheme, there is no need to go further, always bearing in mind that the paramount function of the court is to give effect to the legislative intent.” Lubinsky v. Fair Haven Zoning Bd., 148 Vt. 47, 49, 527 A.2d 227, 228 (1986). We review the environmental court’s construction of a zoning ordinance to determine whether the interpretation is clearly erroneous, arbitrary or capricious. Weeks, 167 Vt. at 554, 712 A.2d at 909.

¶ 7. Landowners’ principal contention in this case is that the environmental court erred in construing Manchester’s zoning ordinance so as to authorize an extension of a nonconforming use to adjacent land. At issue is the environmental court’s interpretation of § 8.1.1.3 of Manchester’s ordinance, which provides:

No nonconforming use shall be extended or expanded, except with the approval of the [ZBA], provided that the [ZBA] shall have found that such extension or expansion will have no adverse effect upon the public health, safety, convenience, and upon property values in the vicinity; and, in judging the application, the [ZBA] should consider the criteria that would apply to the use if it were in a zone in which the use is permitted.

¶ 8. Landowners assert that because “the central purpose of the zoning statute [is] to eliminate nonconforming uses,” In re Richards, 174 Vt. 416, 424, 819 A.2d 676, 683 (2002), a zoning ordinance must be *338 strictly construed against the extension of nonconforming uses onto land not previously occupied by the nonconforming use. Landowners contend that the environmental court’s decision approving Casella’s permit application must be reversed because neither Manchester’s zoning ordinance nor Vermont’s zoning laws provide the authority to grant a permit under the facts of this case. We disagree.

¶ 9. Landowners correctly observe that there is a strong public interest in regulating the extension and undue perpetuation of nonconforming uses. In re Gregoire, 170 Vt. 556, 559, 742 A.2d 1232, 1236 (1999) (mem.). One of the primary goals of zoning is to gradually eliminate nonconforming uses because “they are inconsistent with the purpose of developing use-consistent areas in communities.” Id. at 558, 742 A.2d at 1235. As such, we strictly construe zoning ordinances allowing nonconforming uses. Id. at 559, 742 A.2d at 1236.

¶ 10. Vermont’s relevant zoning statute, 24 V.S.A. § 4408(b), authorizes municipalities to regulate nonconforming uses in the following four circumstances: “(1) Changes of nonconforming uses to another nonconforming use; (2) Extension or enlargement of nonconforming uses; (3) Resumptions of nonconforming uses ...; and (4) Movement or enlargement of a structure containing a nonconforming use.” Vermont law does not mandate a specific method for regulating nonconforming uses; thus, “we turn to the municipal zoning regulation to determine how the municipality regulates nonconforming uses.” In re Miserocchi, 170 Vt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Budget Inn NOV
Vermont Superior Court, 2015
Lakehouse Pub Grille Permit
Vermont Superior Court, 2015
Dorr Earth Extraction
Vermont Superior Court, 2015
In re Burlington Airport Permit
Supreme Court of Vermont, 2014
In re Williamson Third Tier Application
Supreme Court of Vermont, 2014
In re Champlain Oil Company Conditional Use Application
2014 VT 19 (Supreme Court of Vermont, 2014)
In re Group Five Investments CU Permit
2014 VT 14 (Supreme Court of Vermont, 2014)
49 Tanglewood Final Plan
Vermont Superior Court, 2013
In Re Tyler Self-Storage Unit Permits
2011 VT 66 (Supreme Court of Vermont, 2011)
Bowen CU Application
Vermont Superior Court, 2011
Musto Cosntruction Permit
Vermont Superior Court, 2011
Bowen Conditional Use Application
Vermont Superior Court, 2010
Tyler Self-Storage Units Permit
Vermont Superior Court, 2010
Benning Accessory Use Permit
Vermont Superior Court, 2010

Cite This Page — Counsel Stack

Bluebook (online)
2003 VT 49, 830 A.2d 60, 175 Vt. 335, 2003 Vt. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-appeal-of-casella-waste-management-inc-vt-2003.