Hartford Fire Insurance v. Riefolo Construction Co.

410 A.2d 658, 81 N.J. 514, 1980 N.J. LEXIS 1318
CourtSupreme Court of New Jersey
DecidedJanuary 17, 1980
StatusPublished
Cited by34 cases

This text of 410 A.2d 658 (Hartford Fire Insurance v. Riefolo Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Fire Insurance v. Riefolo Construction Co., 410 A.2d 658, 81 N.J. 514, 1980 N.J. LEXIS 1318 (N.J. 1980).

Opinions

The opinion of the court was delivered by

PASHMAN, J.

This case involves questions of contract interpretation arising from a fire at a public construction project. Preliminarily, we consider the right of plaintiff insurance company to sue in subrogation on its insured’s contract claims. Finding that such a suit may be maintained, we next determine which of the [518]*518parties to the construction contracts should bear the risk of loss due to fire occurring prior to completion of construction. We hold that the risk lay with defendant contractors, and that their sureties, also defendants, may be held liable should the contractors fail to satisfy plaintiff’s claims.

In April 1972, the Board of Education of Vocational Schools in Essex County (Board) engaged the five defendant contractors1 to construct the Essex County Technical Careers Center in Newark, New Jersey. The contracts between the Board and each builder incorporated a set of “General Conditions” and “Special Conditions.” The General Conditions were promulgated by the Economic Development Administration of the United States Department of Commerce (EDA), which was financing the construction. The Special Conditions had been drafted by the building’s supervising architect.

Section 28(e) of the General Conditions obliged each contractor to procure and maintain builder’s risk insurance “during the life of [the] contract on the insurable portion of the project.” Before construction began, each builder notified the Board that it had secured all necessary insurance. Section 29 of the General Conditions required each contractor to obtain a performance bond in an amount equal to its contract price as security for complete performance. Each obtained such a bond, executed on a standard EDA form, from one of the surety defendants.2 Sections 13 of the General Conditions and 1.39 of the Special Conditions obligated the contractors to repair any and all damage to the building occurring prior to its acceptance, unless such damage was due to fault of the Board. Section 1.37 of the [519]*519Special Conditions stated that acceptance occurred only when all work including all minor punch-list items, was complete.

In April 1972, each contractor received a written “Notice to Proceed,” which stated that the scheduled completion date was October 2, 1973. Construction was still not complete on April 1, 1974. At that time the Board determined that it needed to assign employees to the Careers Center to prepare for the 1974-1975 school year. On May 17,1974, the architect wrote the Board that its staff could use the executive office area but that “no educational process may be carried on until the building is 100% complete and inspected and approved by the Division of School Building Services of the State Department of Education.” In June 1974 certain personnel were assigned to the building. By August 8, the day before the fire, 16 persons, including 6 teachers, had been assigned to the building, and Board employees occupied the entire first floor and the library on the second floor. Portions of the third floor were being used to store furniture. Employees were interviewing prospective students at the site but no classes had been held there.

Construction continued while the Board was using the building. By August 8 the building was between 90% and 95% complete. On that date, the Board ordered casualty insurance from Hartford for the project’s completed portion. Hartford supplied such coverage and a binder was issued evidencing coverage in the amount of $6,500,000 commencing that same day.

On the next day, August 9, a fire of undetermined origin started on the third floor of the building, causing $250,000 in damage. After two subsequent job site meetings, the Board notified all contractors to begin repair work. In a telegram sent to four of the builders, the Board stated that its payments for the work would be reimbursed by its own insurer and the [520]*520contractors’ builder’s risk carriers.3 The Board and Hartford later reached an agreement whereby Hartford would advance repair monies on condition that it be subrogated to the Board’s claims against the contractors. The contractors were paid with the monies so advanced.

When the Board and Hartford sought reimbursement from the contractors’ builder’s risk insurers, they found that Elizabeth, Fluoro and Riefolo had allowed their policies to lapse in July 1973, July 1974 and April 1974 respectively, without giving the Board prior notice as required by section 28(f) of the General Conditions. Only Grove and possibly Conditioning4 had continued their coverage. Hartford then notified the contractors and their sureties of its intention to assert claims against them.

On April 11, 1975, Hartford brought suit in Superior Court, Chancery Division, to recover the monies it had paid to the Board which had in turn paid the contractors. The complaint named as defendants the five contractors, their sureties and the Board. Hartford alleged that the contractors had breached their agreements by failing to repair the fire damage at their own expense, and that all contractors except Grove were also in breach for failure to maintain builder’s risk insurance.

The defendant contractors claimed that an insurer could be subrogated only to tort and not to contract claims, and that therefore Hartford could not bring the present suit. They further asserted that Hartford was estopped from enforcing the right to subrogation due to its “inequitable” conduct following the fire.

In addition to these defenses, defendants challenged their underlying liability to the Board on numerous other grounds. [521]*521The contractors asserted that since either the “substantial completion” of the building or its occupancy by the Board at the time of the fire would have voided builder’s risk coverage, any failure to maintain such insurance did not injure the Board. By reason of the alleged unavailability of builder’s risk coverage, defendants claimed that a proper construction of the contract shifted the risk of loss to the Board.5 Alternatively, defendants urged that because the fire had started among cartons stored by the Board, it was responsible for the damage and must absorb the loss. The defendants also alleged that the Board had breached section 57 of the General Conditions by occupying the building without the written consent of either the contractors, their insurers or their sureties. It is alleged that such occupancy would have terminated the policies had they been in effect.

Defendant surety companies claimed that their performance bonds did not cover fire repairs. The pre-trial order provided that the sureties would not participate in the trial on the issue of the contractors’ liability, but would be free to litigate whether such liability, if established, was covered by the performance bonds.

The case was tried on a stipulated factual record. In an unreported opinion, the trial court held that Hartford could maintain the suit as the Board’s subrogee without any showing of “superior equities.” The court did not consider the claims of Hartford’s inequitable conduct.

On the merits, the court held that the provisions requiring the contractors to repair all damage should be read together with their obligation to maintain builder’s risk insurance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sompo Japan Insurance Co. of America v. Action Express, LLC
19 F. Supp. 3d 954 (C.D. California, 2014)
Fort Bragg Unified School District v. Colonial American Casualty & Surety Co.
194 Cal. App. 4th 891 (California Court of Appeal, 2011)
DeNike v. Cupo
926 A.2d 869 (New Jersey Superior Court App Division, 2007)
State Farm General Insurance v. Wells Fargo Bank
49 Cal. Rptr. 3d 785 (California Court of Appeal, 2006)
Solondz v. Kornmehl
721 A.2d 16 (New Jersey Superior Court App Division, 1998)
Schirmer-National Co. v. Director, Division of Taxation
17 N.J. Tax 495 (New Jersey Tax Court, 1998)
Howard Sav. Bank v. LIBERTY MUT.
667 A.2d 390 (New Jersey Superior Court App Division, 1995)
Matter of Liquidation of Integrity
657 A.2d 902 (New Jersey Superior Court App Division, 1995)
National Union Fire Insurance Co. of Pittsburgh v. Riggs National Bank of Washington
646 A.2d 966 (District of Columbia Court of Appeals, 1994)
Michele Matthews, Inc. v. Kroll & Tract
645 A.2d 798 (New Jersey Superior Court App Division, 1994)
Holloway v. State
593 A.2d 716 (Supreme Court of New Jersey, 1991)
Jonax v. Allstate Insurance
582 A.2d 1050 (New Jersey Superior Court App Division, 1990)
W v. Pangborne & Co. v. New Jersey Department of Transportation
562 A.2d 222 (Supreme Court of New Jersey, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
410 A.2d 658, 81 N.J. 514, 1980 N.J. LEXIS 1318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-fire-insurance-v-riefolo-construction-co-nj-1980.