Hartford Financial Services Group, Inc. v. Cleveland Public Library

168 F. App'x 26
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 31, 2006
Docket04-4415, 04-4508
StatusUnpublished
Cited by6 cases

This text of 168 F. App'x 26 (Hartford Financial Services Group, Inc. v. Cleveland Public Library) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Financial Services Group, Inc. v. Cleveland Public Library, 168 F. App'x 26 (6th Cir. 2006).

Opinion

ALICE M. BATCHELDER, Circuit Judge.

Cleveland Public Library (“CPL”) appeals the judgment entered after the jury returned a verdict in favor of Hartford Financial Services Group, Inc. (“Hartford”) in Hartford’s action seeking a declaratory judgment that Hartford was not obligated to provide insurance coverage for damage to CPL’s Main Building resulting from the construction of a new wing of the building in 1994. Hartford cross-appeals the district court’s refusal to grant it summary judgment on its suit-limitation defense to CPL’s counterclaims filed in this action. Athough the parties have raised multiple assignments of error, we will affirm the judgment on the basis of our conclusions that the district court did not err either in sending to the jury the issue of whether Hartford’s notice defense was waived or in refusing to grant a new trial on that issue, in finding that sufficient evidence supported the jury’s verdict that Hartford had not waived the notice defense, and in instructing the jury on the definition of “loss” and including a reference date in the instruction. Because we find no error in these particulars, we need not reach the remaining assignments of error in the appeal or the cross-appeal.

I. Factual and Procedural History

Hartford issued insurance policies to CPL in 1993 that provided coverage against “all risks of physical loss or damage, except as excluded, to covered property” and were intended to cover damage resulting from the construction of a new East Wing to the Main Building of the library. The original policy was effective in July 1993 and ran through July 1996; it was renewed for another three years when the original expired.

The construction of the new CPL wing, which commenced in 1994, required that an old building be demolished and the ground excavated to 17 feet below the water table. As part of the construction, soil directly adjacent to the Main Building was removed, and the excavation contractor constructed an “augercast pile wall” in order to prevent the soil underneath the Main Building from flowing into the excavated pit. However, in August 1994, soil seeped through the cracks in the wall and into the pit, which caused settling of the Main Building. CPL noticed damage to the building, but, considering the damage merely cosmetic, did not report it to Hartford.

In October 1994, CPL found large cracks in the Main Building and installed steel sheeting around the excavation site to prevent soil flows. This setup worked for a short time, but on December 20, 1994, work crews discovered a large tear in the sheeting, which had caused a large quantity of soil to flow from underneath the Main Building into the excavated pit. Athough this soil flow had caused new damage to the building, CPL estimated that the damage totaled less than its $100,000 deductible and did not notify Hartford.

After CPL’s contractors repaired the tear and pumped grout underneath the building to stabilize it, the building report *29 edly remained stable for several months. However, the building began to move again in July 1995, and CPL contacted Thomas Borror (“Borror”), its independent insurance consultant, to inquire whether it should notify Hartford about the damage. Borror evidently was surprised that it had not done so already and estimated that by that time the damage totaled approximately $500,000. CPL sent Hartford a written Notice of Loss on September 25, 1995, advising that the damage occurred on December 20, 1994, when workers found the rupture in the steel sheeting. On October 18, 1995, Hartford sent CPL a standard reservation of rights letter stating that CPL had put Hartford on notice of damage that occurred on or about December 23, 1994, and that it would make a determination of coverage when it finished investigating the matter.

Hartford hired a forensic engineer to examine the site and prepare a report. The engineer visited the site in October 1995 and found that construction had continued after the date of loss stated in the Notice of Loss and that the new wing had been constructed, making access to the evidence of the cause of the loss impossible. Hartford then requested a Proof of Loss and documentation of any claim that CPL was going to make for the cracks and damage to the architectural finishes.

CPL contends that it sent Hartford several notices regarding damage and repairs in the years that followed, and that additional information was provided in face-to-face meetings with Hartford representatives. CPL submitted a Proof of Loss in December 1998, when the repairs had been substantially completed. Hartford acknowledged receipt of the notice, but stated that it did not consider the notice to be a “formal claim filing” as required by the policy language.

CPL representatives met with Hartford representatives on April 15, 1999, and CPL presented Hartford with its Proof of Loss (which CPL considered to be an “amended proof of loss,” relating to the one sent in December 1998) and requested a $2.5 million advance on the claim payout. However, the April 15, 1999, Proof of Loss stated that some of the damage incurred had occurred in August 1994, as opposed to December 1994, the date CPL had originally given as the date of the initial damage. Based on this information, Hartford send CPL a letter on April 29, 1999, stating that the Proof of Loss presented “a far different claim than we were originally led to believe was involved in this matter,” inasmuch as the original notice stated that the onset date was in December 1994. Hartford acknowledged that, from January 1996 to April 1999, it intended to pay the claim once the repair costs were known, but that this intent was based on the assumption that the loss had begun in December 1994 when the, steel sheeting gave way, rather than in August 1994, when CPL first experienced problems with settling.

Hartford determined on July 15, 1999, that CPL’s claims were excluded from coverage by several policy exclusions and by CPL’s delay in providing notice and proof of loss and in filing suit. Hartford therefore denied the claim and filed this action in the district court, seeking a declaration that Hartford was not obligated to provide insurance coverage for damage arising from a construction project involving CPL’s Main Building. Hartford based this request on CPL’s failure to provide immediate notice of loss, failure to provide proof of loss, and failure to file suit within one year after inception of the loss. CPL counterclaimed for breach of contract, declaratory relief, bad faith, promissory estoppel, fraud, and negligent misrepresen *30 tation. Hartford denied those claims and raised defenses to them.

After the district court ruled on various motions to dismiss and for summary judgment, the remaining claims — Hartford’s claim for declaratory relief and CPL’s counterclaims for declaratory relief, breach of contract, negligent misrepresentation, promissory estoppel, and fraud' — • were tried to a jury. At the close of the evidence, the district court denied CPL’s motion for a directed verdict on the policy provisions, granted Hartford’s motion for judgment as a matter of law on CPL’s counterclaim for negligent misrepresentation, and denied all other motions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William Howe v. City of Akron
723 F.3d 651 (Sixth Circuit, 2013)
Ventas, Inc. v. HCP, INC.
647 F.3d 291 (Sixth Circuit, 2011)
Holbrook v. Shelter Insurance
186 F. App'x 618 (Sixth Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
168 F. App'x 26, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-financial-services-group-inc-v-cleveland-public-library-ca6-2006.