Hartford Accident & Indemnity Co. v. Boise Cascade Corp.

489 F. Supp. 855, 30 Fed. R. Serv. 2d 848, 1980 U.S. Dist. LEXIS 12931
CourtDistrict Court, N.D. Illinois
DecidedMay 9, 1980
Docket78 C 3721
StatusPublished
Cited by6 cases

This text of 489 F. Supp. 855 (Hartford Accident & Indemnity Co. v. Boise Cascade Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Accident & Indemnity Co. v. Boise Cascade Corp., 489 F. Supp. 855, 30 Fed. R. Serv. 2d 848, 1980 U.S. Dist. LEXIS 12931 (N.D. Ill. 1980).

Opinion

MEMORANDUM OPINION AND ORDER

ASPEN, District Judge:

This action arises out of the performance by plaintiff Hartford Accident and Indemnity Company (“Hartford”) of a construction contract with Boise Cascade Corporation (“Boise”). The undisputed facts are as follows. On July 17, 1974, Boise retained McCollough Construction Company (“McCollough”) to construct additions and improvements to Boise’s Corrugated Container Division manufacturing plant located in LaPorte, Indiana. The contract between Boise and McCollough specified that the construction was to be substantially complete by late March, 1975. As required by Boise, McCollough obtained a performance bond and a labor and material payment bond from Hartford. Pursuant to these bonds, Hartford assumed the role of a surety, guaranteeing that if McCollough defaulted on the contract, it either would remedy the default, complete the contract itself, or arrange for the completion of the contract by another contractor.

On April 22,1975, Boise formally notified Hartford that McCollough had defaulted on the construction contract and that it would hold Hartford liable in accordance with the performance bond. 1 Later, in the summer *857 of 1975, Hartford and Boise entered into a separate agreement with respect to completion of the project. Under the terms of this agreement, Hartford agreed to secure performance of all work not completed under the original contract. In return, Boise agreed to pay to Hartford the unpaid balance of the contract price as it became due under the terms of the original contract. The agreement expressly provided that except as amended, all terms and conditions of the original contract were to remain in full force and effect. In addition, the agreement reserved to Hartford and Boise any rights that each might have against the other under the original contract.

Thereafter, Hartford paid all valid claims of McCollough’s materialmen, procured the necessary labor and materials for completion of the LaPorte project, and in fact did secure the completion of that project. 2 Boise, however, has refused Hartford’s demand for payment of the remaining contract balance of $261,571.96. As a result, Hartford filed this diversity action seeking recovery of the sum due under the contract. Boise has counterclaimed, alleging that Hartford’s failure to secure completion of the construction project by the scheduled date of late March, 1975, has caused it to suffer losses totalling $560,842.44. Thus, Boise seeks recovery of this amount as offset by the amount due to Hartford for completion of the project.

The case now is before the Court on Hartford’s motion under Fed.R.Civ.P. 56(a) for summary judgment on its claim for payment of the contract balance. In addition, Hartford asks the Court to enter this ruling as a final judgment pursuant to Fed. R.Civ.P. 54(b). For the reasons that follow, the Court finds it appropriate to grant both of Hartford’s requests.

I. Summary Judgment

The Seventh Circuit has observed that “[w]ith the ever increasing burden upon the judiciary, persuasive reasons exist for the utilization of summary judgment procedure whenever appropriate.” Kirk v. Home Indemnity Co., 431 F.2d 554, 560 (7th Cir. 1970). The Court is mindful that it is not its function to resolve disputed issues of fact — particularly those which involve questions of motive or intent — in a trial by affidavit. Cedillo v. International Association of Bridge & Structural Iron Workers, Local Union No. 1, 603 F.2d 7, 10-11 (7th Cir. 1979). Nonetheless, it is the function of the Court to make a discerning inquiry into the allegations and supporting documentation to determine whether there are any factual disputes which require resolution by trial. Any doubts must be resolved against the moving party. Moutoux v. Gulling Auto Electric, Inc., 295 F.2d 573, 576 (7th Cir. 1961).

Applying these standards, the Court is satisfied that there remain in dispute no facts material to Hartford’s claim. Boise does not dispute Hartford’s allegations that it completed the construction project at LaPorte, and that there remains an outstanding contract balance of $261,571.96. Indeed, the prayer for relief in Boise’s counterclaim explicitly recognizes that any recovery it obtains thereunder will be diminished by the amount it owes to Hartford. Boise, however, seeks to defeat the motion for summary judgment by construing Hartford’s right to payment upon completion as subject to any claims against Hartford or McCollough.

Under Indiana law, however, 3 the construction of a written contract is a ques *858 tion of law rather than one of fact. McGann & Marsh Company, Inc. v. K. & F. Mfg. Co., 385 N.E.2d 1183, 1187 (3d Dist., Ind.App.1979); Kleen Leen, Inc. v. Mylcraine, 369 N.E.2d 638, 640 (1st Dist., Ind. App. 1978). Only where the Court determines that the contract is ambiguous in that certain terms are susceptible of more than one reasonable interpretation is a question of fact raised. Mylcraine, 369 N.E.2d at 641. In support of its position, Boise cites to the provisions of its agreement with Hartford which reserve any claims under the original contract and which incorporate the provisions of the original contract. The Court, however, finds no ambiguity in either the agreement between Hartford and Boise or the original contract which it incorporates by reference. Boise can point to no clause of the original contract which in any way suggests that Hartford’s right to payment upon completion is conditional upon completion of the project within the specified time period. The clause which establishes the projected completion date is silent as to any such contingency. Moreover, Article 4 of the original contract provides for insertion of any “provisions for liquidated damages relating to failure to complete [the project] on time.” Yet, no such provisions were inserted. 4 Indeed, Boise’s inability to make specific reference to any points of ambiguity in the original contract is eloquent testimony to the clarity of the contract.

Although Boise now might wish otherwise, the Court believes it clear that the various agreements between Boise and Cascade do not condition Hartford’s right to payment on its completion of the project within the specified time period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
489 F. Supp. 855, 30 Fed. R. Serv. 2d 848, 1980 U.S. Dist. LEXIS 12931, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-accident-indemnity-co-v-boise-cascade-corp-ilnd-1980.