Harrison v. Hartford Fire Ins.

67 F. 298, 1894 U.S. App. LEXIS 3179
U.S. Circuit Court for the Southern District of Iowa·Decided December 4, 1894·No. No. 271·Published·Cited by 6 cases

Opinion

WOOLSON, District Judge.

Can tbe present action be maintained, under tbe clause in tbe policy generally known as tbe limita-, [299] lion clause or condition? This is the only question to be decided on ihis hearing. The clause is valid and upheld by the courts. O’Laughlin v. Insurance Co., 3 McCrary, 543,11 Fed. 280; Insurance Co. v. Stanchfield, 1 Dill. 424, Fed. Cas. No. 6,660; Riddlesbarger v. Insurance Co., 7 Wall. 386. The fire occurred October 4,1892. The petition herein was filed on May 29,1894. If this clause be literally and strictly applied to these dates, manifestly this action is barred, and cannot be maintained. On the argument, as in the petition, this ir, substantially confessed by counsel for plaintiff; and there, as here, the attempt is made to avoid the force of this conclusion by reference to a former action instituted on the policy in suit. Such former action, was pending in this court. Upon January 20, 1894, in mi action brought on this policy, and wherein the present plaintiff sought to recmrer thereon from the defendant company for the loss herein complained of, Oils court directed a verdict for the defendant. 59 Fed. 732. The court found, from the uncontradicted evidence submitted therein, that plain ¡.iff, contrary to the terms of the Iowa statute (section 1734, McClain’s Iowa Code), had begun his action Avithin 90 days after proofs of loss had been Avaived by defendant. Wo proofs of loss had been furnished. The action thus determined by direction of the court, solely because of Us having been prematurely brought, Avas begun January 16,1893.

Section 3712, McClain’s Iowa Code, is as follows:

“lí, after the commencement of an action, the plaintiff fail therein for any cause except negligence in its prosecution, anil a now suit be brought within six months thereafter, the second suit shall, for the purposes herein contemplated, be deemed a continuation of the first.”

Plaintiff’s contention is that this section entitles the maintenance of the present action, notwithstanding the contract limitation clause. The reasoning is that the said former suit failed, but not for negligence in its prosecution; that the present is a new suit, brought within six months after the failure of the former action; and that this suit is therefore a continuation of the first action; consequently, it is, in contemplation of laAV, begun within the 12-months period named in the policy. To what extent, if at all, does this section apply to the pending action?

The supreme court of the United States had occasion to consider a statute of the state of Missouri which tended in the same general direction, viz. granting the exceptional right, notwithstanding the general statutes of limitation of that state, to maintain an action which but for this exception would have been barred. This Missouri statute allowed a party wiio “suffers a nonsuit” in an action to bring a new action for the same cause, within one year afterwards. In Riddlesbarger v. Insurance Co., 7 Wall. 396, the policy contained a clause which required suit to be brought, if at all, within 12 months from loss. The supreme court, in considering the question of the applicability of this statute, last stated, to the contract clause in the policy therein in suit, declare:

“The rights of the parties flow from the contract. That relieves them from the general limitations of the statute, and, as a consequence, from its exceptions also.”

[300] The subsequent language of the opinion just quoted is, perhaps, yet stronger. Having called attention to the fact that the Missouri statute was applicable only to cases of involuntary nonsuit, the court declare, as to the limitation claus'e in the contract or policy:

“The action mentioned, which must he commenced within twelve months, is the one which is prosecuted to judgment. The failure of a previous action from any source cannot alter the case. The contract declares that an action shall not be sustained unless such action—not some previous action—shall be commenced within the period designated.”

In O’Laughlin v. Insurance Co., 3 McCrary, 543, 11 Fed. 280, Circuit Judge McCrary, in an action involving the same statute, applies and follows the Riddlesbarger Case, the policy involved containing a like contract-limitation clause. When the circuit judge of this circuit thus closely follows and applies the ruling of the supreme court, there would seem little opportunity for our dissent. Yet, using the language of Judge McCrary in the case just cited, “I have not much sympathy with this sort of a defense in a suit of this kind;” and especially under the circumstances disclosed herein by the allegations of the petition. The former action was decided adversely to plaintiff because brought too soon; and we are now asked to decide this action against plaintiff, because, as claimed, it is brought too late. There appears no evidence of laches on part of plaintiff in bringing this suit. But, as said by the learned circuit judge in the O’Laughlin Case, supra, the Riddlesbarger Case furnishes “the law which must be administered here,” unless its force can be broken by showing that it is not here applicable. If the language of the Missouri and Iowa statutes on this point were identical, the case would be here closed.

But plaintiff calls special attention to the fact that the Iowa statute is peculiarly dissimilar in phraseology, in that it declares that the “new suit,” if brought within six months from the failure of the former, action, is to be “deemed a continuation of the first”; and the contention, therefore, is that the argument in the Riddlesbarger and O’Laughlin Cases does not apply, because in the case at bar, the “action commenced,” to wit, “the one which is to be prosecuted to judgment,” was commenced within the 12 months of the limitation clause; therefore, per force of the statute, it is the continuation of the suit actually1 commenced within such 12 months; and thus the contract clause is met. But it may well be asked, if the new suitis thus to be regarded as having been commenced at the time of the original suit, do we not face the same difficulty which presented itself in the old suit? 59 Fed. 732. Roes not this argument and application bring us, of necessity, to fix the commencement of this action as within the 90 days after waiver of proofs of loss, and therefore as violating the statute which prohibits the action from being commenced within such 90 days? If, for purpose of fixing the commencement within the 12-months contract limitation clause, the new suit is a continuation of the old suit, and was thus commenced within the pendency of that suit, how can we escape the conclusion that its commencement must be the commencement of the old suit? And must not the doctrine which,—applied to the old suit compelled judgment [301] against plaintiff—-be applied here, with no less disastrous effect, on plaintiff’s present action?

Free access — add to your briefcase to read the full text and ask questions with AI

Harrison v. Hartford Fire Ins., 67 F. 298, 1894 U.S. App. LEXIS 3179 (circtsdia 1894).

67 F. 298 (Harrison v. Hartford Fire Ins.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Green v. Peoples Benev. Industrial Life Ins. Co.
5 So. 2d 916 (Louisiana Court of Appeal, 1941)
Ray v. Liberty Industrial Life Ins. Co.
180 So. 855 (Louisiana Court of Appeal, 1938)
Vulcanite Roofing Co. v. Commonwealth S. S. Co.
275 F. 961 (E.D. Virginia, 1921)
Tracy v. Queen City Fire Ins.
61 So. 687 (Supreme Court of Louisiana, 1913)
Hartzell v. Maryland Casualty Co.
163 Ill. App. 221 (Appellate Court of Illinois, 1911)
Matthews v. American Central Insurance
75 N.Y. St. Rep. 716 (Appellate Division of the Supreme Court of New York, 1896)