Harris v. American Surety Co.

24 N.E.2d 42, 372 Ill. 361
Illinois Supreme Court·Decided October 10, 1939·No. No. 25027. Reversed and remanded.)·Published·Cited by 14 cases

Opinion

Mr. Justice Jones

delivered the opinion of the court:

■ This is a suit instituted for the use of a sub-contractor, the Otis Elevator Company, to recover on a surety bond executed to secure the performance of a construction contract entered into between the nominal plaintiffs, Eleanor Davis Harris and others, and the principal contractor, the Good Construction Company. The question presented is whether recovery may be had for the use of the sub-contractor, though he is not a party to either the main contract or the surety bond. The bond and the contract which it secured were executed and were to be performed in the State of Pennsylvania. ' The circuit court sustained a motion to strike the amended complaint and entered judgment for the defendant. The judgment was affirmed by the Appellate Court for the First District and the cause is here on leave granted to appeal.

The facts are not in dispute. The Good Construction Company, as general contractor, entered into a written agreement with the nominal plaintiff for the furnishing of all material and labor and the construction of a building at McKeesport, Pennsylvania, including a freight elevator and appurtenances, in accordance with certain plans and specifications. A contemporaneous supplement, forming part of the original agreement, provides that the contractor shall furnish a surety bond in the sum of $45,000, in form satisfactory to the owners, to guarantee the faithful performance of the contract; that, in accordance with the Pennsylvania statute of 1901, providing for lien waiver by contract, neither the contractor nor any subcontractor, materialman or other person shall file or maintain any lien commonly called a mechanic’s lien for work done or material furnished; and that the contractor shall keep the building and premises free from liens, and indemnify the owner from any costs, expenses, attorney’s fees, loss or damage resulting from the filing of any such lien. A bond, containing numerous conditions, with the Good Construction Company as principal and appellee as surety, was furnished. The general contractor thereafter entered into a contract with Otis Elevator Company for the furnishing and installation of the elevator, which was accordingly installed. Payment in full was not made as contracted for, and this suit was instituted to recover the unpaid balance due.

The bond contains five conditions which are important to be noticed, — i. e.: (1) That the principal shall erect and complete the building in accordance with the terms of the agreement, and in all respects faithfully perform all the obligations of the principal under the agreement, (2) “and shall satisfy all claims and demands incurred for the same,” (3) and shall fully indemnify and save harmless the owners from all costs and damage which the owners may suffer by reason of the failure of the principal so to do, (4) and shall fully reimburse and repay the owners all outlay and expense which the owners may suffer by reason of the failure of the principal so to do, (5) and shall fully reimburse and repay the owners all outlay and expense which the owners may incur in making good any such default.

The construction contract and bond were made in the State of Pennsylvania. The building was erected in that State. The general contractor is a Pennsylvania corporation. The Otis Elevator Company and the defendant surety company are authorized to do business in that State. Appellants predicate their right to recover upon the second condition of the bond, in connection with the.construction contract, which is by the terms of the bond made a part thereof.

The validity, construction and obligation of a contract must be determined by the law of the place where it is made or is to be performed. The law of the place becomes a part of the contract, and courts of another jurisdiction will so interpret its legal effect. (Frankel v. Allied Mills, Inc. 369 Ill. 578; Walker v. Lovitt, 250 id. 543.) The motion to strike avers that the complaint shows there is no privity between the defendant and the plaintiff for use, and that the bond is one of indemnity protecting the obligees only and does not give any right of action to third parties under the law. This averment is sufficient to raise an issue on the question of whether the law of Pennsylvania precludes a recovery.

The earlier decisions of the Supreme Court of Pennsylvania laid down the rule that the law of that State did not permit a recovery upon a bond or contract by or for the use of a third person to which he was not a party, except (1) where one of the parties agreed with the other to pay money or deliver some valuable thing to a third party who was the only one interested in the payment or delivery; (2) where the promise to pay the debt of a third person rested upon the fact that money or property was placed in the hands of the promissor for that purpose; and (3) where one bought the stock of a tradesman and agreed to take the place, fill the contracts, and pay the debts of the vendor. (First Methodist Fpiscopal Church v. Isenberg, 246 Pa. 221; Greene County v. Southern Surety Co. 292 id. 304.) These and other similar holdings were abrogated by later decisions in which the Pennsylvania court adopted the rule hereinafter quoted enunciated by Professor Corbin of the Yale Law School in 38 Yale Law Journal 1. (Concrete Products Co. v. United States Fidelity and Guaranty Co., 310 Pa. 158; Commonwealth v. Great American Indemnity Co. 312 id. 183; McClelland v. New Amsterdam Casualty Co. 322 id. 429.) In the McClelland case it is pointed out that the Great American Indemnity Co. case overrules Greene County v. Southern Surety Co. supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Harris v. American Surety Co., 24 N.E.2d 42, 372 Ill. 361 (Ill. 1939).

24 N.E.2d 42 (Harris v. American Surety Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Progressive Insurance Company v. Williams
Appellate Court of Illinois, 2008
Progressive Insurance v. Williams
884 N.E.2d 735 (Appellate Court of Illinois, 2008)
Hall v. Merck, Sharp & Dohme
774 F. Supp. 601 (D. Kansas, 1991)
Associated Indemnity Co. v. Insurance Co. of North America
386 N.E.2d 529 (Appellate Court of Illinois, 1979)
Harrison v. State Bank of Hull
138 N.E.2d 41 (Appellate Court of Illinois, 1976)
Hartford Accident and Indemnity Co. v. Crider
392 F. Supp. 162 (N.D. Illinois, 1974)
Avco Delta Corp. Canada Ltd. v. United States
484 F.2d 692 (Second Circuit, 1973)
Klondike Helicopters, Ltd. v. Fairchild Hiller Corp.
334 F. Supp. 890 (N.D. Illinois, 1971)
Ryan v. Napier
252 F. Supp. 730 (N.D. Illinois, 1966)
O'MEARA v. Texas Gas Transmission Corp.
230 F. Supp. 788 (N.D. Illinois, 1964)
Hardman v. Helene Curtis Industries, Inc.
198 N.E.2d 681 (Appellate Court of Illinois, 1964)
Otis Elevator Co. v. American Surety Co. of New York
41 N.E.2d 987 (Appellate Court of Illinois, 1942)
Board of Education v. Aetna Casualty & Surety Co.
27 N.E.2d 337 (Appellate Court of Illinois, 1940)