Harold Lee v. Dwp General Contracting, Inc.

CourtCourt of Appeals of Washington
DecidedJune 16, 2020
Docket53290-5
StatusUnpublished

This text of Harold Lee v. Dwp General Contracting, Inc. (Harold Lee v. Dwp General Contracting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harold Lee v. Dwp General Contracting, Inc., (Wash. Ct. App. 2020).

Opinion

Filed Washington State Court of Appeals Division Two

June 16, 2020

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II HAROLD LEE, an individual, No. 53290-5-II

Respondent,

v. UNPUBLISHED OPINION

DWP GENERAL CONTRACTING, INC., a Washington Corporation,

Appellant.

MAXA, J. – DWP General Contracting, Inc. (DWP) appeals the trial court’s order denying

its motion for a new trial under CR 59(a) or remittitur under RCW 4.76.030 in a breach of

contract action. DWP entered a contract with Harold Lee to build apartments and townhomes on

Lee’s property, but DWP failed to complete the project until 14 months after the agreed upon

completion date. Lee filed suit against DWP. A jury rendered a verdict for Lee, including a

$323,195 award for lost profits. The trial court denied DWP’s motion for a new trial or

remittitur based on the size of the lost profit award.

DWP argues that the trial court erred in denying its motion for a new trial or remittitur

because the lost profits the jury awarded did not include a deduction for Lee’s mortgage

payments and all property taxes and insurance. We hold that the lost profits award was not

improper or excessive because expert testimony supported the amount of the lost profits award. No. 53290-5-II

Accordingly, we affirm the trial court’s order denying DWP’s motion for a new trial or

remittitur.

FACTS

In July 2015, Lee contracted with DWP to construct apartments and townhomes on

property he owned in Vancouver, Washington. Lee intended to generate income from the rental

of the apartments and townhouses. He financed the project through a construction loan, which

he planned to convert to a permanent loan when the buildings were completed.

In the contract, DWP promised to complete the project within 180 days of starting

construction (by March 2016). DWP did not complete the project until June 2017, 14 months

after the agreed upon completion date. Lee sued DWP for breach of contract, seeking damages

for the profits he lost because of the delay in the completion of the project as well as other

damages.

At trial, Lee called as an expert witness Laura Markee, a chartered financial analyst and

business appraiser, to testify regarding the amount of his lost profits. Markee also prepared a

written opinion admitted as an exhibit at trial that outlined the damages caused by the

construction delay, including Lee’s lost profits.

Markee’s report detailed her calculation of Lee’s lost profits. To do so, Markee

calculated the average monthly rental income for a test period (September 2017 to May 2018).

She then adjusted the average monthly rental income downward to reflect the fact that rental

rates had increased by 4.4 percent between 2016 and 2017. She then subtracted the average

monthly variable operating expenses for the same time period. The resulting amount was the

average monthly lost profits. She multiplied the average monthly lost profits by 14 months, the

duration of the delay, to derive her unadjusted lost profit total.

2 No. 53290-5-II

Markee made two further adjustments to the lost profit total. First, she reduced the lost

profits to reflect the fact that the delay period was shorter for the two townhomes than it was for

the rest of the project. Second, she reduced the lost profits to reflect the fact that the property

taxes increased once the project was completed. This resulted in her final opinion of lost profits

in the amount of $323,195.

DWP did not present any testimony regarding the calculation of Lee’s lost profits.

Instead, in a vigorous cross-examination, DWP advocated for a contrary position and attempted

to discredit Markee’s opinions.

On cross-examination, Markee acknowledged that her calculation of Lee’s average

variable expenses for September 2017 to May 2018 changed from $8,208 in her initial report to

$7,696 in the report she finalized for her trial testimony. The difference was due to her removal

of monthly flood insurance payments of $511 from her calculation of monthly variable expenses

in the latter report. Markee explained that flood insurance was a fixed expense and therefore had

to be removed from monthly variable expenses.

Markee confirmed that she adjusted her calculation of Lee’s lost profits to reflect a

property tax savings of $12,747 for the period of March 2016 (the contractual date of

completion) to June 2017 (the actual date of completion). Lee would have had to pay the

additional $12,747 in property taxes if the project had been completed on time, but because there

was no finished building in March 2016, Lee was not required to pay the additional property tax.

Markee subtracted the $12,747 in property tax savings from Lee’s lost profits.

Markee disagreed that the mortgage payments Lee made on the permanent loan once the

building was complete were variable operating expenses that should be deducted from the total

lost profits. She emphasized that financing was a fixed cost that did not depend on the

3 No. 53290-5-II

completion of the project. “[T]he financing and . . . the loan payments are going to happen

regardless of whether or not you have revenues.” Clerk’s Papers (CP) at 118:14. Lee was

making payments on the construction loan before the project was completed. Markee stated that

interest and payments on financing debt are not considered in lost profit calculations because

financing is a matter of personal choice. If financing was considered in lost profits, plaintiffs

whose financing was more expensive would have smaller lost profits, even if all other variables

were equal.

On redirect examination, Markee confirmed her opinion that her calculation of $323,195

in lost profits was correct.

At the conclusion of the evidence, the trial court instructed the jury regarding the measure

of damages for Lee’s breach of contract claim. The jury was instructed that

In calculating the plaintiff’s actual damages, you should determine the sum of money that will put the plaintiff in as good a position as he would have been in if both plaintiff and defendant had performed all of their promises under the contract.

In this case Harold Lee claims lost profits. Harold Lee’s damages may include net profits if Harold Lee proves with reasonable certainty that net profits would have been earned, but were not earned because of the breach of DWP General Contracting, Inc.

CP at 77.

The court also gave the following instruction regarding expert testimony:

A witness who has special training, education, or experience may be allowed to express an opinion in addition to giving testimony as to facts.

You are not, however, required to accept his or her opinion. To determine the credibility and weight to be given to this type of evidence, you may consider, among other things, the education, training, experience, knowledge, and ability of the witness. You may also consider the reasons given for the opinion and the sources of his or her information, as well as considering the factors already given to you for evaluating the testimony of any other witness.

CP at 68.

4 No. 53290-5-II

The jury awarded Lee $323,195 in lost profits, the same amount provided in Markee’s

testimony and report.

DWP moved the court for a new trial under CR 59(a) or, in the alternative, for a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. O'CONNELL
523 P.2d 872 (Washington Supreme Court, 1974)
Burnside v. Simpson Paper Co.
864 P.2d 937 (Washington Supreme Court, 1994)
Coast Trading Co. v. Parmac, Inc.
587 P.2d 1071 (Court of Appeals of Washington, 1978)
Bunch v. KING COUNTY DEPT. OF YOUTH SERV.
116 P.3d 381 (Washington Supreme Court, 2005)
Collins v. CLARK COUNTY FIRE DIST. NO. 5
231 P.3d 1211 (Court of Appeals of Washington, 2010)
Bunch v. King County Department of Youth Services
155 Wash. 2d 165 (Washington Supreme Court, 2005)
Millies v. LandAmerica Transnation
372 P.3d 111 (Washington Supreme Court, 2016)
Collins v. Clark County Fire District No. 5
231 P.3d 1211 (Court of Appeals of Washington, 2010)
Mutual of Enumclaw Insurance v. Gregg Roofing, Inc.
315 P.3d 1143 (Court of Appeals of Washington, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Harold Lee v. Dwp General Contracting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/harold-lee-v-dwp-general-contracting-inc-washctapp-2020.