Harnett Co. v. New York State Thruway Authority

3 Misc. 2d 257, 155 N.Y.S.2d 100, 1956 N.Y. Misc. LEXIS 1661
CourtNew York Court of Claims
DecidedAugust 2, 1956
DocketClaim No. 33095
StatusPublished
Cited by3 cases

This text of 3 Misc. 2d 257 (Harnett Co. v. New York State Thruway Authority) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harnett Co. v. New York State Thruway Authority, 3 Misc. 2d 257, 155 N.Y.S.2d 100, 1956 N.Y. Misc. LEXIS 1661 (N.Y. Super. Ct. 1956).

Opinion

Charles Lambiase, J.

By contract dated May 7, 1954 executed by claimant corporation on May 7, 1954 and by the New York State Thruway Authority, hereinafter referred to as the Authority ”, by its chairman on June 2, 1954, being Contract No.— Specification No. 18642, claimant agreed to [258]*258furnish the material and perform the labor required and necessary for construction work, New York State Thruway Authority, for temporary Restaurant Facilities, as shown on the drawings or specified at ROUTE 98 INTERCHANGE (BATAVIA, N. Y.), ROUTE 21 INTERCHANGE (MANCHESTER, N. Y.) AND ROUTE 11 INTERCHANGE (E. SYRACUSE, N. Y.) in accordance with Specification No. 18642 and the following addenda No. 1 dated April 8,1954 No. 2 dated April 12, 1954 ”, and the New York State Thruway Authority agreed to pay therefor.

The construction was accepted by the Authority, and under the final estimate of the quantities of materials 'furnished and work performed prepared by it, the said Authority conceded that there was due to claimant under said contract the sum of $7,764.54, which amount it tendered to claimant. The payment was rejected by claimant on or about January 18, 1955, and the check in said amount was duly returned to the Authority for the reason that it failed to include an item of $9,760 claimed to be due and owing to claimant as is hereinafter more particularly set forth.

The claim alleges that:

“ 7. During the performance of that part of the contract pertaining to the Route 98 interchange at Batavia, New York, said New York State Thruway Authority, acting through its engineers and agents in charge, wrongfully compelled claimant, over its protest, to clear and grub the premises and to remove trees and stumps, which clearing, grubbing, and removal of trees and stumps was not provided for or contemplated by claimant’s contract, whereby claimant performed extra and additional labor and expended materials of the reasonable cost and value of Twenty-seven Thousand Six Hundred Eighty-seven Dollars ($27,687.00), no part of which was allowed or paid for, except the sum of Seventeen Thousand Nine Hundred Twenty-seven Dollars ($17,927.00) which was allowed to claimant in the amount of Seventeen Thousand Nine Hundred Twenty-seven Dollars ($17,927.00) in partial reimbursement for the extra work required to raise the site at the Batavia project to the levels indicated as existing grades on the contract drawing on the Batavia site plan.
“ 8. That claimant has not been reimbursed in full for the extra and additional labor and materials expended in the work required to raise the site at the Batavia project to the levels indicated as existing grades in the contract drawing covering the site plan at the Batavia site. That the value of the extra and additional labor and materials to raise the site at the [259]*259Batavia project to the levels indicated as existing grades on the contract drawing covering the site plan at the Batavia project for which claimant has not been reimbursed or compensated for is Nine Thousand Seven Hundred Sixty Dollars ($9,760.00).”

The cause of action in the sum of $7,764.54 with interest thereon from January 18, 1955 alleged in paragraph 4 of the claim is not before us, except as hereinafter mentioned, the same by order of this court (Major, J.) having been severed and having been heretofore brought on and heard before Honorable Charles T. Major aforesaid who, having heard the proofs and allegations of the parties, did on August 26, 1955 render a decision in which he awarded thereon the sum of $7,764.54, reserving by stipulation of the parties until the final determination of the balance of the claim the question of interest alleged to be due and owing on said sum. Judgment was entered pursuant to said decision and has been satisfied by payment. It is provided in said judgment, among other things, that the payment of said judgment and the acceptance of said payment by claimant is without prejudice to claimant’s right to prosecute the remainder of its claim with respect to the moneys claimed to be due it as set forth in paragraphs five through eight inclusive of the claim herein, and to claimant’s right to litigate the question of interest on the amount of the severed portion of the claim both of which questions we now pass upon.

The cause of action wherein and whereby $9,760 is claimed to be due and owing the claimant, involves the removal of approximately 700 or 800 trees, ranging in diameter from 10 to 36 inches, and of undergrowth from approximately three acres of the afore-mentioned Batavia, New York, contract site. No other contract site mentioned in the contract is involved in connection with said cause of action.

Claimant was awarded the contract in April, 1954. Claimant’s president thereafter and on or about April 26,1954 visited the Batavia, New York, contract site at which time the contract had not been signed by the parties and no work had been done by claimant thereunder at any of the contract sites. Its grade or elevation was three to four feet below what was shown as the existing grade on Drawing 101, Exhibit 4, which drawing is listed on the bottom of the outside cover on Exhibit 3 and is part of the contract papers. An area on said drawing, bearing the legend “ EXISTING DIET EOAD TO BE COVERED WITH 9" of GRAVEL ”, and purportedly 30 feet wide and 200 feet long, contained no such road. About three acres of the [260]*260site of which the existing dirt road area was a part was swampy, contained muck, undergrowth and trees, the last mentioned being some 700 or 800 in number and of the size herein-before set forth.

On April 28, 1954 and two days after claimant’s president had visited the Batavia, New York, contract site, claimant was directed by telephone by the Authority to and did commence work under the contract which it did at the other contract sites doing no work, however, at the Batavia, New York, contract site until June 10, 1954 as hereinafter set forth. The parties had not as yet executed the contract when claimant was thus ordered to commence work, but its bid had been accepted. Time was of the essence of the contract and, in fact, claimant was required to and was given permission to work its crews overtime. (Addendum No. 1, Exhibit 3.)

Following the visit of claimant’s president to the Batavia, New York, site, claimant was in communication with the Authority, its officers and employees, with reference to the situation and condition which he had found at said contract site. Correspondence passed between him and the Authority represented by its chairman and at times by the architect of the State of New York, following which claimant was furnished by the Bochester district engineer’s office of the Department of Public Works of the State of New York on behalf of said Authority a typewritten paper containing estimates for site preparation work at Batavia, New York, to be done by claimant as an extra and under a supplemental agreement. This paper set forth quantities and costs for muck removal and for muck replacement, and for fill and for clearing and grubbing-, and claimant was instructed to submit its proposal for the performance of said items.

Claimant on June 1, 1954 submitted its proposal for site preparation work at the Batavia, New York, contract site on the basis of the items included in the paper which had been furnished it as aforesaid; and on June 4, 1954 it was advised that the proposal, insofar as it affected removal and replacement of muck, and placement of fill was approved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cities Service Company v. Gardinier, Inc.
344 A.2d 254 (Superior Court of Delaware, 1975)
D. W. Winkelman Co. v. State
17 Misc. 2d 418 (New York State Court of Claims, 1959)
Caliendo v. McFarland
13 Misc. 2d 183 (New York Supreme Court, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
3 Misc. 2d 257, 155 N.Y.S.2d 100, 1956 N.Y. Misc. LEXIS 1661, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harnett-co-v-new-york-state-thruway-authority-nyclaimsct-1956.