John J. Harvey Co. v. State

207 Misc. 1116, 141 N.Y.S.2d 417, 1955 N.Y. Misc. LEXIS 2536
New York Court of Claims·Decided April 20, 1955·No. Claim No. 32550·Published·Cited by 1 cases

Opinion

Lambíase, J.

On or about December 3,1952, claimant entered into a contract with the State of New York acting by and through the Department of Public Works to furnish all work, labor and services and material of every kind and to do and perform each and every act and thing necessary or proper for the Resurfacing with Wrought Iron Plates the Chamber Walls of Lock 17 in the City of Little Falls, Herkimer County, New York, in accordance with the plans and specifications for said work hereto annexed and forming a part hereof, and to fully complete said improvement in accordance with the true intent and meaning of said plans and specifications ”. (Exh. 5, Memorandum of Agreement ”, constituting contract M-52-2.)

One of the items under the contract designated Item No. 30Y ” is entitled “ Wrought Iron Plates ”. (Exh. 5, Special Specifications, pp. 30-31; Optional Proposal No. 1, p. 3-D.) Claimant bid a unit price of twenty-seven cents per lb. for this item, and payment thereunder constitutes one portion of the claim which, for the purposes of convenience, we shall herein[1118] after designate as claimant’s first cause of action. (Claim, par. 4.) The pertinent parts of Item No. 30Y are set out in the aforesaid special specifications as follows:

“ ITEM NO. 30Y Wrought Iron Plates
(a) Work. Under this item the contractor shall furnish and place Wrought Iron Plates and %" Wrought Iron Butt Straps of the sizes shown on the contract plans and to the lines and grades shown or as ordered by the engineer. The plates shall be continuously welded to both vertical and horizontal butt straps so as to provide a watertight covering. All welding shall conform to the requirements of the current specifications of the' American Welding Society for Welded Highway and Railway Bridges.
“ (b) * * *
“ (c) * * *
“ (d) * * *
“ (e) * * *
“ (f) Measurement and Payment. The quantity to be paid for under this item will be the number of pounds furnished and placed in accordance with the plans and specifications. The unit price bid shall include the cost of furnishing all labor, materials, equipment, welding, etc. necessary to complete the work.”

In computing by weight the quantities for which payment was made under Item No. 30Y, the State of New York refused to include in its computation 15,000 pounds of welding rods which had been used to fasten the plates to the chamber walls of the lock. Claimant contends that the welding rods were materials furnished under Item No. 30Y; that they were incorporated into the job; and that payment therefor on weight basis should be allowed under this item. The State of New York, on the other hand, while not controverting the amount of welding rods furnished, contends that this part of claimant’s claim should be dismissed, because the payment clause for Item No. 30Y, subdivision (f) (supra), provides that the unit price bid per pound of wrought-iron plates includes the cost of furnishing “ all labor, materials, equipment, welding, etc. necessary to complete the work ”, and that, therefore, claimant was paid for these welding rods when it was paid by weight for the wrought-iron plates.

The second part of the claim which, for the purposes of convenience, we now designate and we shall hereinafter refer to as claimant’s second cause of action, arises out of certain alleged [1119] extra and additional work which claimant alleges it was required to do and which it did perform under protest and for which it received no additional compensation from the State of New York. (Claim, par. 5.) In connection, therewith claimant contends that it completed all of the work called for under the contract in May, 1953, and that thereafter the work was accepted by the State of New York and a final estimate (Exh. 7a) was prepared and sent to the claimant for signature. Claimant signed this estimate and returned it to the State of New York and then waited for payment in accordance therewith. Payment under this final estimate was not made. Furthermore, while claimant was waiting for payment and in September, 1953, it was called back to the job site and was directed by the State of New York to repair certain leaks which had developed. It is this work that claimant asserts is extra and additional and which the State of New York maintains was not additional or extra work but was contract work which was required to be done to meet the specifications of Item No. 30Y which require continuous welding to provide “ a watertight covering ”.

The last part of the claim, which for the purposes of convenience we designate and shall refer to hereinafter as claimant’s third cause of action, alleges in paragraph 6 as follows: 6. That claimant completed said contract on or about September, 1953, and thereafter the State of New York prepared and submitted to claimant its final estimate, wherein it included all quantities of work performed and materials placed at contract unit prices, except the items erroneously or wrongfully omitted therefrom, and set forth and conceded there remained a final balance due and payable to claimant under the terms of the contract in the sum of $9,681.85, which estimate claimant signed under protest and reservation of right to file this claim. Claimant claims herein from the State of New York the sum of $9,681.85, with interest thereon in addition to all other claims herein.” Said cause of action is not before us, however, for a motion having been made by claimant at the close of the trial of this claim to treat as severed said cause of action and for a partial judgment in the sum thereof, to wit: $9,681.85, concededly due claimant from the State of New York, and said motion having been duly granted after proof had been received in relation to the allegations thereof, and the parties having stipulated that so much of said cause of action as prays that interest be awarded upon said sum of $9,681.85 be held in abeyance, this court directed what amounts to a consent judgment in favor of the claimant and against the State of New York on said cause of [1120] action in the sum of $9,681.85. The payment and receipt of said sum, however, was without prejudice to claimant’s right to have its claim for interest on said sum heard and determined at the time of the determination of the remaining causes of action set up in the claim which question and remaining causes of action we pass upon herein.

Free access — add to your briefcase to read the full text and ask questions with AI

John J. Harvey Co. v. State, 207 Misc. 1116, 141 N.Y.S.2d 417, 1955 N.Y. Misc. LEXIS 2536 (N.Y. Super. Ct. 1955).

207 Misc. 1116 (John J. Harvey Co. v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harnett Co. v. New York State Thruway Authority
3 Misc. 2d 257 (New York State Court of Claims, 1956)